CO FTNP ROMO 11(4) Beaver Meadows Road
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 6982AF19B000022
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Rocky Mountain National Park, Colorado, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation involves a construction project to rehabilitate approximately 4.85 miles of Beaver Meadows Road within Rocky Mountain National Park in Colorado. The Federal Highway Administration seeks to rehabilitate the existing asphalt roadway through full depth reclamation, addition of 4 inches of new asphalt concrete, drainage improvements, and construction of concrete curb and gutter. Significant work items include 1.8 miles of reclamation, over 10,000 tons of asphalt paving, and 2,550 linear feet of colored concrete curb and gutter. Bids were due by December 10, 2019 with construction anticipated from May 2020 through October 2020.
The estimated total cost for the base project and three option items ranges from $5-7 million. There is no set-aside designation. The project's NAICS code is 237110 (Water and Sewer Line and Related Structures Construction) and PSC code is R499 (Miscellaneous repair, alteration and fabrication of non-military vehicles, ground support and test equipment). The government files identify Granite Construction Company and American Civil Constructors as the two responsive bidders. The place of performance is Rocky Mountain National Park in Colorado.
Notice text
4 versions
Update #4 · Latest ·
THIS PROJECT IS ADVERTISED ON A FULL AND OPEN BASIS.
THIS IS REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE AVAILABLE.
PROJECT NUMBER: CO FTNP ROMO 11(4)
PROJECT NAME: Beaver Meadows Road
PROJECT DESCRIPTION: This project provides 3R rehabilitation treatment for routes to include 4.85 miles of Beaver Meadows roadway within Rocky Mountain National Park. The project will also be lengthening and adding a FAST lane at Beaver Meadows Entrance Station which is approximately 1,400 feet.
The project consists of pulverizing the existing asphalt for additional base, concrete curb, drainage improvements, and repaving with approximately 4” of asphalt. The project will grade side slopes due to additional pavement thickness along shoulders. Pullouts directly adjacent to the roadway will also be treated and repaved as part of the project.
SIGNIFICANT QUANTITIES:
Significant Items for Schedule A include: 250 LNFT of Standard Underdrain, 1.8 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 10,750 TONS of Hot Asphalt Concrete Paving, 2,550 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,200 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option W include: 0.5 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 4,350 TONS of Hot Asphalt Concrete Paving, 3,050 LNFT of 12-Inch Colored Concrete Curb and Gutter, 1,500 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,500 CUYD of Roadway Excavation, and 400 CUYD of Subexcavation.
Significant Items for Option X include: 0.9 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 5,200 TONS of Hot Asphalt Concrete Paving, 270 LNFT of 14-Inch Mountable Colored Concrete Curb and Gutter, 1,200 LNFT of 14-Inch Colored Concrete Curb and Gutter, 100 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option Y include: 120 LNFT of Curb and Gutter Removal and Installation, 650 SQYD of Asphalt Patch, and 160 LNFT of Standard Underdrain.
COST RANGE: Estimated total cost for Schedule A, Option W, Option X, and Option Y is $5,000,000 to $7,000,000.
CONSTRUCTION DURATION: May, 2020 through October, 2020.
ADDITIONAL INFORMATION:
Anticipated Bid Opening: December 10, 2019
Anticipated Award: January 6, 2019
Update #3 ·
THIS PROJECT IS ADVERTISED ON A FULL AND OPEN BASIS.
THIS IS REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE AVAILABLE.
PROJECT NUMBER: CO FTNP ROMO 11(4)
PROJECT NAME: Beaver Meadows Road
PROJECT DESCRIPTION: This project provides 3R rehabilitation treatment for routes to include 4.85 miles of Beaver Meadows roadway within Rocky Mountain National Park. The project will also be lengthening and adding a FAST lane at Beaver Meadows Entrance Station which is approximately 1,400 feet.
The project consists of pulverizing the existing asphalt for additional base, concrete curb, drainage improvements, and repaving with approximately 4” of asphalt. The project will grade side slopes due to additional pavement thickness along shoulders. Pullouts directly adjacent to the roadway will also be treated and repaved as part of the project.
SIGNIFICANT QUANTITIES:
Significant Items for Schedule A include: 250 LNFT of Standard Underdrain, 1.8 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 10,750 TONS of Hot Asphalt Concrete Paving, 2,550 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,200 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option W include: 0.5 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 4,350 TONS of Hot Asphalt Concrete Paving, 3,050 LNFT of 12-Inch Colored Concrete Curb and Gutter, 1,500 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,500 CUYD of Roadway Excavation, and 400 CUYD of Subexcavation.
Significant Items for Option X include: 0.9 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 5,200 TONS of Hot Asphalt Concrete Paving, 270 LNFT of 14-Inch Mountable Colored Concrete Curb and Gutter, 1,200 LNFT of 14-Inch Colored Concrete Curb and Gutter, 100 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option Y include: 120 LNFT of Curb and Gutter Removal and Installation, 650 SQYD of Asphalt Patch, and 160 LNFT of Standard Underdrain.
COST RANGE: Estimated total cost for Schedule A, Option W, Option X, and Option Y is $5,000,000 to $7,000,000.
CONSTRUCTION DURATION: May, 2020 through October, 2020.
ADDITIONAL INFORMATION:
Anticipated Bid Opening: December 10, 2019
Anticipated Award: January 6, 2019
Update #2 ·
THIS PROJECT IS ADVERTISED ON A FULL AND OPEN BASIS.
THIS IS REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE AVAILABLE.
PROJECT NUMBER: CO FTNP ROMO 11(4)
PROJECT NAME: Beaver Meadows Road
PROJECT DESCRIPTION: This project provides 3R rehabilitation treatment for routes to include 4.85 miles of Beaver Meadows roadway within Rocky Mountain National Park. The project will also be lengthening and adding a FAST lane at Beaver Meadows Entrance Station which is approximately 1,400 feet.
The project consists of pulverizing the existing asphalt for additional base, concrete curb, drainage improvements, and repaving with approximately 4” of asphalt. The project will grade side slopes due to additional pavement thickness along shoulders. Pullouts directly adjacent to the roadway will also be treated and repaved as part of the project.
SIGNIFICANT QUANTITIES:
Significant Items for Schedule A include: 250 LNFT of Standard Underdrain, 1.8 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 10,750 TONS of Hot Asphalt Concrete Paving, 2,550 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,200 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option W include: 0.5 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 4,350 TONS of Hot Asphalt Concrete Paving, 3,050 LNFT of 12-Inch Colored Concrete Curb and Gutter, 1,500 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,500 CUYD of Roadway Excavation, and 400 CUYD of Subexcavation.
Significant Items for Option X include: 0.9 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 5,200 TONS of Hot Asphalt Concrete Paving, 270 LNFT of 14-Inch Mountable Colored Concrete Curb and Gutter, 1,200 LNFT of 14-Inch Colored Concrete Curb and Gutter, 100 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option Y include: 120 LNFT of Curb and Gutter Removal and Installation, 650 SQYD of Asphalt Patch, and 160 LNFT of Standard Underdrain.
COST RANGE: Estimated total cost for Schedule A, Option W, Option X, and Option Y is $5,000,000 to $7,000,000.
CONSTRUCTION DURATION: May, 2020 through October, 2020.
ADDITIONAL INFORMATION:
Anticipated Bid Opening: December 2, 2019
Anticipated Award: December 16, 2019
Update #1 ·
THIS PROJECT WILL BE ADVERTISED ON A FULL AND OPEN BASIS.
THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
PROJECT NUMBER: CO FTNP ROMO 11(4)
PROJECT NAME: Beaver Meadows Road
PROJECT DESCRIPTION: This project provides 3R rehabilitation treatment for routes to include 4.85 miles of Beaver Meadows roadway within Rocky Mountain National Park. The project will also be lengthening and adding a FAST lane at Beaver Meadows Entrance Station which is approximately 1,400 feet.
The project consists of pulverizing the existing asphalt for additional base, concrete curb, drainage improvements, and repaving with approximately 4” of asphalt. The project will grade side slopes due to additional pavement thickness along shoulders. Pullouts directly adjacent to the roadway will also be treated and repaved as part of the project.
SIGNIFICANT QUANTITIES:
Significant Items for Schedule A include: 250 LNFT of Standard Underdrain, 1.8 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 10,750 TONS of Hot Asphalt Concrete Paving, 2,550 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,200 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option W include: 0.5 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 4,350 TONS of Hot Asphalt Concrete Paving, 3,050 LNFT of 12-Inch Colored Concrete Curb and Gutter, 1,500 LNFT of 14-Inch Colored Concrete Curb and Gutter, 1,500 CUYD of Roadway Excavation, and 400 CUYD of Subexcavation.
Significant Items for Option X include: 0.9 MILES of Full Depth Reclamation 8-Inch Depth of Existing Pavement, 5,200 TONS of Hot Asphalt Concrete Paving, 270 LNFT of 14-Inch Mountable Colored Concrete Curb and Gutter, 1,200 LNFT of 14-Inch Colored Concrete Curb and Gutter, 100 CUYD of Roadway Excavation, and 100 CUYD of Subexcavation.
Significant Items for Option Y include: 120 LNFT of Curb and Gutter Removal and Installation, 650 SQYD of Asphalt Patch, and 160 LNFT of Standard Underdrain.
COST RANGE: Estimated total cost for Schedule A, Option W, Option X, and Option Y is $5,000,000 to $7,000,000.
CONSTRUCTION DURATION: May, 2020 through October, 2020.
ADDITIONAL INFORMATION:
Anticipated Advertisement: October 10, 2019
Anticipated Bid Opening: November 12, 2019
Anticipated Award: November 26, 2019
Files
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| CO FTNP ROMO 11(4) Beaver Meadows Road | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| ND NP THRO 204(1) Buck Hill Road | Federal Highway Administration | No set-aside | |
| CO-rocky MTN arsnl NWR-patch hill road | — | No set-aside | |
| Administrative Parking Lot Repairs | Forest Service | Total Small Business | |
| UT NP ARCH 100(2) Bridges on Delicate Arch Road | Federal Highway Administration | No set-aside | |
| AZ BL COLO 7528(1) Burro Creek Road | Federal Highway Administration | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity