Smart Grid for Utilities and Facility Controls at NAF Atsugi, Japan

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
N40084-22-B-8003
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Kanagawa Japan

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks proposals to install a new direct digital control system and smart grid infrastructure at six facilities located at Naval Air Facility Atsugi in Japan. The Naval Facilities Engineering Command aims to procure goods and services to upgrade aging control systems and enable remote monitoring and control of energy-using equipment from the Far East Facility Energy Operations Center. Offerors must provide direct digital controls, network equipment, fiber optic cabling, integration with the base network and Control System Platform Enclave, and meet Risk Management Framework requirements. Proposals are due by August 9, 2022. Evaluation criteria will consider the offeror's technical approach, management plan, and price.

There is no set-aside designation for this opportunity. The project's NAICS code is 238210 and PSC code is R499. The estimated value of the construction contract ranges from 100 million to 500 million Japanese Yen. The place of performance is Kanagawa, Japan at the six specified facilities located on Naval Air Facility Atsugi.

Notice text

8 versions

Update #8 · Latest ·

29 July 2022

Amendment 0006 is hereby issued.  The purpose of this amendment is to provide government responses. See document N40084-22-B-8003 0006 and attachments for additional details.

***********************************************************

27 July 2022

Amendment 0005 is hereby issued.  The purpose of this amendment is to provide government responses and extend bid submission due date. See document N40084-22-B-8003 0005 and attachments for additional details.

***********************************************************

26 July 2022

Amendment 0004 is hereby issued.  The purpose of this amendment is to provide final design spec and drawings, and the environmental report.  See document N40084-22-B-8003 0004 and attachments 1,2, and 5 for more details.

***********************************************************

22 July 2022

Amendment 0003 is hereby issued.  The purpose of this amendment is to provide Q&A for the solicitation and four (4) attachments for Question #7, #11, #12 and #15.  See document N40084-22-B-8003 0003 for more information.

***********************************************************

12 July 2022

Amendment 0002 is hereby issued.  This amendment schedules a second site visit and extends the bid submission due date.  See document N40084-22-B-8003 0002 for more information.

***********************************************************

27 June 2022

Amendment 0001 is hereby issued.  This amendment corrects a typo on site visit information.  See document N40084-22-B-8003 0001 for more information. 

***********************************************************

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Class J&A for Facilities Related Control Systems (FRCS) Johnson Controls Incorporated added in accordance with FAR 5.102(a)(6).

Update #7 ·

27 July 2022

Amendment 0005 is hereby issued.  The purpose of this amendment is to provide government responses and extend bid submission due date. See document N40084-22-B-8003 0005 and attachments for additional details.

***********************************************************

26 July 2022

Amendment 0004 is hereby issued.  The purpose of this amendment is to provide final design spec and drawings, and the environmental report.  See document N40084-22-B-8003 0004 and attachments 1,2, and 5 for more details.

***********************************************************

22 July 2022

Amendment 0003 is hereby issued.  The purpose of this amendment is to provide Q&A for the solicitation and four (4) attachments for Question #7, #11, #12 and #15.  See document N40084-22-B-8003 0003 for more information.

***********************************************************

12 July 2022

Amendment 0002 is hereby issued.  This amendment schedules a second site visit and extends the bid submission due date.  See document N40084-22-B-8003 0002 for more information.

***********************************************************

27 June 2022

Amendment 0001 is hereby issued.  This amendment corrects a typo on site visit information.  See document N40084-22-B-8003 0001 for more information. 

***********************************************************

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Class J&A for Facilities Related Control Systems (FRCS) Johnson Controls Incorporated added in accordance with FAR 5.102(a)(6).

Update #6 ·

26 July 2022

Amendment 0004 is hereby issued.  The purpose of this amendment is to provide final design spec and drawings, and the environmental report.  See document N40084-22-B-8003 0004 and attachments 1,2, and 5 for more details.

***********************************************************

22 July 2022

Amendment 0003 is hereby issued.  The purpose of this amendment is to provide Q&A for the solicitation and four (4) attachments for Question #7, #11, #12 and #15.  See document N40084-22-B-8003 0003 for more information.

***********************************************************

12 July 2022

Amendment 0002 is hereby issued.  This amendment schedules a second site visit and extends the bid submission due date.  See document N40084-22-B-8003 0002 for more information.

***********************************************************

27 June 2022

Amendment 0001 is hereby issued.  This amendment corrects a typo on site visit information.  See document N40084-22-B-8003 0001 for more information. 

***********************************************************

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Class J&A for Facilities Related Control Systems (FRCS) Johnson Controls Incorporated added in accordance with FAR 5.102(a)(6).

Update #5 ·

22 July 2022

Amendment 0003 is hereby issued.  The purpose of this amendment is to provide Q&A for the solicitation and four (4) attachments for Question #7, #11, #12 and #15.  See document N40084-22-B-8003 0003 for more information.

***********************************************************

12 July 2022

Amendment 0002 is hereby issued.  This amendment schedules a second site visit and extends the bid submission due date.  See document N40084-22-B-8003 0002 for more information.

***********************************************************

27 June 2022

Amendment 0001 is hereby issued.  This amendment corrects a typo on site visit information.  See document N40084-22-B-8003 0001 for more information. 

***********************************************************

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Class J&A for Facilities Related Control Systems (FRCS) Johnson Controls Incorporated added in accordance with FAR 5.102(a)(6).

Update #4 ·

12 July 2022

Amendment 0002 is hereby issued.  This amendment schedules a second site visit and extends the bid submission due date.  See document N40084-22-B-8003 0002 for more information.

***********************************************************

27 June 2022

Amendment 0001 is hereby issued.  This amendment corrects a typo on site visit information.  See document N40084-22-B-8003 0001 for more information. 

***********************************************************

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Class J&A for Facilities Related Control Systems (FRCS) Johnson Controls Incorporated added in accordance with FAR 5.102(a)(6).

Update #3 ·

27 June 2022

Amendment 0001 is hereby issued.  This amendment corrects a typo on site visit information.  See document N40084-22-B-8003 0001 for more information. 

***********************************************************

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Class J&A for Facilities Related Control Systems (FRCS) Johnson Controls Incorporated added in accordance with FAR 5.102(a)(6).

Update #2 ·

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Class J&A for Facilities Related Control Systems (FRCS) Johnson Controls Incorporated added in accordance with FAR 5.102(a)(6).

Update #1 ·

This project will include the provision of new DDC System at six (6) facilities at Naval Air Facility Atsugi, Japan with BACNet open protocol and an open license to be maintained by the installation. These facilities were selected based on analysis of
their annual energy consumption, square footage, and potential savings from DDC, and distance to planned network backbone. For all six facilities, the DDC will provide sufficient points to monitor and control all Heating Ventilation and Air Conditioning
(HVAC) chillers, fan coils, air handling units, potable hot water systems, variable air volume systems, direct expansion cooling, reheat boxes, package rooftop units, variable refrigerant flow (VRF) systems, computer room air conditioning, heat pumps, outdoor air units, boiler pumps, and package units currently installed in the facilities.


This project will provide an FRCS telecom cabinet rack to be installed inside the telecommunications room or an approved location for each of the six (6) DDC buildings. Also, provide DoD approved network equipment and cabling from DDC HVAC control system to base fiber optic connection location within the building. Provide OSP fiber optic cable. The DDC system network infrastructure must be integrated or connected to the Control System Platform Enclave (CSPE). Then, the monitoring and control will be done at the Far East Facility Energy Operations Center (FEOC), CFA Yokosuka. The demarcation point for this project is to establish
the connectivity to the CSPE, however, the integration work at the Central DDC Server located at Far East Facility Energy Operations Center (FEOC), CFA Yokosuka will be established by the Government.
 

A DDC server is not required to be provided at the ICS work desk in PW UEM Office. The six (6) buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future. Provide DoD approved network equipment and cabling to be integrated or connected to the SCADA server network switch to be connected to the CSPE. Provide RMF requirements into the construction bid package for the SCADA system. The integration of Advanced Metering Infrastructure System is not part of the Scope of Work of this project as discussed during the project kick-off meeting and confirmed by the Smart Grid Program Manager.


In accordance with DFARS 236.204, the magnitude of this construction project is estimated between Y100,000,000/$1,000,000 and Y500,000,000/$5,000,000.

Files

File Type Posted
Attachment 6 - Pre-Bid Inquiries_resp (All).pdf PDF
N40084-22-B-8003 0006.pdf PDF
Attachment 6 - Pre-Bid Inquiries (ALL).pdf PDF
N40084-22-B-8003 0005.pdf PDF
N40084-22-B-8003 0004.pdf PDF
N40084-22-B-8003 0003.pdf PDF
N40084-22-B-8003 0002.pdf PDF
N40084-22-B-8003 0001.pdf PDF
CJA Japan FRCS-Final_Signed_Redacted 21-JA-FECON-0020.pdf PDF
Att 3_SiteVisitRequestForm.xlsx XLSX spreadsheet
N4008422B8003.pdf PDF
Att 4_PreBidInquiryForm.xlsx XLSX spreadsheet
Show all 12

Notice history

Notice Type Posted
Smart Grid for Utilities and Facility Controls at NAF Atsugi, Japan Award Award Notice
This notice Latest solicitation Solicitation
Smart Grid for Utilities and Facility Controls at NAF Atsugi, Japan Pre-Solicitation
Smart Grid for Utilities and Facility Controls at NAF Atsugi, Japan Special Notice
Smart Grid for Utilities and Facility Controls at NAF Atsugi, Japan Original Pre-Solicitation

Similar open opportunities

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity