Definitive Contract 12445526C0034
- Not listed
- The U.S. Forest Service awarded a $130,523.50 firm fixed-price purchase order to Wayco Inc. on April 21, 2025, for paving and surface rehabilitation work at the Grey Towers National Historic Site in Milford, Pennsylvania. The scope of work includes removal and disposal of existing asphalt, placement of new asphalt materials, mobilization, culvert cleanout, aggregate base installation, concrete pad construction, machine grading, asphalt paving, and permanent pavement markings. The contract is...
- The USDA Forest Service Research Service Northern Research Station awarded a $15,918 firm fixed price delivery order to Ciervo And Sons Renovations, Inc. to complete plaster ceiling repair work at the Grey Towers National Historic Site mansion library in Milford, Pennsylvania. Performance will take place between September 15th and November 15th, 2023. As part of its mission to develop and deliver tools to sustain the health, diversity, and productivity of the nation's forests, the Forest Service...
- <p>This is a firm-fixed-price definitive contract awarded by the U.S. Department of Agriculture (USDA) Forest Service Research Service Northern Research Station to Waters Craftsman I, Inc., doing business as Water Craftsmen, for the restoration of a masonry wall at Grey Towers in Milford, Pennsylvania. The contract has a completion date of December 31, 2020 and a potential value of $231,625.00. It was set aside for small businesses.</p>
- <p>This is a definitive contract awarded by the U.S. Forest Service Research Service Northern Research Station, a civilian agency, to Waters Craftsman I, Inc. (doing business as Water Craftsmen) for $232,475.97. The contract is for masonry work to be performed at Grey Towers in Lehman Township, Pennsylvania, with an ultimate completion date of August 31, 2011. The contract has a firm fixed-price pricing type and does not have a set-aside designation.</p>
- The Forest Service Research Service Northern Research Station issued a delivery order to Sequoia Tree Inc. on February 5, 2024, with a ceiling value of $14,834 for tree removal and maintenance at Grey Towers National Historic Site in Milford, PA. The order was placed under a $2.5 million single-award Indefinite Delivery Contract awarded to Sequoia Tree Inc. in February 2024, covering comprehensive arboricultural services including tree pruning, removal, root work, cabling, bracing, and...
- The Department of Agriculture Forest Service Research Service Northern Research Station awarded a $6,840.72 firm fixed price delivery order to Ciervo And Sons Renovations, Inc. for facility maintenance and construction services at the Grey Towers facility in Milford, Pennsylvania. The delivery order was awarded on March 25, 2021 under an existing indefinite-delivery/indefinite-quantity contract vehicle and has a completion date of March 24, 2022. No set-aside designation was applied to this...
- The U.S. Department of Agriculture Forest Service awarded a $4,185 firm fixed price delivery order to Ciervo And Sons Renovations, Inc. for repointing work at Grey Towers in Milford, Pennsylvania. As part of ongoing maintenance and preservation efforts at the Eastern Region facility, the contract calls for Ciervo And Sons Renovations to perform repointing on the East Terrace to repair and waterproof masonry joints. No set-aside designation was used for this award issued under the Forest...
- This is a $1,193,654.00 Firm Fixed Price Definitive Contract awarded by the U.S. Forest Service Research Service Northern Research Station to the L.R. Costanzo Company, Incorporated for the BLACK LOCUST ALLEE RESTORATION PROJECT at the Grey Towers National Historic Site in Milford, Pennsylvania. The contract does not have a set-aside designation and was awarded on June 2, 2010, with a scheduled completion date of July 3, 2012. The contract is part of the Forest Service's broader efforts to...
- The U.S. Forest Service Research Service Northern Research Station awarded a firm-fixed-price delivery order contract to Ciervo And Sons Renovations, Inc., a minority-owned small disadvantaged business, for maintenance and HVAC services at the Grey Towers National Historic Site in Milford, Pennsylvania. The $11,380 contract has a period of performance through August 17, 2024 and is part of a larger indefinite delivery/indefinite quantity (IDIQ) contract that Ciervo And Sons Renovations holds...
- The Department of Agriculture Forest Service Research Service Northern Research Station awarded a $77,983.45 firm fixed price delivery order to Ciervo And Sons Renovations, Inc. for the GREY TOWERS DEICING CABLE SYSTEM REPLACEMENT project. The delivery order, which does not have a set-aside designation, calls for replacement of the deicing cable system at the Forest Service's Grey Towers National Historic Site in Milford, Pennsylvania by March 29, 2022. As the research arm of the Forest Service,...
The Forest Service Research Service Northern Research Station awarded a $380,296 definitive contract to Ocean Construction LLC for preservation and restoration of historic stone pavers, walkways, water features, and benches at Grey Towers National Historic Site, Pennsylvania, on July 14, 2026, under a total small business set-aside. Ocean Construction LLC is a minority-owned small disadvantaged business. The originating solicitation (RFP #1240LU25R0028) calls for restoration work at two primary locations—the Marble Court and Star & Diamond Terrace—including subgrade preparation, stone paver reconstruction, walkway step restoration, rehabilitation of concrete water features (the "Finger Bowl" and half-moon shaped pool), and repair of two stone benches adjacent to the Moat. Evaluation is by Lowest Price Technically Acceptable, with past performance, technical experience, and project management approach as technical factors. Work is performed at Milford, PA 18337 under firm fixed-price terms. Ultimate completion is December 30, 2026.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Grey Towers Historic Terrace and Walkways Preservation Construction, Pennsylvania (GAOA) | 1240LU25R0028 | Department of Agriculture Forest Service | Pre-Solicitation 1/3 | 8/5/25, 8:22 PM | |
Grey Towers Historic Terrace and Walkways Preservation Construction, Pennsylvania (GAOA) | 12445526Q0014 | Department of Agriculture Forest Service | Solicitation 2/3 | 3/24/26, 1:24 PM | |
Grey Towers Historic Terrace and Walkways Preservation Construction, Pennsylvania (GAOA) | 12445526C0034 | Department of Agriculture Forest Service | Award Notice 3/3 | 7/14/26, 2:20 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $380.3k | 7/13/26 |