Black canyon switchyard and station service upgrades

Active Definitive Contract Awarded Last action

Contract number
140R1024C0005
Awardee
Awarding agency
Obligated
$7,787,076

Award facts

Opportunity
Contract value 100% obligated
$7,787,075.78 Current and potential, with all options
Completion date 87% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Emmett, ID 83617, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00007 $121,350
Change Order P00006 $169,497
Change Order P00005 · Black canyon switchyard and station service upgrades conduit layout, equip pad sizing, and fence gate drawing and specification changes. $91,185
Other Administrative Action P00004 · The purpose of this modification is to change the contracting officer from colby clifford to kasey aldrich. $0
Supplemental Agreement for work within scope P00003 $0
Other Administrative Action P00002 · Black canyon switchyard and station service upgrades: the purpose of modification P00002 is to change the contracting officer. $0
Supplemental Agreement for work within scope P00001 · Black canyon switchyard and station service upgrades: modification P00001 s a no-cost, bilateral modification incorporating specification changes related to RFI… $0
Original award $7,405,044

About this award

The Bureau of Reclamation awarded a $7.79 million definitive contract to Yellowstone Electric Co for switchyard and station service upgrades at Black Canyon on August 12, 2024, under a total small business set-aside. The awardee is a woman-owned small business.

The originating solicitation, posted November 30, 2023, covers removal and replacement of unit switchgear and station service transformers at the Black Canyon Switchyard located approximately six miles northeast of Emmett, Idaho, with work scope including conduit layout, equipment pad sizing, and fence gate drawing and specification changes. Place of performance is Emmett, ID 83617. The contract is firm fixed price with an ultimate completion date of February 18, 2027.

In FY2025, the contract invoiced $927 thousand against a labor footprint of 0.1 FTEs, with the prime self-performing all reported hours.

Quick answers

Who was awarded contract 140R1024C0005?

140R1024C0005 was awarded to Yellowstone Electric Co by Bureau of Reclamation (Department of the Interior) on August 12, 2024.

How much is contract 140R1024C0005 worth?

The government has obligated $7,787,076 on 140R1024C0005.

Was contract 140R1024C0005 competed?

The extent of competition for 140R1024C0005 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award