Glen elder DAM spillway chute replacement, glen elder unit, solomon division, pick-sloan missouri basin program, kansas

Ended Definitive Contract Awarded Last action

Contract number
140R6021C0015
Awardee
Awarding agency
Obligated
$44,680,730

Award facts

Opportunity
Contract value 99% obligated
$45,004,369.94 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Glen Elder, KS 67446, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00017 $1,477,602
Supplemental Agreement for work within scope P00015 $73,507
Supplemental Agreement for work within scope P00014 $1,913,320
Other Administrative Action P00013 $0
Definitize Change Order P00011 $2,094
Supplemental Agreement for work within scope P00012 $24,057
Other Administrative Action P00010 $0
Supplemental Agreement for work within scope P00009 $0
Funding Only Action P00008 $3,382,150
Change Order P00007 $0
Other Administrative Action P00006 $0
Supplemental Agreement for work within scope P00005 $0
Supplemental Agreement for work within scope P00004 $0
Funding Only Action P00003 $360,000
Supplemental Agreement for work within scope P00002 · This modification obligation obligates additional funding in accordance with WBR 1452.232-80 - limitation of funding $21,500,000
Funding Only Action P00001 $1,433,000
Original award $14,515,000
Show all 17

About this award

The Bureau of Reclamation awarded a $45 million definitive contract to Ames Construction, Inc. for replacement of the spillway chute at Glen Elder Dam in Kansas on October 8, 2021, under firm fixed-price terms with no set-aside.

Work includes demolition of the existing chute, excavation, concrete and shotcrete installation, and drainage installation at Glen Elder, KS. The ultimate completion date is June 30, 2025. NAICS code 237990 applies.

Service Contract Inventory reporting shows FY2024 invoicing of $5.6 million across 38.5 FTEs and 80,167 contractor hours, with a derived government-paid blended rate of $70.07 per hour. FY2023 invoicing was $3 million across 28.5 FTEs and 59,331 contractor hours at $51.12 per hour, indicating rising hourly rates year-over-year. Ames Construction subcontracted 13% of contractor hours to four subcontractors in FY2024.

Quick answers

Who was awarded contract 140R6021C0015?

140R6021C0015 was awarded to Ames Construction, Inc. by Bureau of Reclamation (Department of the Interior) on October 8, 2021.

How much is contract 140R6021C0015 worth?

The government has obligated $44,680,730 on 140R6021C0015. Its current value, with exercised options, is $45,004,370.

Was contract 140R6021C0015 competed?

The extent of competition for 140R6021C0015 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award