Recovery - advanced mtering services

Ended Awarded Last action

Contract number
GSP0410BV0102
Awardee
Awarding agency
Obligated
$2,040,745

Award facts

Contract value 100% obligated
$2,040,745.24 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition · 0 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Atlanta, GA 30303, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PS28 · Arra RE-commissioning services -$3,456
Supplemental Agreement for work within scope PS27 · Modification to extend time to allow for work completion and closeout. $0
Other Administrative Action PS26 · Metering projects R4 $25,652
Supplemental Agreement for work within scope PS25 · Installation of additional meters/adjustment to meters to multiple buildings under the currently standing contract. $11,991
Supplemental Agreement for work within scope PS24 · The following work/installation is being added: *RE-visit for GSA network problem - MS0009AA (DAN russell annex); RE-visit for power shutdown at - TN0004ZZ… $27,438
Supplemental Agreement for work within scope PS23 · Installation of additional meters/adjustment to meters at the U.S. EPA building in athens, GA under the currently standing contract. $49,892
Change Order PS22 · The purpose of this modfication was to incorporate local runs required to complete the project. $92,442
Supplemental Agreement for work within scope PS21 · To deobligate arra funds for work not received -$248,182
Other Administrative Action PA19 · This is an administrative modification to change building numbers. $0
Supplemental Agreement for work within scope PS20 · Increase scope of work with additional work $113,567
Supplemental Agreement for work within scope PS18 · Additional meters to be installed to the contract $34,502
Other Administrative Action PA17 · This is an administrative MOD to change the act # $0
Supplemental Agreement for work within scope PS14 · Add additional meters $8,333
Supplemental Agreement for work within scope PS16 · Add local runs to the contract $36,977
Supplemental Agreement for work within scope PS13 · Adding one electric meter to the existing contract $247,189
Supplemental Agreement for work within scope PS15 · To add local runs to the contract $29,244
Supplemental Agreement for work within scope PS11 · To delete gas and water meters for various loations -$247,189
Supplemental Agreement for work within scope PS12 · To add one additoinal electric meter $11,395
Supplemental Agreement for work within scope PS10 · Add additoinal metering to the contract for varioius buildings $108,301
Supplemental Agreement for work within scope PS09 · Adding additional metering for kefauver FB $5,242
Change Order PS08 · Arra metering adding 3 more gas meters and 2 more water meters at the howard baker bldg in knoxville, TN $83,590
Other Administrative Action PA07 · ADM MOD to add project manager to contract $0
Other Administrative Action PA06 · Recovery - administrative MOD to change contracting officers from bobbie clark to wylene bell $0
Other Administrative Action PA05 · Recovery a. This modification is issued at the request of budget to correct ORG code. The ORG code is changed to read as follows:… $0
Supplemental Agreement for work within scope PS04 · Recovery. Modification to install electrical meters at SAM nunn federal center atlanta, GA. $70,204
Supplemental Agreement for work within scope PS03 · Recovery: to perform reconfigurations for piping required for metering installations and to install electric meters at the low building. $53,976
Supplemental Agreement for work within scope PS01 · To provide additional meters ( gas, electric, and cooling towers) installtions for specified buildings. Additions were added due to site visit findings. $269,965
Other Administrative Action PA02 · Advanced metering installations $0
Original award $1,259,673
Show all 29

About this award

This is a federal contract award from the General Services Administration (GSA) to Geo-Marine, Inc. (GMI), a subsidiary of Versar, Inc. The contract is for "RECOVERY - ADVANCED MTERING SERVICES" and has a ceiling value of $2,040,745.24. It is a Blanket Purchase Agreement (BPA) Call with a firm fixed price pricing type. The contract has an ultimate completion date of April 30, 2014 and was awarded on September 29, 2010. The place of performance is Atlanta, GA. This contract does not have a set-aside designation.

The parent company, Versar, Inc., is a global project management company that provides a wide range of professional services to the U.S. federal government, including engineering, environmental consulting, construction management, and program support services. Versar holds several significant federal contract Indefinite Delivery Vehicles (IDVs) with agencies such as the Environmental Protection Agency, the Department of Health and Human Services Food and Drug Administration, and the U.S. Army Corps of Engineers, demonstrating its technical expertise and versatility in supporting government initiatives.

Quick answers

Who was awarded contract GSP0410BV0102?

GSP0410BV0102 was awarded to Geo-Marine, Inc. by Region 4 (Public Buildings Service) on September 29, 2010.

How much is contract GSP0410BV0102 worth?

The government has obligated $2,040,745 on GSP0410BV0102.

Is contract GSP0410BV0102 an order under another contract?

Yes. GSP0410BV0102 is a BPA call under GS10F0359L-GS23FPE019, a blanket purchase agreement.

Was contract GSP0410BV0102 competed?

The extent of competition for GSP0410BV0102 was full and open competition. The government received 0 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award