Grca 190083 / 250176 - improve potable water supply to inner-canyon and south rim, trans-canyon water distribution pipeline, grand canyon national park, AZ

Active Definitive Contract Awarded Last action

Contract number
140P2023C0001
Awardee
Awarding agency
Obligated
$226,387,484

Award facts

Opportunity
Contract value 100% obligated
$226,387,484.00 Current and potential, with all options
Completion date 76% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Grand Canyon Village, AZ 86023, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00040 $1,700,000
Supplemental Agreement for work within scope P00039 $61,019
Supplemental Agreement for work within scope P00038 $0
Supplemental Agreement for work within scope P00037 $0
Supplemental Agreement for work within scope P00036 $1,354,201
Supplemental Agreement for work within scope P00035 $5,130,396
Supplemental Agreement for work within scope P00034 $1,176,368
Supplemental Agreement for work within scope P00033 $0
Supplemental Agreement for work within scope P00032 $1,662,991
Supplemental Agreement for work within scope P00031 $0
Supplemental Agreement for work within scope P00030 $0
Supplemental Agreement for work within scope P00029 $78,332
Supplemental Agreement for work within scope P00028 $0
Supplemental Agreement for work within scope P00027 $143,208
Supplemental Agreement for work within scope P00026 $0
Supplemental Agreement for work within scope P00025 $3,755,050
Supplemental Agreement for work within scope P00024 $292,742
Supplemental Agreement for work within scope P00023 $1,348,243
Supplemental Agreement for work within scope P00022 $0
Supplemental Agreement for work within scope P00021 $345,844
Supplemental Agreement for work within scope P00020 $0
Supplemental Agreement for work within scope P00019 $49,610
Supplemental Agreement for work within scope P00018 $0
Supplemental Agreement for work within scope P00017 $0
Definitize Change Order P00016 $148,704
Definitize Change Order P00015 $102,419
Definitize Change Order P00014 $518
Supplemental Agreement for work within scope P00013 $0
Supplemental Agreement for work within scope P00012 $0
Supplemental Agreement for work within scope P00011 $38,859
Supplemental Agreement for work within scope P00010 $12,404
Supplemental Agreement for work within scope P00009 $0
Supplemental Agreement for work within scope P00008 $84,296
Supplemental Agreement for work within scope P00007 $254,929
Supplemental Agreement for work within scope P00006 $416,526
Supplemental Agreement for work within scope P00005 $42,368
Supplemental Agreement for work within scope P00004 $0
Supplemental Agreement for work within scope P00003 $94,939
Supplemental Agreement for work within scope P00002 $114,059
Supplemental Agreement for work within scope P00001 $0
Original award $207,979,459
Show all 41

About this award

The National Park Service awarded a $226.4 million definitive contract to Stronghold Engineering Inc., a minority-owned, woman-owned, and Asian-Pacific American-owned small business, for replacement and improvement of potable water systems at Grand Canyon National Park on March 14, 2023, with an ultimate completion date of January 8, 2028.

The originating pre-solicitation, posted February 24, 2022, sought comprehensive rehabilitation of Grand Canyon's primary water supply system, including new surface water intake and treatment facilities, replacement of distribution piping via open cut and slipline methods, installation of new storage tanks, and point-of-use disinfection systems serving inner canyon and south rim areas. The project addresses water delivery to remote areas requiring helicopter coordination for inner canyon operations. Work is firm fixed price with place of performance in Grand Canyon Village, Arizona.

Through fiscal 2025, Stronghold Engineering has invoiced $182.6 million across the contract's active years. FY2025 labor footprint stands at 95.1 FTEs performing 197,717 contractor hours; the derived government-paid blended rate (prime and subcontractor) was $371.46 per hour. The contractor engages 16 subcontractors, with approximately 47 percent of hours subcontracted. The blended hourly rate has declined year-over-year from $825.51 in FY2023 to $371.46 in FY2025, reflecting shift in work phase composition and subcontractor deployment as the project advances.

Quick answers

Who was awarded contract 140P2023C0001?

140P2023C0001 was awarded to Stronghold Engineering Inc. by National Office (National Park Service) on March 14, 2023.

How much is contract 140P2023C0001 worth?

The government has obligated $226,387,484 on 140P2023C0001.

Was contract 140P2023C0001 competed?

The extent of competition for 140P2023C0001 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award