Project KS ftfw kirw 14(1), 104(1) the project consists of roadway reconditioning, aggregate base, riprap installation, large pipe culvert replacement, ditch reconditioning, signing and other…

Ended Definitive Contract Awarded Last action

Contract number
693C7320C000021
Awardee
Awarding agency
Obligated
$1,747,150

Award facts

Opportunity
Contract value 100% obligated
$1,747,150.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Kensington, KS 66951, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00005 · The purpose of this no cost administrative modification is to financially and contractually close this contract in the amount of $1,747,150.00. $0
Funding Only Action P00004 · KS ftfw kirw 14(1), 104(1) CM #4 no change to contract amount no change to contract time finalize the existing quantities $0
Other Administrative Action P00003 · KS ftfw kirw 14(1) 104(1) CM# 3 no change to contract amount no change to contract time extend period of performance to january 31, 2023 $0
Funding Only Action P00002 · KS ftfw kirw 14(1) 104(1) CM# 2 no change to contract amount extend contract by 75 calendar days $0
Funding Only Action P00001 · KS ftfw kirw 14(1), 104(1) CM# 1 decrease contract amount by $645.00 no change to contract time -$645
Original award $1,747,795

About this award

The Department of Transportation Federal Highway Administration awarded a $1.7 million firm fixed price definitive contract to Laforge & Budd Construction Co Inc., doing business as Laforge & Budd, to perform roadway rehabilitation work at the Kirwin National Wildlife Refuge in Kensington, Kansas. The work consists of roadway reconditioning, aggregate base installation, riprap placement, replacement of a large pipe culvert, ditch reconditioning, signing, and other miscellaneous tasks as outlined in the solicitation issued under the Eastern Federal Lands Highway Division multiple award task order contract. The 215-day contract is set aside for small businesses and will involve rehabilitation of various routes and parking areas at the refuge to improve access and operations. Performance is expected to be completed by January 2023.

Description

Project KS ftfw kirw 14(1), 104(1) the project consists of roadway reconditioning, aggregate base, riprap installation, large pipe culvert replacement, ditch reconditioning, signing and other miscellaneous work.

Quick answers

Who was awarded contract 693C7320C000021?

693C7320C000021 was awarded to Laforge & Budd Construction Co Inc. by Federal Highway Administration (Department of Transportation) on June 30, 2020.

How much is contract 693C7320C000021 worth?

The government has obligated $1,747,150 on 693C7320C000021.

Was contract 693C7320C000021 competed?

The extent of competition for 693C7320C000021 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award