Rio Consumnes Correctional Center New Potable Water Tank
Closed State & local contract opportunity Posted
- Solicitation number
- 4689
- State
- California
- Responses due
Opportunity facts
- Jurisdictions
- NIGP code
- Point of contact
-
- Terry Keys keyst@saccounty.gov (916) 876-6367
Opportunity details come from procurement.opengov.com. Updated .
About this opportunity
Sacramento County is soliciting bids for design and construction of a new 350,000-gallon potable water prestressed concrete tank at Rio Consumnes Correctional Center, with sealed bids due October 15, 2026 at 2:00 p.m. and a mandatory pre-bid meeting on September 16, 2026 at 10:00 a.m. A Class A California contractor license is required, and the project is subject to prevailing wage requirements under California Labor Code sections 1720 and 1770.
The tank contractor must meet stringent minimum qualifications: at least ten years of experience designing and constructing AWWA D110 Type I strand-wound, prestressed concrete tanks, with five of those ten tanks located in seismic zones with mapped spectral response acceleration (Ss) of 0.626g or greater and in successful service for at least five years. The contractor must submit sealed design drawings and calculations by a California-registered engineer suitable for building permit approval.
Scope includes site preparation, construction of a gravel access road surrounding the tank, installation of water lines and electrical conduit connecting the tank to the existing water treatment facility, and all associated civil, structural, and electrical work. The tank must be 46 feet inside diameter with 30-foot water depth, designed per AWWA D110, ACI 350.3, and ASCE 7-10 standards. The contractor or designated tank prestressor must operate two operable automated strandwrapping systems and two operable automated shotcrete machines with continuous electronic monitoring capability.
The estimated construction cost is $4,906,288. Contract duration is 380 calendar days from execution. Liquidated damages are $4,778 per calendar day for delays beyond completion. The three lowest bidders must submit escrow bid documents. Bid security of ten percent is required as a bid bond, certified check, or cashier's check; performance and payment bonds each equal 100 percent of contract price must be provided by the successful bidder.
All personnel entering the secure facility require background security clearance via the process detailed in Appendix C, submitted at least five business days prior to entry. Contractors must comply with California's CALGreen waste diversion mandate (65 percent minimum recycling of construction and demolition debris), submit waste management and erosion-control plans, and adhere to all facility regulations. Questions on the bid are due September 30, 2026 at 2:00 p.m., with County responses due October 7, 2026. Bids must be submitted electronically through Sacramento County's Electronic Bidding Portal; hand, fax, email, or postal submissions will not be accepted.
Opportunity text
The County of Sacramento ("County") is soliciting Bids from a qualified Tank Contractor ("Contractor") to provide design and construction services to construct a new 350,000 gallon potable water prestressed concrete tank at the Rio Consumnes Correctional Center ("RCCC"). The Contractor will complete site preparation and construction of a gravel access road surrounding the proposed tank. The Contractor will also install the proposed water lines and conduit to connect the tank to the existing water treatment facility. The Contractor will be required to submit design drawings and calculations for the proposed tank and foundation suitable for obtaining building permits sealed by an Engineer registered in the State of California.
This work will take place within a secure correctional facility. Background checks will be required to enter the facility. All regulations set forth by the facility shall be followed throughout the duration of the project. Security Background checks are required for all persons attending the mandatory pre-bid meeting. Follow the instruction on Appendix C for completing the background check.
- Tank contractor must meet the minimum requirements as specified in the Technical Specification 10 30 05 Strand Wound, Prestressed Concrete Tank attached to this solicitation.
- Provide at time of bid the submittals listed in Section 1.03 A of Technical Specifications, 13 30 05 and Appendix B of the Special Provisions.
- The three low bidders shall submit escrow bid documents.
Files