This project is to provide construction services for a new job corps campus to replace the existing job corps center located in atlanta, GA. The new campus is comprised of approximately 25 acres at…

Ended Definitive Contract Awarded Last action

Contract number
1630DC17C0024
Awardee
Awarding agency
Obligated
$29,102,437

Award facts

Contract value 47% obligated
$61,436,769.46 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Atlanta Job Corps Center Office of Job Corps, Department of Labor
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Atlanta, GA 30301, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Terminate for Convenience 15 · Atlanta JCC construction project settlement agreement. Add $5,000,000 in funding. $5,000,000
Other Administrative Action 14 · The atlanta JCC construction project - DE-obligate funds -$37,334,333
Terminate for Default 13 · The atlanta JCC construction project termination for default: effective december 6, 2019. $0
Other Administrative Action 12 · The atlanta JCC construction project suspension of work : effective november 22, suspension work on all hydronic piping work. Please reference the suspension of… $0
Other Administrative Action 11 · The atlanta JCC construction project effective july 22, 2019, JOY fryer-scott replaces maria pizarro as the contracting officer for the project. The contract… $0
Other Administrative Action 10 · The atlanta JCC construction project 1. The suspension of work issued on (october 12, 2018)is here by lifted effective date of june 4, 2019.(per the contracting… $1,500,000
Other Administrative Action 9 · The atlanta JCC construction project suspension of work: effective october 12, 2018 pursuant to federal acquisition regulation (far) clause 52.242-14,… $0
Change Order 8 · The atlanta JCC construction project the item listed below resulting from several negotiations between DOL and 4K global-ACC, the last negotiations was… $30,000
Change Order 7 · The atlanta JCC construction project the items listed below show the final agreed to amounts resulting from several negotiations between DOL and 4K… $273,342
Change Order 6 · The atlanta JCC construction project 1.RFC 22 - sound wall credit (ASI-7 changes). The contract documents require the contractor to construct a sound wall along… -$500,000
Change Order 5 · The atlanta JCC construction project 1.RFC 17 (GC-16)- water treatment controller. Add bacnet communications card to water treatment system controller. The… $974
Change Order 4 · The atlanta JCC construction project 1.RFC 13- rock removal (unforeseen site condition) request for equitable adjustment (REA). No additional days added.… $29,532
Change Order 3 · The atlanta JCC construction project RFC no. 16- time extension: (180 days) 100 day compensable and 89 days non-compensable impact in part, was due to… $325,351
Change Order 2 · RFC-05B construct temporary parking lot (50 car spaces) RFC-06 doors and hardware (CHANGES) all other terms and conditions remain unchanged. $46,379
Change Order 1 · RFC-1. Add reinforcing steel RFC-2 pump out and remove septic tank RFC-3 temporary stabilization all other terms and conditions remain unchanged. $16,515
Original award $59,714,676
Show all 16

About this award

The Department of Labor Office of Job Corps awarded a $61,436,769.46 firm-fixed-price definitive contract to 4K Global-Acc JV, LLC, a women-owned small business joint venture, to provide construction services for a new Job Corps campus in Atlanta, Georgia. The project involves clearing, regrading, and preparing the 25-acre site, installing utilities, and constructing site infrastructure such as fencing, roads, landscaping, and stormwater management. This contract was set aside for small businesses and supports the relocation of the existing Atlanta Job Corps Center.

Description

This project is to provide construction services for a new job corps campus to replace the existing job corps center located in atlanta, GA. The new campus is comprised of approximately 25 acres at the aforementioned location, and the work consists of the following: clearing, regarding, and preparation of the existing site, which is currently wooded. Placement of all utilities required to serve the buildings, in addition to coordination with various utilities to tie into existing services, and with georgia power for coordination of placement of the primary electrical system and site lighting. Construction of the surface site work will include installation of all fencing, gates, roads, walks, landscaping, and grassed areas, in addition to construction of storm water management ponds and BIO retention areas.

Quick answers

Who was awarded contract 1630DC17C0024?

1630DC17C0024 was awarded to 4K Global-Acc JV, LLC by Office of the Assistant Secretary for Administration and Management (Department of Labor) on June 16, 2017.

How much is contract 1630DC17C0024 worth?

The government has obligated $29,102,437 on 1630DC17C0024. Its current value, with exercised options, is $61,436,769.

Which agency awarded contract 1630DC17C0024?

Office of the Assistant Secretary for Administration and Management (Department of Labor) awarded 1630DC17C0024, with funding from Atlanta Job Corps Center (Office of Job Corps).

Was contract 1630DC17C0024 competed?

The extent of competition for 1630DC17C0024 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award