Water service improvement project at FCI englewood
Ended Definitive Contract Awarded Last action
- Contract number
- 15BFA025C00000007
- Awardee
-
American West Construction, LLC UEI MJ5JQN3S3C46
- Awarding agency
-
BOP Field Acquisition Office
Regional Offices, Department of Justice
- Obligated
- $3,561,063
Award facts
- Opportunity
-
- FCI Englewood- Water Service Improvement Project Pre-Solicitation · 15BFA024B00000027 · Posted Aug 8, 2024
- Contract value 100% obligated
- $3,561,062.50 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Funding agency
- Federal Correctional Institution Englewood Correctional Facilities, Department of Justice
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Littleton, CO 80123, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $20,570 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $16,530 | |
| Supplemental Agreement for work within scope | $34,663 | |
| Supplemental Agreement for work within scope | $2,750 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $700,000 | |
| Original award | $2,786,550 |
About this award
The Federal Bureau of Prisons awarded a $3.56 million firm-fixed-price definitive contract to American West Construction, LLC for a water service improvement project at Federal Correctional Institution Englewood on February 10, 2025, under a total small business set-aside. The prime awardee is a service-disabled veteran-owned small business. The contract requires the contractor to provide all materials, labor, and equipment under Solicitation 15BFA024B00000027, with an ultimate completion date of November 9, 2026. Place of performance is Littleton, Colorado 80123.
The originating pre-solicitation, posted August 8, 2024 with responses due August 16, 2024, described replacing the existing main water pipeline at FCI Englewood. The work includes installing a new pipeline, primarily through trenching with some boring, and adding a second new public water utility connection. The notice was issued under NAICS 237110 (Water and Sewer Line and Related Structures Construction) with no set-aside and estimated a project value between $1,000,000 and $5,000,000 and a performance period of 246 calendar days. The award carried a total small business set-aside, which the pre-solicitation did not use.
Quick answers
Who was awarded contract 15BFA025C00000007?
15BFA025C00000007 was awarded to American West Construction, LLC by BOP Field Acquisition Office (Regional Offices) on February 10, 2025.
How much is contract 15BFA025C00000007 worth?
The government has obligated $3,561,063 on 15BFA025C00000007.
Which agency awarded contract 15BFA025C00000007?
BOP Field Acquisition Office (Regional Offices) awarded 15BFA025C00000007, with funding from Federal Correctional Institution Englewood (Correctional Facilities).
Was contract 15BFA025C00000007 competed?
The extent of competition for 15BFA025C00000007 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award