017419 construction waste management and disposal.pdf

PDF 19 KB Posted

Attached to
CONSTRUCT USPFO WAREHOUSE
Solicitation number
W91364-09-B-0003
Issued by

About this file

017419 construction waste management and disposal.pdf

View the file

Other files

File Type Posted
Bid Abstract 09-B-0003.pdf PDF
SF30Amendment2 09-B-0003.pdf PDF
ADDENDUM NO 03 USPFO Narrative.pdf PDF
ADDENDUM NO 02 USPFO Narrative SENT.pdf PDF
SF30Amendment3 09-B-0003.pdf PDF
09-B-0003 Amendment 3.pdf PDF
ADDENDUM NO 03 CSMS PH II Narrative.pdf PDF
ADDENDUM NO 02 CSMS PH II Narrative SENT.pdf PDF
USPFO WH Addendum.pdf PDF
Bid Questions USPFO WAREHOUSE JACOBS RESPONSES JFK.doc DOC document
e2c23100.PDF PDF
OHARNG-USPFO-G-130W .pdf PDF
OHARNG-USPFO-A-820W .pdf PDF
083730 high speed rolling door.pdf PDF
220523 general duty valves for plumbing piping.pdf PDF
092900 gypsum board.pdf PDF
102113 toilet compartments.pdf PDF
OHARNG-USPFO-A-723W .pdf PDF
270500 common work results for communications.pdf PDF
081113 hollow metal doors and frames.pdf PDF
052100 steel joist framing.pdf PDF
017329 cutting and patching.pdf PDF
220516 expansion fittings and loops for plumbing piping.pdf PDF
104413 fire extinguishing cabinets.pdf PDF
102800 toilet bath and laundry accessories.pdf PDF
077100 roof specialties.pdf PDF
061000 rough carpentry.pdf PDF
USPFO_FA501W.pdf PDF
USPFO_M501W.pdf PDF
USPFO_S252W.pdf PDF
E802.pdf PDF
E104.pdf PDF
055000 metal fabrications.pdf PDF
USPFO_M301W.pdf PDF
OHARNG-USPFO-A-806W .pdf PDF
OHARNG-USPFO-A-213bW .pdf PDF
C603.pdf PDF
263600 transfer switches.pdf PDF
017839 project record documents.pdf PDF
230811 pre-functional checklists mechanical.pdf PDF
093000 tiling.pdf PDF
E401.pdf PDF
013200 construction progress documentation.pdf PDF
260533 raceway and boxes for electrical systems.pdf PDF
OHARNG-USPFO-A-320W .pdf PDF
311000 clearing grubbing.pdf PDF
262413 switchboards.pdf PDF
221319 sanitary waste piping specialties.pdf PDF
USPFO_FA301W.pdf PDF
260500 common work results for electrical.pdf PDF
Show 40 more

Latest 50 of 373 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F5W61608 USPFO Warehouse Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 – 1

SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for the following:

1. Recycling nonhazardous site clearing and construction waste.

2. Disposing of nonhazardous site clearing and construction waste.

B. Related Sections include the following:

1. Section 018113 "Sustainable Design Requirements" for additional LEED re-quirements.

2. Section 015000 "Temporary Facilities and Controls" for environmental-protection measures during construction, and location of waste containers at Project site.

3. Section 042000 "Unit Masonry" for disposal requirements for masonry waste.

4. Section 311000 "Site Clearing" for disposition of waste resulting from site clear-ing and removal of above- and below-grade improvements.

5. Section 013110 “Project Management and Coordination” for additional reporting requirements.

1.2 DEFINITIONS

A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construc-tion waste includes packaging.

B. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.

C. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.

D. Salvage: Recovery of demolition or construction waste and subsequent sale or re-use in another facility.

E. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.

1.3 PERFORMANCE REQUIREMENTS

A. General: Develop waste management plan that results in end-of-Project rates for salvage/recycling of 50 percent by weight of total waste generated by the Work.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 – 2

1. Construction Waste:

a. Site-clearing waste.

b. Masonry and CMU.

c. Lumber.

d. Wood sheet materials.

e. Wood trim.

f. Metals.

g. Roofing.

h. Insulation.

i. Carpet and pad.

j. Gypsum board.

k. Piping.

l. Electrical conduit.

m. Packaging: Regardless of salvage/recycle goal indicated above, salvage or recycle 100 percent of the following uncontaminated packaging materials:

1) Paper.

2) Cardboard.

3) Boxes.

4) Plastic sheet and film.

5) Polystyrene packaging.

6) Wood crates.

7) Plastic pails.

1.4 SUBMITTALS

A. Waste Management Plan: Submit 3 copies of plan within 30 days of date established for the Notice to Proceed.

B. Waste Reduction Progress Reports: Concurrent with each Application for Payment, submit three copies of report. Include the following information:

1. Material category.

2. Generation point of waste.

3. Total quantity of waste in tons.

4. Quantity of waste salvaged, both estimated and actual in tons.

5. Quantity of waste recycled, both estimated and actual in tons.

6. Total quantity of waste recovered (salvaged plus recycled) in tons.

7. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste.

C. Waste Reduction Calculations: Before request for Final Acceptance , submit three copies of calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work.

D. Records of Donations: Indicate receipt and acceptance of salvageable waste do-nated to individuals and organizations. Indicate whether organization is tax exempt.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 – 3

E. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to indi-viduals and organizations. Indicate whether organization is tax exempt.

F. Recycling and Processing Facility Records: Indicate receipt and acceptance of recy-clable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.

G. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.

H. LEED Submittals: Refer to Section 018113 “Sustainable Design Requirements: for additional LEED submittal requirements. Requirements are listed in Attachment A to Section 018113, LEED analysis, under column titled “Documentation and Submittal Reference.” Contractor shall provide LEED submittals corresponding to each LEED Credit claimed and provide documentation per Section 018113, paragraph titled LEED Documentation Submittals.

I. Qualification Data: For Waste Management Coordinator.

1.5 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with hauling and disposal regulations of authori-ties having jurisdiction.

B. Waste Management Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to waste management including, but not limited to, the following:

1. Review and discuss waste management plan including responsibilities of Waste Management Coordinator.

2. Review requirements for documenting quantities of each type of waste and its disposition.

3. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays.

4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.

5. Review waste management requirements for each trade or subcontractor at the construction meeting prior to the commencement of that trade or subcontractor’s work.

1.6 WASTE MANAGEMENT PLAN

A. General: Develop plan consisting of waste identification, waste reduction work plan, and cost/revenue analysis. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 – 4

B. Waste Identification: Indicate anticipated types and quantities of site-clearing and construction waste generated by the Work. Include estimated quantities and as-sumptions for estimates.

C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and han-dling and transportation procedures.

1. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.

2. Disposed Materials: Indicate how and where materials will be disposed of. In-clude name, address, and telephone number of each landfill and incinerator fa-cility.

3. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location on Project site where materials separation will be lo-cated.

D. Cost/Revenue Analysis: Indicate total cost of waste disposal as if there was no waste management plan and net additional cost or net savings resulting from imple-menting waste management plan. Include the following:

1. Total quantity of waste.

2. Estimated cost of disposal (cost per unit). Include hauling and tipping fees and cost of collection containers for each type of waste.

3. Total cost of disposal (with no waste management).

4. Revenue from recycled materials.

5. Savings in hauling and tipping fees by donating materials.

6. Savings in hauling and tipping fees that are avoided.

7. Handling and transportation costs. Include cost of collection containers for each type of waste.

8. Net additional cost or net savings from waste management plan.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PLAN IMPLEMENTATION

A. General: Implement waste management plan as approved by Contracting Officer.

Provide handling, containers, storage, signage, transportation, and other items as re-quired to implement waste management plan during the entire duration of the Con-tract.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 – 5

1. Comply with Section 015000 "Temporary Facilities and Controls" for operation, termination, and removal requirements.

B. Waste Management Coordinator: Engage a waste management coordinator to be responsible for implementing, monitoring, and reporting status of waste management work plan. Coordinator shall be present at Project site full time for duration of Pro-ject.

C. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at Project site.

1. Distribute waste management plan to everyone concerned within three days of submittal return.

2. Distribute waste management plan to entities when they first begin work on-site.

Review plan procedures and locations established for salvage, recycling, and disposal.

D. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adja-cent occupied and used facilities.

1. Designate and label specific areas on Project site necessary for separating ma-terials that are to be salvaged, recycled, reused, donated, and sold.

2. Comply with Section 015000 "Temporary Facilities and Controls" for controlling dust and dirt, environmental protection, and noise control.

3.2 RECYCLING WASTE, GENERAL

A. General: Recycle paper and beverage containers used by on-site workers.

B. Recycling Receivers and Processors: Contractor shall be responsible for arranging with Recycling Receivers and Processors to comply with required Performance Goals.

C. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Contractor.

D. Procedures: Separate recyclable waste from other waste materials, trash, and de-bris. Separate recyclable waste by type at Project site to the maximum extent practi-cal.

1. Provide appropriately marked containers or bins for controlling recyclable waste until they are removed from Project site. Include list of acceptable and unac-ceptable materials at each container and bin.

a. Inspect containers and bins for contamination and remove contaminated ma-terials if found.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 – 6

2. Stockpile processed materials on-site without intermixing with other materials.

Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

3. Stockpile materials away from construction area. Do not store within drip line of remaining trees.

4. Store components off the ground and protect from the weather.

5. Remove recyclable waste off Government's property and transport to recycling receiver or processor.

3.3 RECYCLING CONSTRUCTION WASTE

A. Packaging:

1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.

2. Polystyrene Packaging: Separate and bag materials.

3. Pallets: As much as possible, require deliveries using pallets to remove pallets from Project site. For pallets that remain on-site, break down pallets into com-ponent wood pieces and comply with requirements for recycling wood.

4. Crates: Break down crates into component wood pieces and comply with re-quirements for recycling wood.

B. Site-Clearing Wastes: Chip brush, branches, and trees at landfill facility.

C. Wood Materials:

1. Clean Cut-Offs of Lumber: Grind or chip into small pieces.

2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood.

D. Gypsum Board: Stack large clean pieces on wood pallets and store in a dry location.

1. Clean Gypsum Board: Grind scraps of clean gypsum board using small mobile chipper or hammer mill. Screen out paper after grinding.

3.4 DISPOSAL OF WASTE

A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

1. Except as otherwise specified, do not allow waste materials that are to be dis-posed of accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn waste materials.

C. Disposal: Transport waste materials off Government's property and legally dispose of them.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 – 7

END OF SECTION 017419

File details come from the government source that posted it. Updated .