Definitive Contract 12435H18C0005
- Not listed
- The Forest Service, an agency of the Department of Agriculture, awarded a $33,631 firm fixed price purchase order to Roberts Timber Co., Inc. of Eatonton, Georgia. The contract is for culvert replacement according to documentation attached to the original solicitation. It has a total small business set aside designation and work is to be completed by June 30, 2017 at the specified place of performance in Eatonton. The purchase order is associated with the Forest Service's ongoing...
- The Department of Agriculture Forest Service awarded a $274,427 firm fixed price definitive contract to Cp&G Construction LLC, doing business as Cp&G, to complete construction of Forest Service Road 404 Cane Creek Culvert Replacement in Georgetown, South Carolina. The solicitation sought replacement of an existing 10'9" x 6'7" x 47' culvert with a new 19' x 8'2" x 46' structural plate aluminum arch culvert. With a period of performance of 180 calendar days, the...
- This is a $749,325 firm fixed price delivery order awarded to Price Contracting Inc., a veteran-owned small business, by the U.S. Department of Agriculture Forest Service under the Great American Outdoors Act (GAOA) program. The contract is for the Knieff Creek Culvert Replacement Project, a task order executed against an Indefinite Delivery/Indefinite Quantity (IDIQ) road construction services contract. The project involves infrastructure upgrades on Forest Service lands, including culvert...
- This contract was awarded by the U.S. Department of Agriculture Forest Service R8-Southern Region to Robert Thomas, a sole proprietorship based in Blairsville, Georgia, for the installation of culvert pipes on Forest Service roads. The contract has a firm fixed price of $236,680.00 and a completion date of July 28, 2022. The contract was not set aside for any specific business type. Robert Thomas has previously performed road maintenance, gravel placement, culvert replacements, right-of-way...
- This is a firm fixed-price delivery order contract awarded by the U.S. Department of Agriculture's Forest Service, Region 8 - Southern Region, to Carl Mcdade Construction Inc., a veteran-owned small business. The contract, valued at $46,944.00, is for the replacement of culverts along the Pleasant Hill Sylamore area within the Ozark National Forests in Arkansas. The contract is part of the USDA North Road Construction Multiple Award Task Order Contract (MATOC), which provides road...
- This is a firm fixed-price BPA call order awarded by the U.S. Department of Agriculture (USDA) Forest Service to Snow Country Contracting Inc., an SBA-certified HUBZone small business. The $184,791.25 contract is for the replacement of a culvert along Forest Route 283 in the Chequamegon-Nicolet National Forest in Wisconsin. The work is being performed under the Northeast Zone - Region 9 Roads BPA, one of three active indefinite delivery vehicles the contractor holds with the Forest Service's...
- This contract award is for the construction of a culvert replacement on FR 2112 within the Lakewood-Laona Ranger District, funded by the U.S. Department of Agriculture (USDA) Forest Service. The $96,639.47 firm-fixed-price contract was awarded to the small business prime contractor Snow Country Contracting Inc., an SBA-certified HUBZone firm. The contract is a call order under the Forest Service's Northeast Zone - Region 9 Roads Blanket Purchase Agreement (BPA), an indefinite delivery vehicle...
- This federal contract was awarded by the U.S. Forest Service, a civilian agency, to A.G.C., Inc., a small business contractor, for the construction of a culvert replacement project titled "GAOA SF LOGAN CREEK CULVERT REPLACEMENT - CONSTRUCTION CONTRACT." The contract has a firm fixed price of $99,843.00 and is a delivery order under the Great American Outdoors Act (GAOA) Multiple Award Task Order Contract (MATOC). The contract has a completion date of November 30, 2024 and does not...
- This is a $747,721.55 firm-fixed price definitive contract awarded by the U.S. Department of Agriculture (USDA) Forest Service to Snow Country Contracting Inc., an SBA-certified HUBZone small business. The contract is to replace a culvert on Sidnaw Creek within the Ottawa National Forest in Michigan. The work involves surveying the site, removing an existing 12' x 8' corrugated metal pipe culvert, and installing a new 20' x 10' x 64' precast concrete box culvert to improve aquatic organism...
- This is a firm-fixed price contract awarded by the U.S. Department of Agriculture Forest Service R8-Southern Region to Circle V Harvesting CO., a small business, for a culvert replacement project on Forest Service Road 665A in the Sumter National Forest in South Carolina. The $167,466.62 contract involves replacing an existing reinforced concrete pipe culvert with a 4-sided precast concrete box culvert, including temporary stream diversion, excavation, backfill, stream simulation, road...
This contract, awarded by the U.S. Department of Agriculture Forest Service to Patton Excavation, a for-profit Subchapter S corporation, replaces two Civilian Conservation Corps (CCC)-era culverts and constructs two temporary bypass roads with temporary bridges on Mulky Gap Road in Gainesville, Georgia. The contract, which has a firm-fixed-price of $494,564.34, does not have a set-aside designation. The work was originally solicited as a competitive, unrestricted contract opportunity. The contract requires the replacement of a 15-foot long, 42-inch diameter culvert at Dixon Creek and a 22-foot long, 36-inch diameter culvert at Mulky Creek, as well as the construction of new concrete headwalls to match the original CCC-era masonry structures.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Construction - AOP Culvert Replacements at Mulky Gap and Dixon Creek | 12435H18R0007 | Department of Agriculture Forest Service R8-Southern Region | Solicitation 1/1 | 6/28/18, 5:36 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00005 | Change Order | $82.1k | 7/17/19 | |
| P00004 | Supplemental Agreement for work within scope | $0 | 5/20/19 | |
| P00003 | Supplemental Agreement for work within scope | $0 | 5/9/19 | |
| P00002 | Other Administrative Action | $0 | 3/27/19 | |
| P00001 | Supplemental Agreement for work within scope | $660 | 11/8/18 |