Construction services for project AK FS CNF 1015(2) russian river campground, phase 2

Ended Definitive Contract Awarded Last action

Contract number
69056722C000022
Awardee
Awarding agency
Obligated
$11,556,026

Award facts

Opportunity
Contract value 100% obligated
$11,556,025.56 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Anchor Point, AK, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00022 -$5,196
Funding Only Action P00020 -$500,000
Other Administrative Action P00018 $0
Supplemental Agreement for work within scope P00017 $0
Other Administrative Action P00016 $0
Funding Only Action P00015 $105,000
Change Order P00014 $50,000
Definitize Change Order P00013 $0
Supplemental Agreement for work within scope P00012 $0
Change Order P00011 $0
Other Administrative Action P00010 $99,684
Funding Only Action P00009 $324,350
Change Order P00008 $100,000
Supplemental Agreement for work within scope P00007 $0
Additional Work (new agreement, FAR part 6 applies) P00006 $6,180
Supplemental Agreement for work within scope P00005 -$6,138
Supplemental Agreement for work within scope P00003 $4,383
Exercise an Option P00004 $918,003
Supplemental Agreement for work within scope P00002 -$15,000
Other Administrative Action P00001 $0
Original award $10,474,759
Show all 21

About this award

The Federal Highway Administration awarded a definitive contract to Qayaq Construction, LLC for construction services at Russian River Campground, Phase 2 in Anchor Point, Alaska, with a ceiling value of $11.56 million and an ultimate completion date of May 6, 2026, under a total small business set-away.

The originating pre-solicitation notice, posted March 17, 2022, describes improvements over 0.78 miles including clearing, grading, asphalt paving, drainage infrastructure, retaining walls, riprap and gabion slope reinforcement, MSE walls, bridge work with piles and concrete, culverts and underdrains, guardrails, fencing, landscaping, and traffic control. The work requires survey and staking, quality control and materials testing, construction scheduling, erosion control installation, blasting with consultant oversight, and earthwork completion.

In FY2024, the most recent invoiced year, Qayaq Construction operated at 10.0 FTEs across 20,851 contractor hours with seven subcontractors performing 26% of hours. The derived government-paid blended hourly rate was $198.05/hr in FY2024, up from $175.80/hr in FY2023. FY2024 invoiced labor totaled $4.1 million, compared to $1.9 million in FY2023, reflecting year-over-year growth in utilization.

Quick answers

Who was awarded contract 69056722C000022?

69056722C000022 was awarded to Qayaq Construction, LLC by Federal Highway Administration (Department of Transportation) on August 4, 2022.

How much is contract 69056722C000022 worth?

The government has obligated $11,556,026 on 69056722C000022.

Was contract 69056722C000022 competed?

The extent of competition for 69056722C000022 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award