Definitive Contract 6913G620C100013
- Not listed
- This is a definitive contract awarded by the Immediate Office of the Secretary of Transportation to Track Tech, Inc., a for-profit small business entity, for the repair of 1/4 mile of trolley track and replacement of 49 wooden catenary poles with steel poles at Lowell National Historical Park. The contract has a firm fixed price of $2,364,100.00 and a completion date of May 14, 2025. Track Tech, Inc. has previously provided railroad repair services to the federal government through...
- This is a $479,203.60 firm fixed-price purchase order contract awarded by the U.S. Department of Transportation to BBA Construction LLC, a small business contractor, for the replacement of the existing power substation for the Lowell National Historical Park trolley system in Lowell, Massachusetts. The contract has a total small business set-aside designation and a completion date of June 30, 2021. BBA Construction LLC has a history of delivering various infrastructure upgrade and...
- This $119,145.66 Firm Fixed Price delivery order was awarded by the Department of Transportation to WSP USA Inc. to conduct a condition assessment of the trolley system at Lowell National Historic Park. The contract was issued under the Transportation Architect and Engineering Modernization Support (TEAMS) indefinite delivery contract. WSP USA Inc. is an engineering and professional services firm that has previously supported federal agencies such as the Federal Highway Administration and...
- <p>This is a firm-fixed-price purchase order contract awarded by the Immediate Office of the Secretary of Transportation, a civilian agency, to HDR Engineering Inc. for $151,024.80. The contract is for the design of new street and rail crossings at Bridge Street and Merrimack Street within the Lowell National Historical Park in Lowell, Massachusetts. The work is scheduled for completion by September 30, 2024. No set-aside designation was used for this award.</p>
- The U.S. Department of Transportation awarded a $36,084.00 firm fixed-price purchase order to Watermark Environmental Inc., a self-certified small disadvantaged business, to perform engineering and geotechnical investigation services to replace wooden catenary poles with steel poles for the trolley system at the Lowell National Historical Park in Lowell, Massachusetts. This contract was set aside for small businesses and was issued under the simplified acquisition procedures at the agency's John...
- This is a $251,055.54 definitive contract awarded by the Federal Railroad Administration (FRA), a civilian agency within the U.S. Department of Transportation, to the University of Massachusetts (UMass) to develop a probabilistic methodology for evaluating railroad track ballast condition using large data sets. The contract is a continuation of previous sole-source research efforts conducted by UMass under FRA contract and purchase order awards. The goal is to create a framework for assessing...
- This is a delivery order contract awarded to Tscb Enterprise, LLC, a minority and woman-owned small business joint venture, by the U.S. Department of Transportation's Federal Transit Administration (FTA). The purpose of this $158,879.55 contract is to provide targeted technical assistance and travel support to the FTA's Financial Management Oversight (FMO) program for the Massachusetts Department of Transportation. The contract is a labor hours-priced delivery order placed against Tscb...
- This federal contract award, DTFR5316C00020, was issued by the Federal Railroad Administration (FRA), a civilian agency, to the University of Massachusetts (UMass) for the development of systems targeting known ballast failure mechanisms, problem conditions, or safety concerns. The contract also covers methods to remediate problem ballast conditions to provide more reliable and effective ballast maintenance, with the goal of improving the safety and reliability of rail transportation, especially...
- This is a firm-fixed-price delivery order contract awarded by the Immediate Office of the Secretary of Transportation to Infrastructure Management Group Inc., a self-certified small disadvantaged business and limited liability company. The $84,920 contract is for financial services to support the Massachusetts Bay Transportation Authority's Positive Train Control (PTC) project, which is being funded through the Build America Bureau. The contract is not set aside. Through various delivery...
- This is a $159,337.54 firm fixed price definitive contract awarded by the U.S. Army Training and Doctrine Command (TRADOC) to Coastal Rail Solutions, LLC, a minority-owned, service-disabled veteran-owned small business, for TMTD rail car maintenance supplies. The contract has a period of performance through February 29, 2028 and is set aside for small businesses. The contract provides for the delivery of supplies and services related to rail car maintenance in support of TRADOC's mission.
The Department of Transportation awarded a $1,007,821.66 firm fixed price contract to MFS Construction LLC to perform trolley track maintenance and replace rail ties and ballast in Lowell, Massachusetts. The contract is associated with the repair and maintenance of the trolley track system, as described in the original solicitation, and has a performance period from July 24, 2020 through November 23, 2020. The funding agency, the Department of Transportation Immediate Office of the Secretary Transportation, set this opportunity aside for total small businesses only. The prime contractor, MFS Construction LLC, will replace rail ties and ballast and perform maintenance on the trolley track system to support local public transportation needs in the specified location.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Repair and Maintenance of the Trolley Track System | 6913G620C100013 | Department of Transportation Immediate Office of the Secretary Transportation | Award Notice 5/5 | 8/14/20, 12:08 PM | |
Repair and Maintenance of Trolley Track System at National Historical Park Lowell | 6913G620R200006 | Department of Transportation Immediate Office of the Secretary Transportation | Pre-Solicitation 2/5 | 4/2/20, 9:04 PM | |
Repair and Maintenance of the Trolley Track System | 6913G620R200006 | Department of Transportation Immediate Office of the Secretary Transportation | Special Notice 4/5 | 8/13/20, 3:46 PM | |
Repair and Maintenance of the Trolley Track System | 6913G620R200006 | Department of Transportation Immediate Office of the Secretary Transportation | Solicitation 3/5 | 6/1/20, 1:55 PM | |
Trolley Track Work at Lowell National Historical Par | 6913G620SSLOWE2 | Department of Transportation Immediate Office of the Secretary Transportation | Pre-Solicitation 1/5 | 11/4/19, 7:46 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00004 | Supplemental Agreement for work within scope | $178 | 11/5/20 | |
| P00003 | Change Order | $31.5k | 10/27/20 | |
| P00002 | Additional Work (new agreement, FAR part 6 applies) | $28.8k | 9/26/20 | |
| P00001 | Exercise an Option | $22.5k | 9/9/20 | |
| Not listed | Not listed | $892.7k | 7/23/20 |