Ended Definitive Contract Awarded Last action

Contract number
47PK0118C0007
Awardee
Awarding agency
Obligated
$15,175,382

Award facts

Contract value 100% obligated
$15,175,382.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
San Diego, CA 92101, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0026 · MOD for additional services $36,569
Other Administrative Action PA0025 · Admin MOD to cover fire alarm acceptance and final payment $0
Supplemental Agreement for work within scope PS0024 · CE 152 - south facade (-$100,953) CE 162 - T-stat conflict at ATS ($914) CE 187 - pump room finishes ($1,928) CE 211 - jockey pump circuit ($2,008) CE 212 -… $16,640
Supplemental Agreement for work within scope PS0023 · MOD for additional services FY16 DBB $9,264
Supplemental Agreement for work within scope PS0022 · 47PK0118C0007, MOD PS0022 - implementation of section 889 $0
Supplemental Agreement for work within scope PS0021 · Eoir construction of 3 rooms $89,690
Supplemental Agreement for work within scope PS0020 · 47PK0118C0007, MOD PS0020 - FY16 design bid build tenant improvements $32,366
Supplemental Agreement for work within scope PS0019 · Add additional CE's $36,407
Supplemental Agreement for work within scope PS0018 · MOD for additional services $51,812
Supplemental Agreement for work within scope PS0017 · This BI-lateral MOD is for eoir wood grille infill slats per CE 128 and changes to grand jury wall mounted glass supports per CE 135 at the edward J. Schwartz… $63,179
Supplemental Agreement for work within scope PS0016 · This BI-lateral MOD is for change estimates 119, 121 & 122 in the edward J. Schwartz federal building and courthouse. In consideration of the modification… $16,933
Supplemental Agreement for work within scope PS0015 · This BI-lateral MOD is for changes to provide labor & material to replace doors with full-glass lite, new hardware & frame; relocate existing cabinet to break… $32,548
Supplemental Agreement for work within scope PS0013 · This BI-lateral modification is being issued to provide grand jury STC 55 doors in hearing rooms located in the edward J. Schwartz federal building and… $51,164
Supplemental Agreement for work within scope PS0014 · This BI-lateral MOD is for changes to the fire pump and includes revised shop drawings, upsizing the fire pump from 85PSI to 125PSI, and a new automatic fill… $43,947
Supplemental Agreement for work within scope PS0012 · This modification is being issued to provide grand jury door finishes & acoustic properties for the above mentioned project located at the schwartz federal… $44,202
Supplemental Agreement for work within scope PS0011 · This MOD is for changes to 1ST floor courthouse public corridor adjacent to grand jury suite and includes scope for unforeseen conditions $68,839
Supplemental Agreement for work within scope PS0010 · Schwartz FY16 DBB SAN diego, CA this BI-lateral modification is being issued to provide GJ public corridor above ceiling electrical conduit support and… $22,111
Supplemental Agreement for work within scope PS0009 $31,545
Supplemental Agreement for work within scope PS0008 · FY16 DBB, TI schwartz federal building SAN diego, CA this BI-lateral modification is being issued to provide rooftop generator paralleling fear interface for… $59,635
Supplemental Agreement for work within scope PS0007 · RE: schwartz FY16 DBB grand jury SAN diego, CA this modification is being issued to provide grand jury space for the above mentioned project located at the… $112,570
Supplemental Agreement for work within scope PS0006 · FY16 design bid build tenant improvements schwartz CH/FB SAN diego, CA this modification is being issued to provide ASI #03 changes for eoir and grand jury… $87,276
Supplemental Agreement for work within scope PS0005 · FY16 DBB schwartz federal building & CH SAN diego, CA this BI-lateral modification is being issued to provide for demolition/rough-in, including new ceiling… $99,650
Supplemental Agreement for work within scope PS0004 $112,638
Supplemental Agreement for work within scope PS0003 · FY 16 DBB tenant improvements schwartz federal building SAN diego, CA this BI-lateral modification is being issued to provide replacement of roof drains level… $27,702
Supplemental Agreement for work within scope PS0002 · Project: FY16 design bid build tenant improvements, eoir, grand jury and EPA, edward J. Schwartz federal building, 880 front street, SAN diego, california (CE… $30,921
Change Order PC0001 · FY16 DBB construction eoir, EPA and grand jury schwartz FB, SAN diego, CA task order MOD $100,000
Original award $13,897,774
Show all 27

About this award

The General Services Administration (GSA) Public Buildings Service Region 9 awarded a $15,175,382.00 Definitive, Firm Fixed Price contract to Hensel Phelps Construction Co. for work to be performed in San Diego, CA. The contract was not set aside for any specific business type. The contract was awarded on July 12, 2018 with a completion date of September 1, 2020.

Quick answers

Who was awarded contract 47PK0118C0007?

47PK0118C0007 was awarded to Hensel Phelps Construction Co by Region 9 (Public Buildings Service) on July 12, 2018.

How much is contract 47PK0118C0007 worth?

The government has obligated $15,175,382 on 47PK0118C0007.

Was contract 47PK0118C0007 competed?

The extent of competition for 47PK0118C0007 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities