Fund construction project or flap umatilla 582(1), mill creek road. Work includes chip seal, crushed aggregate, grading, repair of soldier pile walls with anchored wire mesh, signing, traffic control,…

Ended Definitive Contract Awarded Last action

Contract number
69056725C000008
Awardee
Awarding agency
Obligated
$3,114,450

Award facts

Opportunity
Contract value 100% obligated
$3,114,449.92 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Walla Walla, WA 99362, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00006 · Or flap umatill 582(1) mill creek road - this modification - closeout modification -$409,194
Supplemental Agreement for work within scope P00005 · Or flap umatill 582(1) mill creek road - this modification definitizing CM addressing anchored wire mesh quantity and utility adjustments $0
Funding Only Action P00004 · Or flap umatill 582(1) mill creek road - this modification obligation CM for anchored mesh costs $300,000
Other Administrative Action P00003 · Or flap umatill 582(1) mill creek road - this modification incorporates special notice DOT compliance with trump priorities and agenda and also incorporates… $0
Other Administrative Action P00002 · Or flap umatill 582(1) mill creek road - admin MOD $0
Other Administrative Action P00001 · This administrative modification updates the notice to proceed from 01/10/2025 to 01/15/2025 and the fixed completion date from 10/31/2025 to 11/05/2025 for… $0
Original award $3,223,644

About this award

The Federal Highway Administration awarded a $3.11 million definitive contract to Granite Construction Company for the OR FLAP UMATILL 582(1) Mill Creek Road improvement project on January 7, 2025, under a firm fixed-price structure with no set-aside.

Work is located in Walla Walla, WA and includes chip seal, crushed aggregate placement, grading, soldier pile wall repairs with anchored wire mesh, signing, traffic control, and erosion control along a 2.91-mile stretch of Mill Creek Road in Umatilla County, Oregon. The originating solicitation, posted August 6, 2024, was conducted on a full and open competitive basis as a sealed-bid procurement; the project represents a readvertisement of a previously canceled solicitation. Ultimate completion is set for August 19, 2026.

In FY2025, the contract generated $161 thousand in invoiced labor across 3.5 FTEs and 7,310 contractor hours, with a derived government-paid blended hourly rate of $22.05/hr. One subcontractor performed 43 percent of contractor hours. The contract falls under NAICS 237310 (Highway, Street, and Bridge Construction).

Description

Fund construction project or flap umatilla 582(1), mill creek road. Work includes chip seal, crushed aggregate, grading, repair of soldier pile walls with anchored wire mesh, signing, traffic control, and erosion control.

Quick answers

Who was awarded contract 69056725C000008?

69056725C000008 was awarded to Granite Construction Company by Federal Highway Administration (Department of Transportation) on January 7, 2025.

How much is contract 69056725C000008 worth?

The government has obligated $3,114,450 on 69056725C000008.

Was contract 69056725C000008 competed?

The extent of competition for 69056725C000008 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award