The National Park Service Midwest Region awarded Wintrow Construction Co Inc a $542,667 firm-fixed price definitive contract to provide railroad tamping and crossing replacement services within Cuyahoga Valley National Park in Ohio. The scope of work involves tamping and aligning an eight-mile section of railroad track, replacing two full and one partial railroad crossings, as well as one pedestrian crossing, as requested in solicitation 140P6422R0008. The funding agency is the Department of the...
This is a definitive contract awarded by the National Park Service (NPS), Interior Regions 3/4/5, Ohio Major Acquisition Buying Office to Bush Basher Contracting LLC, a small business, for repairing and replacing fence segments at Bow Creek for the Missouri National Recreational River Headquarters in Yankton, South Dakota. The contract has a ceiling value of $15,490.80 and is a firm-fixed price contract. The contract was set aside 100% for total small businesses. The original solicitation was...
The Department of the Interior National Park Service Midwest Region awarded a $327,693.84 firm-fixed price contract to RW Clark Co, a self-certified small disadvantaged business, for the Valley Gate Replacement Project at Cuyahoga Valley National Park in Brecksville, Ohio. The contract, which was set aside for small businesses, requires the demolition of existing gates and the fabrication and installation of 21 new gates at 19 locations, with options for an additional 11 gates. The work involves...
This federal contract award to Diamond S Fencing Inc., a self-certified small disadvantaged and veteran-owned business, is for the purchase and installation of a 6-foot-high chain link fence with 3 strands of barbed wire at Yellowstone National Park. The contract, valued at $61,427.54, was awarded by the U.S. Department of the Interior's National Park Service Intermountain Region and is designated as a total small business set-aside. The work, which must be completed within 65 days of the notice...
This is a $249,650.00 firm-fixed price purchase order contract awarded by the National Park Service, a component of the Department of the Interior, to The Mensah Group Inc., a small disadvantaged business, to replace approximately 2,120 linear feet of perimeter fencing at the Carter Barron Amphitheatre in Washington, D.C. The contract was set aside for small businesses and has a performance period ending on January 13, 2025. The original solicitation was a pre-solicitation notice issued by the...
This is a $856,000 firm-fixed price contract awarded to Brannon Contracting & Maintenance Services, LLC, a service-disabled veteran-owned small business (SDVOSB), by the Ohio National Guard. The contract is for the removal and replacement of approximately 6,175 linear feet of perimeter security fencing at Camp James A. Garfield Joint Military Training Center in Ravenna, Ohio. This project was originally solicited as an unrestricted procurement, but was set aside for SDVOSB contractors....
The National Park Service awarded a $2,280,000 firm fixed price contract to Akron Building & Outdoor Maintenance Inc. to perform riverbank stabilization work along 1,250 linear feet of riverbank along the Valley Railway within Cuyahoga Valley National Park in Northfield, Ohio. The contract has a completion date of July 15, 2024. As a 100% set-aside for total small businesses, this definitive contract for OTHER CONSTRUCTION, RIVERBANK STABILIZATION PROJECT was awarded under a pre-solicitation...
This definitive contract awarded by the Department of the Interior National Park Service Midwest Region is valued at $375,000 to Mary ANN Houle Interprizes for replacing approximately 5.84 miles of boundary fence at Theodore Roosevelt National Park in North Dakota. The firm fixed price contract requires the prime contractor to furnish labor, equipment, and materials to remove the existing fence and install new woven wire fencing with steel posts between April 15, 2022 and the completion date...
The U.S. National Park Service, Intermountain Region, awarded a $105,698.00 firm-fixed-price construction contract to Cargill Fence Co, LLC, a self-certified small disadvantaged business located in Oregon. The contract is for the construction of a water source fence at the Madison Junction in Yellowstone National Park. This contract is a definitive contract with a completion date of November 30, 2016. Cargill Fence Co, LLC specializes in fence construction, repair, and related services for...
The Department of the Interior National Park Service Midwest Region awarded a $186,048.00 firm-fixed-price contract to Wintrow Construction Corp, a self-certified small disadvantaged business and woman-owned company, for the EPREF Construction, Railroad Tie Replacement Project. The contract involves the removal and replacement of 1,550 pre-selected out-of-face treated wood crossties, out-of-face surfacing and regulating of 2,000 linear feet of mainline track, and the provision of 500 tons of...
This federal contract award to Jagger Construction LLC is for the removal and replacement of approximately 2,170 linear feet of fencing at the Hammond-Cranz property in Cuyahoga Valley National Park in Ohio. The $90,608 firm-fixed price contract was awarded by the Midwest Region of the National Park Service, a civilian agency within the U.S. Department of the Interior. The work includes demolition and disposal of existing fence materials as well as installation of new wooden fence posts, railings, pickets, and hardware. This project was set aside for small businesses, and Jagger Construction LLC is a self-certified small disadvantaged business. Based on the firm's prior experience, they appear to specialize in construction projects related to stream bank stabilization, erosion control, and flood mitigation for government agencies in the Midwest region.