Bull lake DAM spillway modifications, riverton unit, pick-sloan missouri basin program, wyoming

Ended Definitive Contract Awarded Last action

Contract number
140R6018C0015
Awardee
Awarding agency
Obligated
$108,991,096

Award facts

Opportunity
Contract value 100% obligated
$108,991,096.04 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 8 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Riverton, WY 82501, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Definitize Change Order P00064 $0
Supplemental Agreement for work within scope P00063 $1,653,298
Supplemental Agreement for work within scope P00062 $1,338,961
Change Order P00061 $0
Definitize Change Order P00060 $0
Funding Only Action P00059 $5,000,000
Definitize Change Order P00058 $0
Change Order P00057 $0
Change Order P00056 $0
Supplemental Agreement for work within scope P00054 $2,525,430
Change Order P00055 $0
Change Order P00053 · The purpose of this modification is to direct the contractor to remove 41,031 SQ FT of geogrid from the temporary cofferdam area. $0
Change Order P00052 · The purpose of this modification is to direct the contractor to obtain additional zone 1A material offsite for the permanent cofferdam. $0
Change Order P00051 · The purpose of this modification is to direct the contractor to obtain zone 1A material offsite for the permanent cofferdam. $0
Definitize Change Order P00050 · The purpose of this modification is to definitize unilateral change order no. P00029. $0
Change Order P00049 · This modification is a change order directing the contractor to cut existing bridge plates to fit with the new bearing pads based on modified specifications and… $0
Change Order P00048 · This modification is a change order directing the contractor to install dewatering systems, use zone 5A material, install a chain link fence in a different… $2,700,000
Supplemental Agreement for work within scope P00047 · This modification provides equitable adjustment in response to serial letter 080, coronavirus and quarantine impacts. $0
Definitize Change Order P00046 · This modification definitizes unilateral change order no. P00016. $0
Supplemental Agreement for work within scope P00044 · This modification addresses the time period escalation for field office overhead for the additional 708 days of contract performance (due to GOV suspension). $0
Supplemental Agreement for work within scope P00045 · This modification provides equitable adjustment in response to serial letters 049 and 103, REA zone 4 material. $0
Change Order P00042 · This modification directs the contractor to perform investigative drilling and dewatering of the permanent cofferdam. $2,200,000
Supplemental Agreement for work within scope P00043 · This modification provides equitable adjustment for expired concrete materials (expired during government suspension). $0
Supplemental Agreement for work within scope P00041 · This modification provides equitable adjustment for REA NW corner wells. $0
Definitize Change Order P00040 · This modification definitizes unilateral modification no. P00019. $0
Definitize Change Order P00039 · This modification definitizes unilateral modification no. P00010 $0
Funding Only Action P00038 · This modification obligates additional funding. $5,000,000
Definitize Change Order P00035 · This modification definitizes unilateral modification no. P00004 and P00009 $0
Definitize Change Order P00037 · This modification definitizes unilateral modification no. P00008 and P00014 $0
Definitize Change Order P00036 · This modification definitizes unilateral modification no. P00036 $0
Funding Only Action P00034 $1,950,000
Supplemental Agreement for work within scope P00033 · This modification incorporates revisions to specs and drawings regarding the reinforcement in the crest structure walls $0
Change Order P00032 · This modification directs the contractor to construct external counterfort walls on the exterior of stilling basin walls on slabs 10 and 12 $500,000
Funding Only Action P00031 · This modification obligates additional funding $5,000,000
Change Order P00030 · This modification directs the contractor to install a layer of geotextile between the zone 2 - sand filter and zone 3 - gravel material $210,000
Change Order P00029 · This modification directs the contractor to provide additional zone 1A, misc fill materials, to address shortage. $1,400,000
Supplemental Agreement for work within scope P00027 · This modification incorporates a time extension of 709 calendar days from the 01 32 10-4 - construction program, time impact analyses for modification P00006… $0
Definitize Change Order P00028 · This modification provides an equitable adjustment for all work performed under unilateral modification no. P00007 $17,407
Funding Only Action P00026 $7,330,000
Funding Only Action P00025 · This modification obligates additional funding to cover additional costs of unilateral modifications until definitization $5,000,000
Change Order P00024 · This modification directs the contractor to install embankment measurement points in the stilling basin area $75,000
Change Order P00023 · This modification directs the contractor to complete land based lidar scans of the upper crest structure, spillway chute location, surrounding area, and other… $200,000
Funding Only Action P00021 · This modification obligates additional funding to cover some of the contractors costs of the suspension of work (july 2020) in advance of the suspension REA… $2,000,000
Change Order P00020 · This modification directs the contractor to construct the temporary access road so that the government drill RIG can perform additional testing in the… $450,000
Funding Only Action P00022 · This modification obligates additional funding to cover some of the contractors costs as a result of the differing site condition in the northwest corner $700,000
Funding Only Action P00018 · The purpose of this modification is to increase the limitation on cost for unilateral modification no. P00015 $6,000,000
Change Order P00017 · This unilateral modification incorporates revisions to specifications sections $0
Change Order P00019 · This modification directs the contractor to provide drilling support for government as they complete the cone penetration testing $500,000
Change Order P00016 · This unilateral modification directs the contractor to perform work necessary to correct damage to the top of the secant pile wall $40,000
Change Order P00015 · This unilateral modification directs the contractor to drill approximately 66 deep wells and additional piezometers as necessary to dewater the site $8,000,000
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The Bureau of Reclamation awarded a $109.0 million firm fixed-price definitive contract to Krew Heavy Civil LLC for Bull Lake Dam Spillway Modifications under the Riverton Unit of the Pick-Sloan Missouri Basin Program in Wyoming. The contract was awarded on September 20, 2018, with an ultimate completion date of September 16, 2024. Work will be performed in Riverton, Wyoming. No set-aside designation was used in this competitive solicitation, which was posted on June 27, 2017, with a due date of November 17, 2017.

The Pick-Sloan Missouri Basin Program is a comprehensive water resource development initiative spanning multiple states, and this contract represents a significant infrastructure investment in dam safety and operational improvements. The Bull Lake Dam spillway modifications project addresses critical structural and hydraulic needs at this important water management facility in the Riverton Unit, supporting irrigation, water supply, and flood control objectives in Wyoming's water resource management framework.

Quick answers

Who was awarded contract 140R6018C0015?

140R6018C0015 was awarded to Krew Heavy Civil LLC by Bureau of Reclamation (Department of the Interior) on September 20, 2018.

How much is contract 140R6018C0015 worth?

The government has obligated $108,991,096 on 140R6018C0015.

Was contract 140R6018C0015 competed?

The extent of competition for 140R6018C0015 was full and open competition. The government received 8 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award