- Klessens Construction was awarded a $8,916 firm fixed price delivery order against the Custer Gallatin National Forest Road Maintenance and Light Construction IDIQ with the U.S. Department of Agriculture Forest Service, Region 1 - Northern Region. This task order calls for road maintenance services for Northwest Energy for West Rosebud Road in Red Lodge, Montana, to be completed by September 30, 2021. The Beartooth Ranger District IDIQ provides road maintenance and light construction services...
- Klessens Construction was awarded a firm fixed price delivery order against the U.S. Forest Service's Custer Gallatin National Forest Road Maintenance and Light Construction IDIQ for the Beartooth Ranger District. Valued at approximately $27,690, this order is for road maintenance services within the Beartooth Ranger District under the agency's Fiscal Year 2021 program. No set-aside designation was applied to this award. Performance will occur in Red Lodge, Montana, with the U.S. Department of...
- Klessens Construction was awarded a firm fixed price delivery order against the USDA Forest Service R1-Northern Region's Beartooth Ranger District Road Maintenance and Light Construction IDIQ for an emergency culvert installation to provide fire equipment access to a needed area. The $0 delivery order was issued on July 29, 2021, with a completion date of September 30, 2021. No set-aside designation was applied to this award made under the Forest Service's Northern Region program for road...
- This is a $327,738.08 firm fixed-price contract awarded by the USDA Forest Service, Region 1 - Northern Region, to ED Baxter Construction, a small business sole proprietorship based in Billings, Montana. The contract is for the reconstruction of the Main Fork Rock Creek Road 2421 in the Custer Gallatin National Forest, Beartooth Ranger District, located in Carbon County, Montana. This is a set-aside contract for small businesses. The work may commence following the contractor's submission of...
- This is a $73,400 firm fixed price definitive contract awarded to Jody Klessens LLC, a for-profit construction company, by the USDA Forest Service's Northern Region. The contract is for the installation of a temporary bridge and placement of riprap to repair flood damage. Klessens Construction has previously performed road maintenance, grading, surfacing, and culvert replacement work for the Forest Service under several indefinite delivery contracts. This contract is not associated with a...
- This is a firm fixed-price delivery order awarded to Jody Klessens LLC, a small business prime contractor, by the USDA Forest Service (Region 1 - Northern Region). The order is for road maintenance services on the Beartooth Ranger District, including grading, surfacing, culvert replacements, and erosion control on forest access roads. The order has a ceiling value of $29,950.00 and a completion date of June 30, 2017. It was issued against the Custer Gallatin NF Road Maintenance 2016-2020...
- This is a $228,897.03 firm-fixed-price delivery order contract awarded to Tri State Excavating LLC, a small business based in Bozeman, Montana, to perform road and bridge construction work for the Custer Gallatin National Forest under the Region 1 Road and Bridge Construction MATOC. The contract is part of the FY25 Disaster Roads Project and will run through June 30, 2026. Tri State Excavating LLC has extensive experience providing infrastructure support, including road maintenance,...
- Klessens Construction was awarded a firm fixed price delivery order against the Custer Gallatin National Forest Road Maintenance and Light Construction IDIQ with the USDA Forest Service Northern Region. The $22,200 potential value order is for road maintenance and light construction services within the Beartooth Ranger District under the IDIQ's scope. No set-aside provisions were applied to this award. Performance will occur in Red Lodge, Montana through October 2021. The IDIQ vehicle and this...
- This federal contract award, valued at $79,597.96, was issued by the Region 1 - Northern Region of the U.S. Forest Service, a civilian agency, to Triple L Excavation LLC, a small business based in Stevensville, Montana. The contract is for the ENG FY25 GOOSE CREEK ROADS PUBLIC WORKS project, which is part of the Region 1 Road and Bridge Construction Multiple Award Task Order Contract (MATOC). This delivery order contract is for firm fixed-price road and bridge construction services, with an...
- This contract is for maintenance work along the Elk City Wagon Road on the Nez Perce-Clearwater National Forests in Idaho. The U.S. Forest Service is the funding agency, and the work is being performed under the Great American Outdoors Act. The contract was awarded to K2 Excavation & Construction, LLC, a service-disabled veteran-owned small business (SDVOSB) based in Terrebonne, Oregon. The contract has a ceiling value of $400,150.97 and is a firm fixed-price definitive contract. The work...
Klessens Construction was awarded a $859,798.40 definitive contract by the USDA Forest Service Northern Region to reconstruct approximately 4.27 miles of the Main Fork Rock Creek Road #2421 located on the Custer Gallatin National Forest in Montana. The firm fixed price contract is being funded through the Great American Outdoors Act program. Per the original solicitation, the work includes reconditioning and surfacing the roadway, replacing one culvert, installing traffic control measures, and placing boulders for erosion control, with completion required within 60 days of the notice to proceed. Designated as a total small business set-aside, the contract is being performed in Red Lodge, Montana under NAICS code 237110 for highway, street, and bridge construction.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
GAOA CUSTER GALLATIN NATIONAL FOREST - Main Fork Rock Creek Road #2421 Reconstruction Project | 1240LU22B0001 | Department of Agriculture Forest Service R1-Northern Region | Award Notice 3/3 | 4/14/22, 11:06 AM | |
GAOA CUSTER GALLATIN NATIONAL FOREST - Main Fork Rock Creek Road #2421 Reconstruction Project | 1240LU22B0001 | Department of Agriculture Forest Service R1-Northern Region | Solicitation 2/3 | 3/4/22, 10:33 AM | |
GAOA CUSTER GALLATIN NATIONAL FOREST - Main Fork Rock Creek Road #2421 Reconstruction Project | 1240LU22B0001 | Department of Agriculture Forest Service R1-Northern Region | Pre-Solicitation 1/3 | 2/2/22, 6:18 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00003 | Change Order | $0 | 11/1/23 | |
| P00002 | Additional Work (new agreement, FAR part 6 applies) | $363.8k | 6/22/23 | |
| P00001 | Change Order | $0 | 7/29/22 | |
| Not listed | Not listed | $496.0k | 4/11/22 |