Saint louis demolition and paving at jefferson barracks medical facility

Ended Definitive Contract Awarded Last action

Contract number
36C10F21C0001
Awardee
Awarding agency
Obligated
$19,726,379

Award facts

Opportunity
Contract value 100% obligated
$19,726,378.50 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
NAICS code
238910 Site Preparation Contractors
Set-aside
Service-Disabled Veteran-Owned Small Business
Competition
Full and Open Competition after exclusion of sources · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Lemay Township, MO 63125, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00026 · P00026 final settlement modification. $68,977
Supplemental Agreement for work within scope P00025 $0
Supplemental Agreement for work within scope A00085 · A00085 (SA-A00085) radiographic testing. $10,344
Supplemental Agreement for work within scope P00024 · P00024 incorporate PCO 50 changes (SD) $51,802
Supplemental Agreement for work within scope P00023 · P00023 (SD) modify steam piping . $34,294
Change Order P00020 · A00080 (SA-A00080) modify building 18 waterline $11,030
Change Order P00022 · A00084 (SA-A00084) additional electrical work in the north phase. $10,676
Change Order P00021 · A00080 (SA-A00080) modify building 18 waterline $8,954
Supplemental Agreement for work within scope A00084 · A00084 (SA-A00084) additional electrical work in the north phase. $44,875
Supplemental Agreement for work within scope A00082 · A00082 (SA-A000820) remove two electrical manholes from north phase. $3,350
Supplemental Agreement for work within scope A00083 · A00083 (SA-A00083) extend east gate power $5,104
Supplemental Agreement for work within scope P00019 · P00017 (SA-P00017) road closure delays and work under road $0
Supplemental Agreement for work within scope A00081 · A00081 (SA-A00081) lower sump pump electric $8,748
Supplemental Agreement for work within scope A00080 · A00080 (SA-A00080) modify building 18 waterline $17,050
Other Administrative Action P00018 · P00017 (SA-P00017) road closure delays and work under road $449
Supplemental Agreement for work within scope A00077 · A00077 (SA-A00077) asbestos items. $17,318
Supplemental Agreement for work within scope A00078 · A00078 (SA-A00078) thrust block $1,575
Supplemental Agreement for work within scope A00076 · A00076 (SA-A00076) multiple items. $24,363
Supplemental Agreement for work within scope A00079 · A00079 (SA-A00079) B-53 service gate #6 additional work. $15,654
Definitize Change Order A00074 · A00074 (SA-A00074) remove asbestos ductbank and chilled water manhole in north phase $16,843
Definitize Change Order P00016 · P00016 (SA-P00016) south sequence 2 delays $12,615
Supplemental Agreement for work within scope A00072 · A00072 (SA-A00072) additional work associated with RFI-63 response $2,217
Supplemental Agreement for work within scope A00075 · A00075 (SA-A00075) additional curb and asphalt $15,036
Supplemental Agreement for work within scope A00073 · A00073 (SA-A00073) building 53 loading dock trench drain $5,739
Definitize Change Order P00017 · P00017 (SA-P00017) road closure delays and work under road $73,168
Supplemental Agreement for work within scope A00070 · A00070 (SA-A00070) multiple items -$3,172
Definitize Change Order A00069 · A00069 (SA-A000069) remove 3 light poles and base in the north. -$725
Definitize Change Order A00071 · A00071 (SA-A00071) install domestic water valve near MH-S20 $3,434
Definitize Change Order P00015 · P00015 (SA-P00015) extend existing 4" telecom conduit in south phase -$468
Supplemental Agreement for work within scope A00068 · A00068 (SA-A00068) delete gas line removal and delete topsoil install -$17,909
Definitize Change Order A00063 · A00063 (SA-A00063) remove concrete block in north phase -$504
Definitize Change Order P00012 · P00012 (SA-P00012) asbestos removal from foundation of bldgs. 61 & 63 $167,552
Definitize Change Order A00065 · A00065 (SA-A00065) add 15 slow-grow sumac shrubs $167
Supplemental Agreement for work within scope A00051 · A00051 (SA-A00051) remove additional asbestos in buildings 61 & 63. $25,734
Definitize Change Order A00061 · A00061 (SA-A00061) steam piping changes at building 18 per SI-008 $38,734
Definitize Change Order A00067 · A00067 (SA-A00067) remove existing entrance at building 75 $15,398
Definitize Change Order A00066 · A00066 (SA-A00066) remove miscellaneous asbestos in south phase $20,767
Definitize Change Order A00064 · A00064 (SA-A00064) add handrail at west campus amphitheater $45,097
Change Order P00013 · P00013 (CO-P00013) delays starting south sequence 2 $51,471
Change Order P00014 · P00014 (CO-P00014) delays crossing road and unforeseen work under road $79,100
Supplemental Agreement for work within scope P00011 · P00011 (SA-P00011) weather impacts - october thru december 2022 $0
Definitize Change Order A00062 · A00062 (SA-A00062) relocate contractor office trailer $883
Supplemental Agreement for work within scope A00060 · A00060 (SA-A00060) modify handrail detail -$5,041
Change Order A00058 · A00058 (CO-A00058) concrete removal $5,000
Change Order A00059 · A00059 (CO-A00059) relocate contractor office trailer $5,000
Change Order A00057 · A00057 (CO-A00057) install water valve near MH-S20 $8,000
Change Order A00056 · A00056 (CO-A00056) add 15 slow-grow sumac shrubs to south sequence 2 $750
Definitize Change Order A00052 · A00052 (SA-A00052) remove electrical ductbank in south phase. $4,525
Definitize Change Order A00053 · A00053 (SA-A00053) modify fence and grading at south entrance gate per SI-017 $5,169
Change Order A00054 · A00054 (CO-A00054) extend existing 4" telecom conduit $6,000
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $19,726,378.50 firm fixed price contract awarded by the U.S. Department of Veterans Affairs (VA) Office of Construction and Facilities Management to Spees-Hernandez JV LLC, a Service-Disabled Veteran-Owned Small Business (SDVOSB) joint venture, for a demolition and paving project at the Jefferson Barracks campus of the St. Louis VA Medical Center. The contract, which has a completion date of July 27, 2023, involves the abatement, removal, and disposal of existing buildings, as well as related site work including excavation, utilities, pavements, walkways, and landscaping. This project was originally solicited as a pre-solicitation notice in July 2020, with proposals due in May 2020, and was set aside exclusively for SDVOSB firms. As a SDVOSB contractor, Spees-Hernandez JV LLC has been awarded over $80 million in federal contracts from 2020 to 2022, primarily from the VA for construction, renovation, and facility improvement projects at VA medical centers across the country.

Quick answers

Who was awarded contract 36C10F21C0001?

36C10F21C0001 was awarded to Spees-Hernandez JV LLC by VA Office of Construction and Facilities Management (Headquarters) on December 3, 2020.

How much is contract 36C10F21C0001 worth?

The government has obligated $19,726,379 on 36C10F21C0001.

Was contract 36C10F21C0001 competed?

The extent of competition for 36C10F21C0001 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award