47PF0017C0033 - 985 michigan avenue building modernization and backfill project construction manager as constructor (CMC) services, detroit, michigan 48226 base award for design phase services at…

Ended Definitive Contract Awarded Last action

Contract number
47PF0017C0033
Awardee
Awarding agency
Obligated
$116,790,128

Award facts

Opportunity
Contract value 100% obligated
$116,790,128.21 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Detroit, MI 48226, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0058 · Modification PS58 to deobligate remaining balance in conjunction with the finalizing of the guaranteed maximum price for the for the 985 michigan avenue… -$265,345
Supplemental Agreement for work within scope PS0057 · Modification PS57 is being issued to add additional corridor signage and garage door hardware. For the 985 michigan AVE project located in detroit michigan. $12,456
Supplemental Agreement for work within scope PS0056 · Modification PS56 is issued for CE50049 involves construction services to provide repair work to the service drive gate due to a truck collision for the 985… $62,524
Supplemental Agreement for work within scope PS0055 · This modification is to incorporate construction changes into the construction manager as constructor contract for the 985 michigan avenue project at the… $150,804
Supplemental Agreement for work within scope PS0054 · This modification is for the purpose of incorporating a no cost time extension for the construction manager as constructor contract for the 985 michigan… $0
Other Administrative Action PA0053 · This modification is for the purpose of completing an administrative budget change for the construction manager as constructor contract for the 985 michigan… $0
Supplemental Agreement for work within scope PS0052 · This modification is to issue a no cost time extension for the construction manager as constructor contract for the 985 michigan avenue project in detroit… $0
Supplemental Agreement for work within scope PS0051 · This modification is to incorporate construction changes into the construction manager as constructor contract for the 985 michigan avenue modernization project… $105,432
Supplemental Agreement for work within scope PS0050 · This modification is to provide construction changes to the core and shell areas of the backfill project at 985 michigan avenue in detroit michigan. $32,042
Supplemental Agreement for work within scope PS0049 · This modification is for various construction changes to the construction manager as contractor contract for the 985 michigan avenue modernization project at… $72,999
Supplemental Agreement for work within scope PS0046 · This modification is to incorporate several construction changes for TEH construction manager as contractor contract for the 985 michigan avenue project in… $1,909,829
Funding Only Action PA0045 · This modification is to process a cost transfer for the internal revenue service - reimbursable work authorization for the 985 michigan avenue backfill… -$1,552,925
Supplemental Agreement for work within scope PS0044 · This modification is for the purpose of adding several construction changes to the construction manager as contractor contract for the 985 michigan avenue… $1,013,681
Funding Only Action PA0043 · This modification is part of an ongoing effort to process a cost transfer for the 985 michigan avenue backfill project at 985 michigan avenue in detroit… $929,967
Funding Only Action PA0042 · This modification is to finalize a cost transfer for the internal revenue services - reimbursable work authorization for the 985 backfill project at 985… -$929,967
Funding Only Action PA0041 · This modification is to initiate a cost transfer for the internal revenue service reimbursable work authorization for the 985 backfill project at 985 michigan… $1,818,270
Supplemental Agreement for work within scope PS0040 · This modification is for the purpose of incorporating various construction changes into the construction manager as constructor contract for the 985 michigan… $253,480
Supplemental Agreement for work within scope PS0039 · This modification is for the purpose of extending the period of performance by one month, due to the delay of acquiring city permits for the construction… $0
Supplemental Agreement for work within scope PS0038 · This modification is for the purpose of incorporating construction changes as defined in CE50038 for the construction manager as constructor contract for the… $739,500
Supplemental Agreement for work within scope PS0037 · This modification is for the purpose of deobligating and removing the united states department of agriculture scope of work from the 985 michigan avenue… -$249,538
Supplemental Agreement for work within scope PS0036 $0
Funding Only Action PA0035 $0
Funding Only Action PA0034 · This is an administrative modification to complete an accounting line reorganization. All terms and conditions of the contract remain unchanged. $0
Supplemental Agreement for work within scope PS0033 · This modification is for the purpose of awarding construction phase services as outlined in bid package 4, including tenant build-outs for three tenant… $14,047,582
Supplemental Agreement for work within scope PS0032 · This modification is for the purposed of relocating a gas line so construction can continue in the area safely at the 985 michigan backfill project at the 985… $374,916
Supplemental Agreement for work within scope PS0031 · This modification is for construction services for the 985 michigan avenue backfill project at the 985 michigan avenue building in detroit michigan. $607,055
Supplemental Agreement for work within scope PS0030 · This modification is for the purposes of incorporating a multitude of construction changes, stemming primarily from tenant change requests and unforeseen… $758,925
Supplemental Agreement for work within scope PS0029 · This modification is for the purposes of incorporating additional construction services, as outlined in change request 50033 for the 985 michigan AVE… $771,050
Other Administrative Action PA0028 · This is an admin MOD to correct a fixed asset in an accounting line and update the contracting officer of record for the 985 michigan AVE modernization… $0
Supplemental Agreement for work within scope PS0027 · This modification is to award bid package 3, for construction services for the buildout of space for several different tenants at the 985 michigan building in… $10,257,491
Supplemental Agreement for work within scope PS0026 · This modification is for several construction changes for the 985 michigan AVE backfill project at 985 michigan AVE in detroit michigan. $2,237,484
Supplemental Agreement for work within scope PS0025 · This modification is to incorporate multiple rfis and changes for the IRS print shop, office, and navy, including the remaining portion of bid package 2 for… $2,944,872
Supplemental Agreement for work within scope PS0024 · This modification is for construction services to complete: ASI 10 ASI 11 ASI 12 ASI 14.1 ASI 15A ASI 16.1 ASI 19 IRS BP2 J3 (TELECOM) and J4 (SECURITY) $3,854,994
Supplemental Agreement for work within scope PS0023 · RFI's - 081, 188, 170, 143, 067, 218, 388, 310/372, 408, 334/346, 394, 433, 404, 457, 458, 477, 412, 413/417, 505, 051, 432 CS5021 - relocation of power service… $184,835
Supplemental Agreement for work within scope PS0022 · 889 mass MOD $0
Supplemental Agreement for work within scope PS0021 · No cost time extension $0
Supplemental Agreement for work within scope PS0020 · Additional work within scope as described in rfis - 037 079 170 241 246 additional services (TCC #) - CS5063, CS5070, CS5073, CS5076, CS5079 $143,953
Supplemental Agreement for work within scope PS0019 · Contract# 47PF0017C0033; construction manager as constructor (CMC) for the 985 michigan avenue building modernization and backfill project located at the 985… $453,382
Supplemental Agreement for work within scope PS0018 · Incorporation of bid package 2 $11,611,217
Supplemental Agreement for work within scope PS0017 · Contract# 47PF0017C0033; 985 michigan avenue building modernization and backfill project; detroit, michigan; MOD PS0017 - rfls 27/165, 70/147, 135/244, 308,… $308,250
Supplemental Agreement for work within scope PS0016 $877,879
Supplemental Agreement for work within scope PS0015 $518,485
Supplemental Agreement for work within scope PS0014 $256,712
Supplemental Agreement for work within scope PS0013 $296,735
Supplemental Agreement for work within scope PS0012 $759,190
Supplemental Agreement for work within scope PS0011 · Contract # 47PF0017C0033; construction manager as constructor (CMC) for the 985 michigan avenue building modernization and backfill project located at the 985… $399,071
Supplemental Agreement for work within scope PS0010 · Contract 47PF0017C0033 construction manager as constructor for the 985 michigan avenue building modernization and backfill project located in detroit, michigan.… $137,513
Other Administrative Action PA0009 $0
Supplemental Agreement for work within scope PS0008 $10,139
Supplemental Agreement for work within scope PS0007 · Contract # 47PF0017C0033; construction manager as constructor (CMC) for the 985 michigan avenue building modernization and backfill project located at the 985… $28,868
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The General Services Administration (GSA) has awarded a $116,790,128.21 definitive contract to The Christman Company, a for-profit construction services firm, for the 985 Michigan Avenue Building Modernization and Backfill Project in Detroit, Michigan. The contract includes a firm-fixed-price award of $671,953.00 for the design phase and a guaranteed maximum price (GMP) of $74,932,367.00 for the construction phase, which has been accepted and may be awarded at a later date. This contract is not set aside for small businesses. The work to be performed includes construction manager as constructor (CMC) services for building modernization and backfill efforts at the 985 Michigan Avenue location in Detroit, with a completion date of December 1, 2023.

Description

47PF0017C0033 - 985 michigan avenue building modernization and backfill project construction manager as constructor (CMC) services, detroit, michigan 48226 base award for design phase services at the firm-fixed price of $671,953.00. The option for construction phase services, at the guaranteed maximum price (GMP) of $74,932,367.00 has been accepted and may be awarded at a later date.

Quick answers

Who was awarded contract 47PF0017C0033?

47PF0017C0033 was awarded to The Christman Company by Region 5 (Public Buildings Service) on September 12, 2017.

How much is contract 47PF0017C0033 worth?

The government has obligated $116,790,128 on 47PF0017C0033.

Was contract 47PF0017C0033 competed?

The extent of competition for 47PF0017C0033 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award