EL vado seepage reduction modification to DAM

Ended Definitive Contract Awarded Last action

Contract number
140R4020C0002
Awardee
Awarding agency
Obligated
$33,585,511

Award facts

Opportunity
Contract value 100% obligated
$33,585,510.79 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Not Competed · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Chama, NM 87520, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00024 · The purpose of this MOD is to extend the period of performance through september 30, 2025 so carpi can submit an invoice for work performed to button up the… $0
Supplemental Agreement for work within scope P00023 · The purpose of this MOD is to extend the period of performance from 26 march 2024 to 21 july 2024. $0
Supplemental Agreement for work within scope P00022 · The purposed of this MOD is to add funds for the collaboration meeting regarding design changes and includes travel. $64,000
Supplemental Agreement for work within scope P00021 · The purpose of this modification is to add funds for pilot test requirement from EPA and nmed. $48,905
Supplemental Agreement for work within scope P00020 · The purpose of this modification is to extend the period of performance through the off season to allow time to negotiate an appropriate period of performance… $0
Definitize Change Order P00019 · The purpose of this modification is to definitize P00015 for the grout cap effort. -$34,695
Change Order P00018 · The purpose of this modification is to increase the UN-definitized grout cap modification saw cutting quantity. $0
Change Order P00016 · The purpose of this undefinitized action is for a change in effort to the follow plate as identified in specification 05 50 00 metal fabrications. $0
Change Order P00017 · The purpose of this undefinitized modification is for work related to the cellular grout/backfill grouting redesign to proceed to prevent delays. $0
Change Order P00015 · The purpose of this undefinitized action is for redesign of grout cap due to differing site conditions. $660,000
Change Order P00014 · The purpose of this undefinitized action is for the design, fabrication and to furnish and install a faceplate restraint system within the capability of the… $0
Supplemental Agreement for work within scope P00013 · The purpose of this modification is to add in-scope travel and consulting services for testing the new grouting design $25,208
Supplemental Agreement for work within scope P00012 · The purpose of this modification is to change quantities for rock and common excavation. This will also increase the area for clearing and grubbing. $36,590
Supplemental Agreement for work within scope P00011 · The purpose of this modification is to increase quantities for faceplate repairs. $1,271,042
Change Order P00010 · The purpose of this unilateral undefinitized action is to add observation holes to the phase II grouting process. $0
Definitize Change Order P00009 · The purpose of this modification is to definitize P00006 for additional G18 port access. $15,190
Change Order P00008 $0
Change Order P00007 · The purpose of this modification is to revise the quantity of clin A14 from 385 to 480 for backfill grouting. This MOD also adds up to 10 observation holes.… $0
Change Order P00006 · The purpose of this modification is to revise the specifications 03 60 10 backfill grouting. This an undefinitized change order. $0
Supplemental Agreement for work within scope P00005 · Modification to incorporate changes to specifications and sections that weren't included with final copy. This modification also changes the COR to mark hruza… $0
Supplemental Agreement for work within scope P00004 · EL vado modification to add covid far clause 52.223-99 $0
Exercise an Option P00003 · EL vado modification to exercise the construction option clin 0030 $31,247,963
Other Administrative Action P00002 · Modification to change CO and COR for EL vado seepage reduction modification project $0
Other Administrative Action P00001 · EL vado seepage reduction modification $0
Original award $251,308
Show all 25

About this award

This is a firm-fixed price contract awarded by the U.S. Bureau of Reclamation to C.A.R.P.I., U.S.A., Inc. (doing business as Carpi USA) for the El Vado Seepage Reduction Modification to Dam project. The contract, valued at $33,585,510.79, is a two-phase effort that includes design review, consultation, site preparation, grouting, repair work, and installation of a geomembrane liner on the El Vado Dam in New Mexico. This is a dam safety project that was sole-sourced to Carpi USA under the justification of 41 U.S.C. 3304(a)(1) and FAR Subpart 6.302-1, as the agency determined Carpi USA was the only responsible source. There was no set-aside designation for this contract.

Quick answers

Who was awarded contract 140R4020C0002?

140R4020C0002 was awarded to C.a.r.p.i., U.s.a., Inc. by Bureau of Reclamation (Department of the Interior) on May 12, 2020.

How much is contract 140R4020C0002 worth?

The government has obligated $33,585,511 on 140R4020C0002.

Was contract 140R4020C0002 competed?

The extent of competition for 140R4020C0002 was not competed. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award