The silvio O. Conte national fish and wildlife refuge project FW-sico 10(1), 104(1), 105(1) - the project consists of the reconstruction of lewis pond road (0.09 miles), eagle nest road (0.14…

Ended Definitive Contract Awarded Last action

Contract number
693C7319C000013
Awardee
Awarding agency
Obligated
$483,981

Award facts

Opportunity
Contract value 100% obligated
$483,981.24 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 9 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Bloomfield, VT 05905, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00002 · The purpose of this no cost administrative modification is to financially and contractually close this contract in the amount of $483,981.24. $0
Funding Only Action P00001 · FW-sico 10(1),104(1),etc CM #1 decrease contract amount by $29,391.76 add 3 calendar days to contract time finalize the existing quantities -$29,392
Original award $513,373

About this award

This federal contract award, identified as 693C7319C000013, was made by the Federal Highway Administration, a civilian agency, to Blow & Cote, Inc., a for-profit organization. The $483,981.24 firm fixed-price contract is for the reconstruction of three roads - Lewis Pond Road, Eagle Nest Road, and Tin Shack Road - within the Silvio O. Conte National Fish and Wildlife Refuge. The work includes roadway obliteration, reconditioning, embankment construction, installation of cellular confinement systems and precast reinforced concrete box culverts with embedded material and aquatic organism passages, as well as aggregate roadway resurfacing. This contract has a set-aside designation for small businesses and is scheduled for completion by August 27, 2020.

Description

The silvio O. Conte national fish and wildlife refuge project FW-sico 10(1), 104(1), 105(1) - the project consists of the reconstruction of lewis pond road (0.09 miles), eagle nest road (0.14 miles), and tin shack road (.03 miles). The work includes existing roadway obliteration and reconditioning, embankment construction, installation of cellular confinement systems, installation of precast reinforced concrete box culverts with embedded material and aquatic organism passages, aggregate roadway resurfacing, and other miscellaneous work.

Quick answers

Who was awarded contract 693C7319C000013?

693C7319C000013 was awarded to Blow & Cote, Inc. by Federal Highway Administration (Department of Transportation) on April 25, 2019.

How much is contract 693C7319C000013 worth?

The government has obligated $483,981 on 693C7319C000013.

Was contract 693C7319C000013 competed?

The extent of competition for 693C7319C000013 was full and open competition after exclusion of sources. The government received 9 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award