Design build FCI leavenworth

Ended Definitive Contract Awarded Last action

Contract number
15B70023C00000008
Awardee
Awarding agency
Obligated
$465,575,321

Award facts

Opportunity
Contract value 50% obligated
  • $465,700,349.00 Current, with exercised options
  • $927,629,119.71 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Bethesda, MD 20814, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00022 · Subtotal - negotiated mprs : $404,467.00 $889,739
Funding Only Action P00021 · 1 reimbursement for utilities until the accounts can be transferred to the government. $169,977
Other Administrative Action P00020 · 1) the project contract completion date was established in MOD 4 as july 8, 2026, and, by this modification, hereby extends the final completion date by 45 days… $0
Definitize Change Order P00018 · 1) MPR-031, equitable adjustment to wage rate, add: $297,061.00. $297,061
Supplemental Agreement for work within scope P00017 · 1) CPC-030 $238,650
Funding Only Action P00016 · MOD-016 ufms correction. $30
Supplemental Agreement for work within scope P00015 · 1) MPR-011, IT servers, add: $47,218.29 2) MPR-020, detention-grade toilet accessories, add: $124,689.00 3) MPR-025, PLC system redundancy, add: $166,745.00… $330,608
Other Administrative Action P00014 · Correcting the clin and funding totals to accurately reflect the previous modifications adjustments. $0
Supplemental Agreement for work within scope P00013 · 1) MPR-011, IT servers, add: $722,512.00 2) MPR-019, video management system, add: $90,827.00 total change: $813,339.00 $813,339
Supplemental Agreement for work within scope P00012 · 1) CPC-017, 2) CPC-021, 3) MPR-016, 4) MPR-017, 5) MPR-022, total change: $725,721.00 $725,721
Supplemental Agreement for work within scope P00011 · CPC-003, truck decontamination CPC-022, sealed polished concrete MPR-002, revisions to frames, doors, and hardware MPR-006, visual barrier MPR-014, fences,… $731,957
Supplemental Agreement for work within scope P00010 · Total change: (-$420,975.00) -$420,975
Change Order P00009 $271,964
Change Order P00008 · This unilateral modification authorizes clark to proceed with time-sensitive electrical, voice/data cables and jacks, IT server network, building automation,… $372,928
Other Administrative Action P00007 · Wage rate determination correction per DOL. $0
Supplemental Agreement for work within scope P00006 · CPC 004, EPA pond water removal, add: $578,144.65 CPC 015, high mast grounding loop, add: $0.00 CPC-0019, trap guard substitution, add: $0.00 CPC-0025, AO… $578,145
Supplemental Agreement for work within scope P00005 · MPR-005 for: $56,116.00 MPR-008 for: $33,310.00 MPR-009 for: $5,781.00 MPR-013 for: $226,119.00 CPC-007 for: $83,962.55 CPC-014 for: $0.00 total: $406,288.55 $406,289
Supplemental Agreement for work within scope P00004 · CPC 001 for $218,750.00 CPC 005 for $44,530.00 CPC 008 for $106,323.00 CPC 009 for $4,614.00 CPC-011 for $20,513.00 MPR-004 for $53,038.00 CPC-191 for four… $447,768
Supplemental Agreement for work within scope P00003 · CPC 002, "grading revisions", add: $100,658.00 CPC 006, "large rubble removal", add: $24,463.00 alternate proposals, no. 03, "hdpe for underground CHW and HHW… -$1,774,879
Other Administrative Action P00002 $0
Other Administrative Action P00001 · Design/build construction contract for FCI/FPC leavenworth, KS document BPQ 15B70022PR000290 reversed on 09/30/2022 $0
Original award $461,497,000
Show all 22

About this award

The Federal Bureau of Prisons awarded a definitive firm fixed-price contract to Clark Construction Group LLC for design and construction of a new medium security Federal Correctional Institution in Leavenworth, Kansas on August 7, 2023, with a ceiling value of $927.6 million and ultimate completion by September 11, 2026.

The solicitation, posted June 10, 2022, sought a design-build contract for a 52,000 gross square meter facility housing 1,152 inmates, with no set-aside designation. The contract evolved through a two-phase selection process evaluating past performance, technical qualifications, preliminary design, management approach, small business participation, and price. Place of performance is Bethesda, MD.

As of the most recent contract modification (August 7, 2023), the contract total is $465.7 million obligated, reflecting negotiated changes of $889,739. The pricing type is firm fixed-price.

SCI reporting shows significant labor mobilization and subcontracting depth. FY2024 invoiced $170.4 million across 83.0 FTEs and 172,824 contractor hours. FY2025 invoiced $231.2 million across 280 FTEs and 582,937 contractor hours, with 34 subcontractors performing 90% of contractor hours. Derived government-paid hourly rates declined from $985.86/hr in FY2024 to $396.60/hr in FY2025, reflecting the blended prime-and-subcontractor composition as execution scaled. Major subcontractors include Hockenbergs Equipment and Supply LLC (food service equipment), Epic Concrete Construction Inc. (concrete and paving), Capital Electric Construction Company Inc. (security electronic raceway), Faith Technologies Inc., South Western Communications Inc., and a multi-vendor team spanning structural steel erection, fire suppression, precast concrete, cast-in-place concrete, and plumbing trades.

Subawards

Subcontractor Amount Awarded
Hockenbergs Equipment And Supply, LLC Design build FCI leavenworth food service equipment $6,307,733
Epic Concrete Construction, Inc. Design build FCI leavenworth concret paving $3,353,666
Capital Electric Construction Company, Inc. Design build FCI leavenworth security electronic racyways, complete $18,852,590
Faith Technologies, Inc. Design build FCI leavenworth electrical $66,132,922
South Western Communications Inc. Design build FCI leavenworth security electronics general provisions $6,793,671
Ben HUR Construction Company Design build FCI leavenworth steel, precast, modular cell erection $11,283,750
API Group Life Safety USA LLC Design build FCI leavenworth fire suppression $4,694,667
Crossland Prefab LLC Design build FCI leavenworth precast structural concrete $13,322,000
Concrete Strategies LLC Design build FCI leavenworth cast-in-place concrete $19,750,000
Cerris Systems, Inc. Design build FCI leavenworth plumbing $90,789,057

Quick answers

Who was awarded contract 15B70023C00000008?

15B70023C00000008 was awarded to Clark Construction Group LLC by Central Office (Bureau of Prisons) on August 7, 2023.

How much is contract 15B70023C00000008 worth?

The government has obligated $465,575,321 on 15B70023C00000008. Its current value, with exercised options, is $465,700,349. Its potential value, with all options, is $927,629,120.

Was contract 15B70023C00000008 competed?

The extent of competition for 15B70023C00000008 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award