CA FLAP SR89(1), Truckee River Bridge
Awarded Award Notice Posted
- Solicitation number
- DTFH6816B00001
- Agency
- Federal Highway Administration Department of Transportation
- Awarded
- to Martin Brothers Construction
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- DTFH6816C00034 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- Lake Tahoe Lake Tahoe, California 96150, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Added: May 11, 2016 4:42 pm Modified: May 12, 2016 11:36 amTrack Changes
Revised on 5/12/16
The Truckee River Bridge project is located along Lake Tahoe's west shore near the SR 89 and SR 28 intersection area in Tahoe City, California. The work includes realigning State Route 89 between Granlibakken Road and the junction of State Route 89/State Route 28 (SR 89/SR 28) to replace the structurally deficient Fanny Bridge, and to accommodate traffic demands at the SR 89/SR 28 junction in Tahoe City. The purpose of the project is to reduce traffic congestion and improve the safety and operations of SR 89/SR 28 junction in Tahoe City by addressing: present and future automobile travel demand, pedestrian and bicycle mobility, public transit needs, the structural integrity of the Truckee River Bridge (Fanny Bridge), and emergency access to the West Shore within the Fanny Bridge Influence area. Three roundabouts, a new bridge, a bridge replacement, and realigned shared use paths are proposed with the improvements.
The Dollar Creek Trail project proposes to construct 2.2 miles of new shared-use trail along the north shore of Lake Tahoe near State Route (SR) 28 between Dollar Hill and Tahoe Vista. The project will include a shared-use trail, a bridge over Dollar Creek, a marked pedestrian crossing at SR 28 and Dollar Drive, and a neighborhood connector at County Club Drive. The Dollar Creek Shared-Use Trail runs from the Dollar Hill area northeast to Fulton Crescent Drive.
SIGNIFICANT QUANTITIES:
Schedule A: (1.5 miles of roadway improvements, 0.6 miles of path improvements, three roundabouts, one new bridge, one bridge replacement) - Significant items include (quantities are subject to change):
•· 18 acres of clearing and grubbing
•· Removal and replacement of 1 bridge (Fanny Bridge)
•· Construction of new bridge over the Truckee River
•· Sewer Line Utility Relocation
•· 13,500 Tons of Asphalt Concrete Pavement
•· 12,000 Tons of Aggregate Base
•· 370 Square Feet of Concrete Retaining Walls
•· 2,000 Linear Feet of Girders
•· 200,000 Pounds of Reinforcing Steel
•· 360 Linear Feet of Drilled Shafts
•· 13,000 Linear Feet of Concrete Curb
•· 5,500 Square Feet of Rockery Walls
•· 21,000 Cubic Yards of Excavation
•· 31,500 Cubic Yards of Embankment
•· Landscaping and Revegetation
•· Signing and Striping
•· Wetland Mitigation
Option X: (0.12 miles of roadway improvements) - Significant items include (quantities are subject to change):
•· 2,300 Cubic Yards of Roadway Excavation
•· 900 Tons of Aggregate Base
•· 1,500 Tons of Asphalt Concrete Pavement
Option Y: 2.2 miles of new trail and one new pedestrian bridge - Significant items include:
•· 5.8 Acres of Clearing and Grubbing
•· 4, 050 Cubic Yards of Excavation
•· 7,900 Tons of Aggregate Base
•· 2.700 Tons of Hot Asphalt Concrete Pavement
•· 1 Pre-fabricated Steel Bridge (pedestrian bridge)
ENGINEER'S ESTIMATE:
The project engineer's estimate for Schedule A is approximately $25 M
The project engineer's estimate for Option X is approximately $600,000
The project engineer's estimate for Option Y is approximately $3 M
CONSTRUCTION DURATION:
Tentative start date is July 12th, 2016 and estimated completion date is October 15, 2017.
FUNDING SOURCE:
Funding sources are through the Federal Lands Access Program and Local Matching funds from Placer County.
MISCELLANEOUS:
The Tahoe Regional Planning Agency (TRPA) has grading restrictions greater than 3 cubic yards between October 15 and May 15. Exemptions can be granted due to dry weather.
ADDITIONAL INFORMATION FOR NOTICE
Anticipated advertisement on May 28th, 2016
Anticipated bid opening June 17th, 2016
Anticipated Award on July 1st, 2016
Anticipated Notice to Proceed on July 12th, 2016
Update #1 ·
Added: May 11, 2016 4:42 pm
The project is located along Lake Tahoe's west shore near the SR 89 and SR 28 intersection area in Tahoe City, California. The work includes realigning State Route 89 between Granlibakken Road and the junction of State Route 89/State Route 28 (SR 89/SR 28) to replace the structurally deficient Fanny Bridge, and to accommodate traffic demands at the SR 89/SR 28 junction in Tahoe City. The purpose of the project is to reduce traffic congestion and improve the safety and operations of SR 89/SR 28 junction in Tahoe City by addressing: present and future automobile travel demand, pedestrian and bicycle mobility, public transit needs, the structural integrity of the Truckee River Bridge (Fanny Bridge), and emergency access to the West Shore within the Fanny Bridge Influence area. Three roundabouts, a new bridge, a bridge replacement, and realigned shared use paths are proposed with the improvements.
Option X of the Truckee River Bridge project includes the Dollar Creek Trail project, CA FLAP 10089(1). The Dollar Creek Trail Option proposes to construct 2.2 miles of new shared-use trail along the north shore of Lake Tahoe near State Route (SR) 28 between Dollar Hill and Tahoe Vista. The option will include a shared-use trail, a bridge over Dollar Creek, a marked pedestrian crossing at SR 28 and Dollar Drive, and a neighborhood connector at County Club Drive. The Dollar Creek Shared-Use Trail runs from the Dollar Hill area northeast to Fulton Crescent Drive.
Scope of the Work
Schedule A: 1.5 miles of roadway improvements, 0.6 miles of path improvements, three roundabouts, one new bridge, one bridge replacement - Significant items include (quantities are subject to change):
Sewer Line Utility Relocation
13,000 Tons of Asphalt Concrete Pavement
10,300 Square Feet of Concrete Retaining Walls
1500 Linear Feet of Girders
360 Linear Feet of Drilled Shafts
1,079 Cubic Yards of Concrete
6,800 Square Feet of Rockery Walls
23,000 Cubic Yards of Earthwork
Option X: 2.2 miles of new trail and one new pedestrian bridge - Significant items include:
5.8 Acres of Clearing and Grubbing
4, 050 Cubic Yards of Excavation
7,900 Tons of Aggregate Base
2.700 Tons of Hot Asphalt Concrete Pavement
1 Pre-fabricated Steel Bridge (pedestrian bridge)
It is anticipated that this project will be advertised in May or June 2016 with construction beginning August 2016 and ending October, 2017. The contracting range for Schedule A and Option X for this project are between $25 million to $35 million.