Project WI erfo FS 2016-1(2) the project consists of the rehabilitation and reconstruction of storm damaged roadways and the rehabilitation of the morgan creek bridge within the chequamegon-nicolet…

Ended Definitive Contract Awarded Last action

Contract number
693C7319C000009
Awardee
Awarding agency
Obligated
$1,129,357

Award facts

Opportunity
Contract value 100% obligated
$1,129,356.52 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Butternut, WI 54514, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00002 · The purpose of this no cost administrative modification is to financially and contractually close this contract in the amount of $1,129,356.52. $0
Funding Only Action P00001 · WI erfo FS 2016-1(2) CM #1 increase contract amount by $1,334.02 no change to contract time finalize the existing quantities $1,334
Original award $1,128,023

About this award

This is a federal contract awarded by the Department of Transportation Federal Highway Administration to M Jolma Inc., a for-profit subchapter S corporation based in Northern Wisconsin. The $1,129,356.52 fixed-price contract is for the rehabilitation and reconstruction of storm-damaged roadways and the Morgan Creek Bridge within the Chequamegon-Nicolet National Forest. The work includes earthwork, roadway excavation and reconditioning, aggregate resurfacing, asphalt pavement removal and replacement, wingwall repair, drainage improvements, and other miscellaneous work. M Jolma Inc. has previously performed road, bridge, trail, and infrastructure construction, maintenance, and repair services for the U.S. Forest Service across national forests in the region, often as the prime contractor on multiple award IDIQ vehicles. This contract does not utilize a set-aside designation.

Description

Project WI erfo FS 2016-1(2) the project consists of the rehabilitation and reconstruction of storm damaged roadways and the rehabilitation of the morgan creek bridge within the chequamegon-nicolet national forest. Work includes earthwork, roadway excavation and reconditioning, aggregate resurfacing, asphalt pavement removal with separation-stabilization geotextile and aggregate base replacement, asphalt concrete pavement overlay, wingwall repair, tie rods and deadman anchors repair and replacement, drainage improvements and replacements, riprap installation, and other miscellaneous work.

Quick answers

Who was awarded contract 693C7319C000009?

693C7319C000009 was awarded to M Jolma Inc. by Federal Highway Administration (Department of Transportation) on March 28, 2019.

How much is contract 693C7319C000009 worth?

The government has obligated $1,129,357 on 693C7319C000009.

Was contract 693C7319C000009 competed?

The extent of competition for 693C7319C000009 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities