TFB US attorney's office relocation - 8TH floor tenant improvements, tucson federal building, 300 W congress ST., tucson, AZ 85701

Ended Definitive Contract Awarded Last action

Contract number
47PK1725C0003
Awardee
Awarding agency
Obligated
$4,256,624

Award facts

Opportunity
  • 47PK1724R0054 Solicitation number
Contract value 100% obligated
$4,256,623.80 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Contracting staff
Funding agency
US Attorney's Offices Offices Boards and Divisions, Department of Justice
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Tucson, AZ 85701, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA0015 · Extension of contract completion date for construction contract for the US attorney's office tenant improvement project in tucson federal building, AZ $0
Supplemental Agreement for work within scope PS0014 · Floor leveling for the US attorney's office tenant improvement project on 8TH floor tucson federal building, arizona. $35,581
Supplemental Agreement for work within scope PS0013 · Electrical panel updgrades for the US attorney's office tenant improvement project at the tucson federal building, AZ $5,465
Supplemental Agreement for work within scope PS0012 · Concrete coring for IT and electrical for the US attorneys office tenant improvement in the tucson federal building, AZ $3,705
Supplemental Agreement for work within scope PS0011 · FCU cover and mullions finish, chair rail and baseboard, and manbar sleeves and dampers for US attorney's office tenant improvement in tucson federal… $43,889
Supplemental Agreement for work within scope PS0010 · Incorporating DEI clause under EO 14398 for the 8TH floor US attorney's office TI project at the tucson federal building, AZ $0
Supplemental Agreement for work within scope PS0008 · Asbestos removal for 8TH floor renovation for US attorney's office in tucson federal building, arizona. $21,522
Other Administrative Action PA0007 · Administrative modification only to extend contract completion date for credentialing purposes for the US attorney's office renovation in tucson federal… $0
Supplemental Agreement for work within scope PS0006 · Sound attenuation for tenant renovation for US attorneys office in tucson federal building, arizona $5,184
Supplemental Agreement for work within scope PS0005 · PS0005 is to include additional data and electrical work to complete US attorneys office 8TH floor TI project at tucson federal building, 300 W congress ST,… $10,861
Supplemental Agreement for work within scope PS0004 · Modification PS0004 is to add additional work due to unforseen site conditions. Remove and install new ductwork for the TFB US attorneys office 8TH floor tenant… $17,259
Supplemental Agreement for work within scope PS0003 · Modification PS0003 is to add additional work for PS0003 for TFB US attorneys office 8TH floor tenant improvements at the tucson federal building, 300 W… $19,752
Supplemental Agreement for work within scope PS0002 · TFB united states attorney's office 8TH floor tenant improvements, at the tucson federal building, 300 S congress ST., tucson, AZ $0
Other Administrative Action PA0001 · TFB US attorneys office 8TH floor tenant improvements, tucson federal building, 300 W congress ST., tucson, AZ 85701 $0
Original award $4,093,406
Show all 15

About this award

The US Attorney's Offices awarded a $4.256 million definitive contract to Sonoran Pueblo Contracting, LLC, an 8(a) and HUBZone-certified tribally owned firm, for floor leveling and tenant improvements on the 8th floor of the Tucson Federal Building on December 12, 2024, under an 8(a) sole-source set-aside.

Work is located at 300 W Congress Street, Tucson, Arizona 85701. The contract carries firm fixed pricing with an ultimate completion date of September 30, 2026. In fiscal year 2025, the contract invoiced $1.3 million across 2.2 FTEs and 4,475 contractor hours, yielding a derived blended government-paid rate of $298.09 per hour. Approximately 50 percent of contractor hours were subcontracted out to two sub-engagement partners in FY2025.

Quick answers

Who was awarded contract 47PK1725C0003?

47PK1725C0003 was awarded to Sonoran Pueblo Contracting, LLC by Region 9 (Public Buildings Service) on December 12, 2024.

How much is contract 47PK1725C0003 worth?

The government has obligated $4,256,624 on 47PK1725C0003.

Which agency awarded contract 47PK1725C0003?

Region 9 (Public Buildings Service) awarded 47PK1725C0003, with funding from US Attorney's Offices (Offices Boards and Divisions).

Was contract 47PK1725C0003 competed?

The extent of competition for 47PK1725C0003 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award