Design-build construction of new land port of entry in madawaska, me

Ended Definitive Contract Awarded Last action

Contract number
47PB0021C0005
Awardee
Awarding agency
Obligated
$61,303,003

Award facts

Opportunity
Contract value 100% obligated
$61,303,003.18 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Madawaska, ME, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0066 · This modification gives a credit the contract to resolve the damper situation. -$133,000
Supplemental Agreement for work within scope PS0065 · This modification adds additional workfor the thermostats in the booths, madawaska, me $5,384
Supplemental Agreement for work within scope PS0064 · This modificaiton is for additional work to replace the CUH thermostats from manual to automatic. $0
Supplemental Agreement for work within scope PS0063 · This MOD is to extend the contract to 6/30/2025. $0
Supplemental Agreement for work within scope PS0061 · This modification PS0061 is for the design and construction of the stacks, madawaska lpoe, maine $596,981
Other Administrative Action PA0060 · This administrative MOD PA0060 extends the contract completion date from 8/30/2024 to 9/30/2024. $0
Supplemental Agreement for work within scope PS0059 · This modification PS0059 is to credit the contract by $40K so that the government can complete/resolve the lawn landscaping issues. -$40,000
Other Administrative Action PA0058 · PA0058 is a no cost time extension for madawaska lpoe. $0
Other Administrative Action PA0057 · This modification PA0057 issues a no cost time extension from 6/14/2024 to 7/31/2024. $0
Other Administrative Action PA0056 · This MOD PA0056 is to extend the contract completion from 5/28/2024 to 6/14/2024 to review final work and punch list items and determine a final contract… $0
Supplemental Agreement for work within scope PS0055 · The EV charger issued in previous MOD, is being removed. A credit to contract is being issued via this MOD PS0055. -$11,000
Other Administrative Action PA0054 · This unilateral MOD corrects the subject object code (SOC) on clin 0062, acct line # 15 from K01 to M51. $0
Change Order PS0053 · Purchase of EV charger for madawaska lpoe. $11,000
Other Administrative Action PA0052 · Corrective administrative action madawaska lpoe. $0
Change Order PS0051 · No cost substantial completion extension to 3/27/2024, madawaska lpoe. $0
Change Order PS0050 · MOD to move from old to new lpoe and change COR for madawaska lpoe. $79,600
Funding Only Action PA0049 · MOD PA0049 is an administrative MOD that transfers $168,000. -$168,000
Funding Only Action PA0048 · Cost transfer modification for madawaska lpoe, madawaska, me. $168,000
Change Order PS0047 · EV infrastructure and heater block install madawaska lpoe, madawaska me. $379,026
Change Order PS0046 · Add deduct MOD for madawaska lpoe, madawaska, me. $1,603
Change Order PS0045 · No cost extension madawaska lpoe, madawaska, me. $0
Change Order PS0044 · Modification for additional equipment and construction items madawaska lpoe, madawaska, me. $806,000
Change Order PS0043 · Equitable adjustment and time extension madawaska lpoe, madawaska me. $264,000
Other Administrative Action PA0042 · COR administrative change madawaska lpoe. $0
Change Order PS0041 · Fall protection madawaska lpoe, madawaska, me. $53,441
Funding Only Action PA0040 · Administrative MOD for madawaska lpoe, madawaska me. -$58,500
Funding Only Action PA0039 · Administrative funding modification madawaska lpoe. $58,500
Definitize Change Order PS0038 · Furniture buy for madawaska lope, madawaska, me. $1,184,013
Supplemental Agreement for work within scope PS0037 · Dpas modification increase madawaska lpoe madawaska, me. $94,433
Definitize Change Order PS0036 · Definitization of pcos 28 C, 28 E and 28 H for madawaska lpoe. $1,333,836
Supplemental Agreement for work within scope PS0034 · Dpas clauses madawaska lpoe, madawaska me $0
Change Order PS0033 · Deobligation of electronic conduits and boxes. -$6,000
Change Order PS0032 · Buying signs for madawaska lpoe. $442,034
Supplemental Agreement for work within scope PS0031 · Security and access control changes (ACS) $1,340,700
Other Administrative Action PA0030 · Incorporation of IPV6. $0
Definitize Change Order PS0029 · This modification completes funding for CPO 28 a and 28 D for the madawaska lpoe project. $508,536
Change Order PS0028 · Video wall, printing and rendering MOD $175,490
Other Administrative Action PA0027 · Contracting officer change. $0
Change Order PS0026 · Multiple small change order for additional within scope work at the new lpoe in madawaska, me. $40,673
Supplemental Agreement for work within scope PS0025 · Modification to substitute the project switchgear, due to supply chain issues with the original. $326,300
Funding Only Action PA0024 · Administrative modification to transfer costs between line items. -$12,290
Change Order PS0022 · Change order for sidewalk and curbing work, madawaska lpoe, madawaska, me $172,700
Change Order PC0020 · Price to be determined later - PDL - modification for miscellaneous changes to the contract for a new lpoe at madawaska, me. $237,664
Change Order PS0019 · Modification to definitize electrical changes to the contract. $250,730
Funding Only Action PA0017 · Administrative MOD to correct clin 8 function environmental cost . $12,290
Change Order PS0016 · Modification to install bathroom, UPS and design work. $308,853
Supplemental Agreement for work within scope PS0015 · Madawaska lpoe new construction -- change from EPM to kahua project management system $21,878
Change Order PC0014 · Madawaska new lpoe bridging design-build | undefinitized change order for construction of electrical change to 1200 amps $1,732,270
Supplemental Agreement for work within scope PS0013 · Madawaska new land port of entry construction - time extension and time-related cost modification $211,200
Supplemental Agreement for work within scope PS0012 · This modification is the definitization for the NTE issued on MOD PC0007 for the fill and fencing. -$62,310
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This contract was awarded by the General Services Administration (GSA) to J & J Contractors, Inc., a minority-owned small business, for the design and construction of a new 76,717 square foot Land Port of Entry (LPOE) facility in Madawaska, Maine. The contract has a ceiling value of $61,303,003.18 and is a definitive, firm-fixed price contract. It is not a set-aside contract.

The new LPOE facility will replace the existing 1959 mission and operationally deficient LPOE, and will connect to a concurrent Maine Department of Transportation (MaineDOT) bridge replacement project costing over $5 million. The contract performance period is approximately 1,102 calendar days, with anticipated substantial completion by late 2023. This procurement utilized a design-build bridging approach, where GSA contracted with a design-build bridging architect to develop the final concept design and bridging contract documents, which J & J Contractors will use to complete the final design and construction.

Quick answers

Who was awarded contract 47PB0021C0005?

47PB0021C0005 was awarded to J & J Contractors, Inc. by Region 1 (Public Buildings Service) on January 20, 2021.

How much is contract 47PB0021C0005 worth?

The government has obligated $61,303,003 on 47PB0021C0005.

Was contract 47PB0021C0005 competed?

The extent of competition for 47PB0021C0005 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award