Contract 47PF0018C0122, glycol cooling tower replacement at the everett dirksen courthouse, located at 219 south dearborn street, chicago IL 60604. The general services administration requires…

Ended Definitive Contract Awarded Last action

Contract number
47PF0018C0122
Awardee
Awarding agency
Obligated
$944,222

Award facts

Opportunity
  • 47PF0018R0166 Solicitation number
Contract value 100% obligated
  • $944,221.72 Current, with exercised options
  • $944,749.76 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Chicago, IL 60604, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0013 · Modification to deduct unused escorting services. -$528
Supplemental Agreement for work within scope PS0012 · Modification to extend the completion date of the contract. Time extension will allow contractor time to evaluate and review current leak repairs. $0
Supplemental Agreement for work within scope PS0011 $0
Other Administrative Action PA0010 · The purpose of this modification is to update the funding fixed asset RIL11415IL0205ZZ information from cipimp to improvmnt in the accounting lines of this… $0
Supplemental Agreement for work within scope PS0009 · Modification to extend the contract to allow time for additional leak repairs and post-repair observations. $0
Other Administrative Action PA0007 · This mass modification is to update the designated billing office to allow for electronic invoicing via https://finance.ocfo.GSA.GOV/webvendors approval… $0
Supplemental Agreement for work within scope PS0006 · Modification to extend completion date in order to allow contractor to fix cooling tower leaks during non cooling season. $0
Other Administrative Action PA0004 · Modification to change the contracting officer. New contracting officer will be kimberly bogan-ridley. $0
Additional Work (new agreement, FAR part 6 applies) PS0005 · Modification for a for valve replacement and jace upgrade. Total value of modification $10,644.04, total contract value is $944,749.76. Completion date… $10,644
Supplemental Agreement for work within scope PS0002 · Modification PS0002, contract 47PF0018C0122 for the glycol cooling tower replacement at the everett M. Dirksen federal building, 219 south dearborn street,… $13,257
Supplemental Agreement for work within scope PS0001 · Contract 47PF0018C0122 - glycol cooling tower replacement everett dirksen federal building, 219 south dearborn street, chicago, illinois 60604; modification… $0
Original award $920,849
Show all 12

About this award

The U.S. General Services Administration (GSA) Public Buildings Service Region 5 awarded a Definitive, Firm Fixed Price contract worth $944,749.76 to Amalgamated / Hill JV, LLC, a joint venture small disadvantaged business, for the replacement of a glycol cooling tower at the Everett Dirksen Federal Courthouse in Chicago, Illinois. The contract was awarded on August 30, 2018 and has a completion date of June 1, 2022. The contractor will be required to remove the existing cooling tower and install a new closed circuit (fluid cooler) cooling tower that is compatible with the existing building automation system, as well as provide associated equipment and services.

Description

Contract 47PF0018C0122, glycol cooling tower replacement at the everett dirksen courthouse, located at 219 south dearborn street, chicago IL 60604. The general services administration requires construction services for the replacement of a glycol cooling tower in the everett dirksen federal courthouse. The contractor will be required to remove the existing cooling tower, and purchase and install a new complete and operating closed circuit (fluid cooler) cooling tower that can be retrofitted to all existing systems and be compliant with the existing building automation system. IT will also include, but is not limited to, purchase and installation of condenser pumps, domestic cold water, power, a complete chemical treatment system, building automation system controls and the structural frame.

Quick answers

Who was awarded contract 47PF0018C0122?

47PF0018C0122 was awarded to Amalgamated / Hill JV, LLC by Region 5 (Public Buildings Service) on August 30, 2018.

How much is contract 47PF0018C0122 worth?

The government has obligated $944,222 on 47PF0018C0122. Its potential value, with all options, is $944,750.

Was contract 47PF0018C0122 competed?

The extent of competition for 47PF0018C0122 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award