- This is a Definitive Contract awarded by the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Yellowstone Electric Co, a woman-owned small business. The $49,394,902.63 firm-fixed-price contract is for the replacement of main transformers and iso-phase bus at an unspecified location. The contract has a total small business set-aside designation and a period of performance through December 31, 2025. Yellowstone Electric Co is a for-profit electrical...
- This is a $1,309,606.70 firm fixed price contract awarded by the U.S. Bureau of Reclamation, a civilian agency under the Department of the Interior, to Yellowstone Electric Co, a woman-owned small business. The contract is for the Fontenelle Unit Breaker Replacement project, which involves replacing electrical components at a hydroelectric facility in Kemmerer, Wyoming. The contract has a total small business set-aside and was awarded on September 15, 2015, with a final completion date of August...
- This contract is for the replacement of a station service transformer at a hydroelectric facility operated by the Department of the Interior's Bureau of Reclamation. The $550,468.93 firm fixed price contract was awarded to Yellowstone Electric Co., a woman-owned small business, on September 7, 2017. The work was completed by October 15, 2018 and involved the supply and installation of electrical equipment and components at the Montrose, Colorado facility. As a prime contractor, Yellowstone...
- This is a Definitive Contract awarded by the Department of the Interior's Bureau of Reclamation to Yellowstone Electric Co, a woman-owned small business, for $200,500.00. The contract is for the replacement of a station service transformer and the addition of gauges and cable on the KR2B transformer at a facility in Dutch John, Utah. The contract has a firm fixed price and has no set-aside designation. Yellowstone Electric Co has received over $11 million in federal contracts from the Department...
- This is a definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Yellowstone Electric Co, a woman-owned small business, to manufacture and deliver 115 kV transformers. The contract has a firm fixed price of $15,501,226.69 and a completion date of May 4, 2012. The contract did not have a set-aside designation. As a prime contractor, Yellowstone Electric has received over $11 million in federal contracts from agencies like the Department of the Interior to supply and install...
- This is a firm fixed price delivery order awarded by the Department of the Interior Bureau of Reclamation to Yellowstone Electric Co, a for-profit woman-owned small business. The $718,104.49 contract is for the installation of a transformer at the Davis Dam Power Plant as part of the agency's "Generator Step Up (GSU) Transformer Replacements for Davis Dam Power Plant IDIQ" program. This work is not designated as a small business set-aside. Yellowstone Electric Co has received over...
- The Department of the Interior Bureau of Reclamation awarded a Firm Fixed Price definitive contract to Yellowstone Electric Co, a for-profit woman-owned small business (WOSB), for the DAVIS DAM UNIT BREAKER REPLACEMENT, PARKER-DAVIS PROJECT in Bullhead City, Arizona. The 585-calendar day contract has a potential value of $2,488,592.60 and was set aside for small businesses. Yellowstone Electric Co provides electrical equipment and services, including replacing transformers, switchgear,...
- This federal contract was awarded by the Department of the Interior Bureau of Reclamation to Yellowstone Electric Co, a woman-owned small business. The $655,764.07 firm-fixed-price delivery order contract is for the installation of a transformer as part of the "Generator Step Up (GSU) Transformer Replacements for Davis Dam Power Plant Indefinite Delivery Indefinite Quantity (IDIQ)" program. The work is to be performed in Bullhead City, Arizona. Yellowstone Electric Co has previously...
- This is a federal contract award worth $683,821.67 to Yellowstone Electric Co, a woman-owned small business, for the demolition and installation of a new transformer at the Davis Dam Power Plant. The contract was awarded by the Bureau of Reclamation, a civilian agency within the Department of the Interior, under the "Generator Step Up (GSU) Transformer Replacements for Davis Dam Power Plant IDIQ" program. The contract has a firm fixed price and is a delivery order, but does not have...
- The U.S. Department of the Interior's Rocky Mountain Region has awarded a $88,044.00 Firm Fixed Price Purchase Order contract to Yellowstone Electric Co, a woman-owned small business, for the installation of an emergency backup generator at the Crow Water Treatment Plant in Crow Agency, Montana. This contract does not have a small business set-aside designation. Yellowstone Electric Co has a strong track record as a prime contractor, having been awarded over $11 million in federal contracts from...
The U.S. Bureau of Reclamation awarded a $7,405,044.08 firm-fixed price contract to Yellowstone Electric Co, a woman-owned small business, for the Black Canyon Switchyard and Station Service Upgrades project near Emmett, Idaho. The contract involves the removal and replacement of unit switchgear and station service transformers at the Black Canyon Switchyard. This project was designated as a total small business set-aside, with a period of performance through February 18, 2027. Yellowstone Electric Co, headquartered in Billings, Montana, has a strong track record of providing electrical engineering, installation, and maintenance services for federal agencies, particularly for power generation and water treatment facilities in the Western United States.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Black Canyon Switchyard and Station Service Upgrades | 140R1024R0008 | Department of the Interior Bureau of Reclamation | Award Notice 3/3 | 8/12/24, 11:48 AM | |
Black Canyon Switchyard Upgrades | 140R1024R0008 | Department of the Interior Bureau of Reclamation | Pre-Solicitation 1/3 | 11/30/23, 10:46 AM | |
Black Canyon Switchyard Upgrades | 140R1024R0008 | Department of the Interior Bureau of Reclamation | Solicitation 2/3 | 1/22/24, 1:01 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00003 | Supplemental Agreement for work within scope | $0 | 6/24/25 | |
| P00002 | Other Administrative Action | $0 | 4/15/25 | |
| P00001 | Supplemental Agreement for work within scope | $0 | 3/4/25 | |
| Not listed | Not listed | $7.4m | 8/12/24 |