Definitive Contract 12034320C0021
Award Date 4/3/20
Potential Completion Date 5/30/22
Potential Value $9.7K
Funding Federal Agency
Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
Set-Aside Type
Total Small Business
Federal Contract Vehicle
- Not listed
Extent Competed
Competed under SAP
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Libby, MT 59923, USA
Solicitation Procedures
Simplified Acquisition
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a $149,468 definitive contract awarded by the Operations Center Intermountain, a civilian agency, to S&K Engineering and Research, LLC, a tribally owned small disadvantaged business that is a subsidiary of the Confederated Salish and Kootenai Tribes. The contract is for the reconstruction of the Teepee Creek Bridge under the American Recovery and Reinvestment Act (ARRA) Capital Improvement and Maintenance program. The contract has a firm fixed price pricing type and was set aside for...
- <p>The Defense Logistics Agency Troop Support awarded a $273 firm fixed price delivery order contract to The Conrad Company of Memphis, Tennessee for the provision of 8507860310 CLAMP,BRIDGE. No set-aside designation was applied to this award made on December 13, 2020, with a completion date of February 11, 2021. The Conrad Company will deliver the requested bridge clamps to support hardware needs under the Agency's procurement and supply chain programs.</p>
- This is a $6,204,376.08 definitive contract awarded by the Federal Highway Administration, a civilian agency, to Record Steel and Construction, Inc. (RSCI) for the Williams Creek (Shoup) Bridge Replacement project in Salmon, Idaho. The contract is a firm fixed-price arrangement with no set-aside designation. RSCI, a for-profit HUBZone joint venture, is the prime contractor. Key subcontractors include Idaho Construction & Development LLC and Inland Crane Inc., who were awarded subcontracts...
- The Forest Service awarded a $42,493 firm fixed price delivery order contract to River Design Group, Inc., dba Flathead Geomatics, for bridge inspections in the Kootenai National Forest in Libby, Montana. As part of its regular maintenance and safety programs, the Forest Service requires qualified contractors to perform detailed inspections of bridges and structures throughout the national forests. This delivery order was issued against an existing Indefinite Delivery/Indefinite Quantity...
- <p>This is a $56,150.00 firm fixed price definitive contract awarded by the U.S. Department of Agriculture, Forest Service to Koocanusa Excavating, Inc. for the ARRA / Kootenai National Forest trail bridges replacement project. The contract includes the replacement of the Little Therriault Trail Bridge, Rock Creek Trail Bridges 2 and 4, and the St. Paul Trail Bridge. This contract does not have a set-aside designation. The work is to be completed by April 1, 2011.</p>
- The Federal Highway Administration awarded a $6,737,948.97 firm-fixed-price contract to Krci LLC, a small disadvantaged business, for the construction of a new 125-foot precast deck bulb T girder bridge in Cle Elum, Washington. The project involves demolishing the existing concrete bridge and constructing the new bridge with abutments on cast-in-drilled piles. Major subcontractors include Malcolm Drilling Company, Inc., Combined Construction Inc., Columbia Basin Striping LLC, B&B...
- This is a $594,299.81 firm fixed-price contract awarded by the U.S. Department of Agriculture's Intermountain Operations Center to Engleman Steel Erection, Inc. to perform the TAS Recovery Clearwater NF Forest-Wide Trail Bridge Repair Project. The project involves deferred maintenance on a trail suspension bridge in the Lochsa Corridor. The contract was awarded under the American Recovery and Reinvestment Act (ARRA) Major Program Code for Forest Service Capital Improvement and Maintenance,...
- The U.S. Forest Service awarded a $205,800 firm-fixed-price purchase order contract to Western Wood Structures, Inc. for the Palisades Ranger District to purchase five trail bridges. The bridges are four 50-foot stringer glue-laminated timber bridges that meet specifications for pack and saddle use. This requirement was set aside for total small business participation. The bridges will be delivered to the Rainey Creek Trailhead in Swan Valley, Idaho by June 28, 2024 to support the Rainey Creek...
- Morrison-Maierle Incorporated has been awarded a $30,148.80 firm fixed price delivery order against an unidentified contract vehicle to provide geotechnical specialist services in support of the Kootenai Falls Swinging Bridge construction project. The U.S. Department of Agriculture Forest Service, Northern Region, will fund the contract to review shop drawings and submittals for the bridge reconstruction taking place in Libby, Montana through December 2019. No set aside designation or...
- This $65,500 firm fixed-price purchase order was awarded by the U.S. Forest Service, Intermountain Region, to RTI Fabrication, Inc., a small disadvantaged business, for the supply and delivery of a new 35-foot prefabricated steel bridge. The bridge is to be designed for HL-93 loading, delivered in two longitudinal segments, and have a galvanized corrugated steel deck with a treated timber wearing surface. This purchase order is funded under the Infrastructure Investment and Jobs Act (IIJA)...
KOOTENAI SWINGING BRIDGE CLIP INSTALLATION
Posted 4/3/20
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00001 | Change Order | $1.8k | 11/29/21 | |
| Not listed | Not listed | $7.9k | 4/3/20 |