Operation and maintenance of the south BAY wastewater treatment plant.
Ended Definitive Contract Awarded Last action
- Contract number
- 191BWC20C0003
- Awardee
-
Veolia Water West Operating Services Inc. UEI VQTPF9KTZAY8
- Awarding agency
-
International Boundary and Water Commission U.S.-Mexico
- Obligated
- $87,960,473
Award facts
- Opportunity
-
- 191BWC20R0002 Solicitation number
- O&M Services SBIWTP Award Notice · Posted Sep 28, 2020
- O&M Services SBIWTP Solicitation · Posted Apr 29, 2020
- O&M Services SBIWTP Pre-Solicitation · Posted Feb 25, 2020
- Contract value 100% obligated
- $88,320,919.18 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 221320 Sewage Treatment Facilities
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 1 offer Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- San Ysidro, CA 92173, USA
- Legislative mandates
-
- Service Contract Act FAR subpart 22.10
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $2,079,854 | |
| Supplemental Agreement for work within scope | $589,114 | |
| Funding Only Action | $8,740,231 | |
| Funding Only Action | $1,013,538 | |
| Funding Only Action | $0 | |
| Additional Work (new agreement, FAR part 6 applies) | $3,198,614 | |
| Supplemental Agreement for work within scope | $11,869,360 | |
| Supplemental Agreement for work within scope | $2,378,692 | |
| Funding Only Action | $1,469,017 | |
| Exercise an Option | $0 | |
| Funding Only Action | $734,508 | |
| Supplemental Agreement for work within scope | $5,401 | |
| Funding Only Action | $734,508 | |
| Supplemental Agreement for work within scope | $637,012 | |
| Funding Only Action | $734,508 | |
| Supplemental Agreement for work within scope | $746,323 | |
| Supplemental Agreement for work within scope | $300,201 | |
| Funding Only Action | $734,508 | |
| Supplemental Agreement for work within scope | $518,122 | |
| Supplemental Agreement for work within scope | $1,517,714 | |
| Funding Only Action | $746,323 | |
| Supplemental Agreement for work within scope | $161,063 | |
| Supplemental Agreement for work within scope | $225,928 | |
| Funding Only Action | $1,422,721 | |
| Supplemental Agreement for work within scope | $22,327 | |
| Funding Only Action | $723,005 | |
| Exercise an Option | $1,469,299 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $1,446,010 | |
| Supplemental Agreement for work within scope | $1,908,000 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $1,162,071 | |
| Supplemental Agreement for work within scope | $439,066 | |
| Supplemental Agreement for work within scope | $572,337 | |
| Funding Only Action | $723,005 | |
| Funding Only Action | $1,446,010 | |
| Funding Only Action | $734,649 | |
| Exercise an Option | $1,211,699 | |
| Supplemental Agreement for work within scope | $872,934 | |
| Supplemental Agreement for work within scope | $2,384,511 | |
| Supplemental Agreement for work within scope | $1,649,128 | |
| Supplemental Agreement for work within scope | $3,205,871 | |
| Exercise an Option | $711,699 | |
| Other Administrative Action | $2,135,096 | |
| Funding Only Action | $1,401,171 | |
| Change Order | $1,092,543 | |
| Exercise an Option | $0 | |
| Funding Only Action | $1,423,397 | |
| Funding Only Action | $711,099 | |
| Funding Only Action | $700,586 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
The International Boundary and Water Commission U.S.-Mexico awarded Veolia Water West Operating Services Inc. a definitive firm fixed-price contract valued at approximately $88.3 million for the operation and maintenance of the South Bay Wastewater Treatment Plant in San Ysidro, California. The contract, awarded on September 28, 2020, with an ultimate completion date of March 31, 2026, includes comprehensive facility management services along with additional scope work encompassing dirt hauling and electrical work. The award is not designated as a set-aside contract and reflects the IBWC's commitment to ensuring reliable wastewater treatment infrastructure along the U.S.-Mexico border.
The contract represents a continuation of Veolia's established partnership with the IBWC for critical water infrastructure management. Beyond routine operations and maintenance, the contract has been modified to address emergency repairs, infrastructure rehabilitation, and unforeseen challenges requiring additional work within the original scope. Veolia Water West Operating Services Inc., a water infrastructure specialist registered in the System for Award Management since 2010, brings extensive expertise in managing complex treatment facilities, having previously managed multiple emergency and long-term operational projects for the South Bay facility. The funding supports essential environmental compliance and operational continuity for this strategically important international water treatment facility.
Quick answers
Who was awarded contract 191BWC20C0003?
191BWC20C0003 was awarded to Veolia Water West Operating Services Inc. by International Boundary and Water Commission U.S.-Mexico on September 28, 2020.
How much is contract 191BWC20C0003 worth?
The government has obligated $87,960,473 on 191BWC20C0003. Its current value, with exercised options, is $88,320,919.
Was contract 191BWC20C0003 competed?
The extent of competition for 191BWC20C0003 was full and open competition. The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award