Kortes river gauge power cable replacement

Ended Definitive Contract Awarded Last action

Contract number
140R4022C0003
Awardee
Awarding agency
Obligated
$429,068

Award facts

Contract value 100% obligated
$429,067.80 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Competitive 8(a)
Competition
1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Mills, WY 82644, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00002 · The purpose of this modification is to obligate the additional funds needed to cover the increased trenching costs due to differing site conditions. $93,461
Other Administrative Action P00001 · Kortes river gauge power cable replacement - P00001 $0
Original award $335,607

About this award

The Bureau of Reclamation awarded a definitive contract to JTR Excavation LLC, an 8(a)-certified small disadvantaged business, for Kortes River Gauge power cable replacement in Mills, Wyoming on March 18, 2022, under a competitive 8(a) set-aside. The contract ceiling is $429,067.80 on a firm fixed price basis.

This modification obligates additional funds to cover increased trenching costs due to differing site conditions. Ultimate completion is scheduled for May 31, 2023.

Quick answers

Who was awarded contract 140R4022C0003?

140R4022C0003 was awarded to JTR Excavation LLC by Bureau of Reclamation (Department of the Interior) on March 18, 2022.

How much is contract 140R4022C0003 worth?

The government has obligated $429,068 on 140R4022C0003.

Was contract 140R4022C0003 competed?

The government received 1 offer. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record