PWS_JBCC_ID-IQ_Seed_Task_Order_3-5-2018_Rev.pdf

PDF 2 MB Posted

Attached to
(IDIQ) for Remediation Services Contract for Joint Base Cape CodBourne, Massachusetts
Solicitation number
W912WJ18R0002
Issued by

About this file

PWS JBCC ID-IQ Seed Task Order_3-5-2018_Rev

View the file

Other files

File Type Posted
Amendment_0005.pdf PDF
Attachment_I-1_-_Prime_Binding_Rates_Rev_3-15-2018.xlsx XLSX spreadsheet
Attachment_I-2_-_Subcontractor_Binding_Rates_Rev_3-15-2018.xlsx XLSX spreadsheet
Amendment_0004.pdf PDF
Attachment_I-4_-_Seed_Task_Order_Rates_for_Subcontractor_Rev_3-15-2018.xlsx XLSX spreadsheet
Attachment_I-3_-_Seed_Task_Order_Rates_for_Prime_Rev_3-15-2018.xlsx XLSX spreadsheet
Demo_1_Decision_Document_2006.pdf PDF
J-3_Range_Decision_Document_2015_.pdf PDF
Demo_1_Decision_Document_Addendum_No._1_2009.pdf PDF
J-2_Range_Decision_Document_2013.pdf PDF
Demo_1_Decision_Document_Addendum_No.2_2013.pdf PDF
CIA_Decision_Document_2012.pdf PDF
IAGWSP_cameras_locations.pdf PDF
Amendment_0003.pdf PDF
J-1_Range_Decision_Document_2011.pdf PDF
Amendment_0002_.pdf PDF
Final_J-1_Range_South_RRA_SPM_Plan_2007.pdf PDF
J-3_Range_O&M_Manual_&_Drawings.pdf PDF
Attachment_I-4_-_Seed_Task_Order_Rates_for_Subcontractor_JM_Rev1.xlsx XLSX spreadsheet
Demo_1_Pew_Rd_&_Base_Boundary_O&M_Manual.pdf PDF
Attachment_I-1_-_Prime_Binding_Rates_Rev2.xlsx XLSX spreadsheet
CIA_1&2_O&M_Manual_&_Drawings.pdf PDF
Final_J-3_Range_RRA_SPEIM_Plan_2006.pdf PDF
Attachment_I-2_-_Subcontractor_Binding_Rates_Rev2.xlsx XLSX spreadsheet
Final_SPEIM_Plan_RRA_Systems_Demo_1_Groundwater_OU_2005.pdf PDF
QAPP_Appendix_D_Files.pdf PDF
Attachment_I-3_-_Seed_Task_Order_Rates_for_Prime_JMRev1.xlsx XLSX spreadsheet
SIR-110-Spec-Sheet.pdf PDF
J-1_North_O&M_Manual_&_Drawings_.pdf PDF
JBCC_GAC_Sample_Non-HazManifest-BOL.PDF PDF
Demo_1-Base_Boundary_GWT-_Drawings.pdf PDF
Final_J-2_Range_East_SPM_Plan_2008.pdf PDF
CIA_3_Leading_Edge_O&M_Manual_&_Drawings.pdf PDF
Final_J-2_North_RRA_PME_Plan.pdf PDF
Demo_1_Pew_Road_RRA_Plan_Nov2003.pdf PDF
Demo_1_Frank_Perkins_Road_O&M_Manual.pdf PDF
J-2_East_O&M_Manual.pdf PDF
Demo_1_Off_Base_O&M_Manual_&_Drawings.pdf PDF
Final_J-2_North_O&M_Manual_&_Drawings.pdf PDF
Final_J-1_SE_RRA_Eng_Specs_&_Drawings.pdf PDF
Demo_1_Leading_Edge_MTU.pdf PDF
CIA3_Range_MTU.pdf PDF
JBCC_camera_spec_sheet.pdf PDF
J2_Range_North_Treatment_Facility.pdf PDF
Amendment_0001.pdf PDF
Demo_1_Base_Boundary_MTU.pdf PDF
J2_Range_North_MTUs.pdf PDF
J1_Range_South_and_J2_Range_East.pdf PDF
J1_Range_North.pdf PDF
J3_Range.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement

FOR REMEDIATION SERVICES CONTRACT

OPERATION AND MAINTENANCE AND

LONG-TERM MONITORING

Joint Base Cape Cod Camp Edwards, Massachusetts

New Solicitation W912WJ-18-R-0002

Seed Task Order

U.S. Army Corps of Engineers New England District

March 2018

ACROYNM LIST

AFCEE Air Force Center for Engineering and the Environment

EB Equipment Blank

EPA U.S. Environmental Protection Agency

ETR extraction, treatment, and reinjection

FD Field Duplicate

GAC granular activated carbon

Gpm gallons per minute

HA Health Advisory

HMX octahydro-1,3,5,7-tetranitro-1,3,5,7-tetrazocine

IAGWSP Impact Area Groundwater Study Program

IDIQ Indefinite Delivery/Indefinite Quantity

IX ion exchange

JBCC Joint Base Cape Cod

K hydraulic conductivity

MassDEP Massachusetts Department of Environmental Protection

MDL Method Detection Limit

MEC Munitions and Explosives of Concern mg/L milligrams per liter

MMCL Massachusetts Maximum Contaminant Level

Msl mean sea level

RDX hexahydro-1,3,5-trinitro-1,3,5-triazine

RRA Rapid Response Action

TB Trip Blank μg/L micrograms per liter

PERFORMANCE WORK STATEMENT

FOR REMEDIATION SERVICES CONTRACT

OPERATION AND MAINTENANCE AND LONG-TERM MONITORING

AT THE

JOINT BASE CAPE COD

CAMP EDWARDS, MASSACHUSETTS

New Solicitation W912WJ-18-R-0002

Seed Task Order

March 2018

1.0 Introduction

The Contractor will be responsible for fully executing a firm fixed-price Task Order under Indefinite Delivery/Indefinite Quantity Type Environmental Services Contract W912WJ-18-R-0002 with the New England District, U.S. Army Corps of Engineers (USACE). USACE is performing the function of Supervising Contractor (started January 2001) at Joint Base Cape Cod (JBCC) [formerly Massachusetts Military Reservation (MMR)] to support the Army/National Guard Bureau in its role as respondent to the EPA Administrative Orders issued under the Safe Drinking Water Act. The Groundwater Study Program requires contaminated soil and groundwater characterization, feasibility studies, remedial design and action, as well as operations and maintenance (O&M) of required treatment facilities.

This Task Order will include activities associated with O&M of groundwater treatment facilities as well as groundwater sampling associated with contaminated groundwater within and emanating from Camp Edwards. These activities will be required in support of existing and planned groundwater treatment activities at the JBCC.

The Contractor shall perform all the necessary services required to successfully meet all performance objectives of this Performance Work Statement (PWS). The Contractor shall comply with all applicable Federal, State, and local laws and regulations in order to successfully complete all performance objectives of this PWS in a manner that is consistent with any applicable orders and permits and relevant Department of Defense (DOD) and Army policies for the duration of this Task Order. Work shall be performed in accordance with the latest versions of the background documents provided with Task Order 0001 and the other documents identified in this PWS. The Contractor shall also use the references listed below (and default to most recent version if different) when preparing the proposal and executing the work.

Engineer Manual (EM) 1110-1-4007 Safety and Health Aspects of Hazardous, Toxic, and Radioactive Waste Remediation Technologies, USACE, 2003.

EM 200-1-3, Requirements for the Preparation of Sampling and Analysis Plans, USACE, 01 Feb. 2001

ER 1110-1-263, Chemical Data Quality Management for Hazardous, Toxic, Radioactive Waste Remedial Activities, USACE, 30 Apr 1998

EM 200-1-6, Chemical Quality Assurance for HTRW Projects, USACE, 10 Oct. 1997 DOD Quality Systems Manual (QSM), for Environmental Laboratories, Revision 5.0 dated July

Uniform Federal policy for Quality Assurance Project Plans (UFP for QAPP), Evaluating, Assessing and Documenting Environmental Data Collection and Program Use, Part 1 and Part 2, Final version 1, March 2005

Intergovernmental Data Quality Task Force Uniform Federal Policy for Quality Assurance Project Plans Optimized UFP-QAPP Worksheets. www.epa.gov/fedfac. DoD/EPA/DOE, March 2012

EPA New England Environmental Data Review Program Guidance. Version 4-22-2013 DoD General Data Validation Guidelines Final Draft, Environmental Data Quality Workgroup, December 2016 National Functional Guidelines for Superfund Organic Methods Data Review. EPA-540-R-

2016-002 National Functional Guidelines for Superfund Inorganic Methods Data Review. EPA-540-R-

2016-001 ER1180-1-6, Construction Quality Management, USACE, 30 Sep 1995 EM 385-1-1 U.S. Army Corps of Engineers Safety and Health Requirements Manual (2008) EM 1110-1-4000, Monitoring Well Design, Installation, and Documentation at Hazardous

Toxic, and Radioactive Waste Sites, USACE, Dated November 1, 1998.

42 U.S. Code Chapter 103 – Comprehensive Environmental Response, Compensation, and

Liability.

EQASOP-GW 0001, Low Stress (low flow) Purging and Sampling Procedure for the Collection of Groundwater Samples From Monitoring Wells, prepared by USEPA Region 1, dated July 30, 1996, revised January 19, 2010.

ER 1110-1-8157, Engineering and Design Geotechnical Data Quality Management for Hazardous Waste Remedial Activities, 2002.

EM 1110-1-1804 Geotechnical Investigations, Engineering and Design, 2001.

EM 1110-1-1802 Geophysical Exploration for Engineering and Environmental Investigations, 1995.

United States Environmental Protection Agency, 2006. Guidance on Systematic Planning

Using the Data Quality Objectives Process (EPA QA/G-4). Published by the Office of Environmental Information.

Applicable ASTM Standards Revised Data Validation Guidelines, Region 1 EPA-NE, Dec. 1996 Draft Investigative Derived Waste, Material Disposition Plan, Camp Edwards, Massachusetts

Military Reservation (ECC, March 5, 2004) Environmental Data Management System (EDMS) Data Management Plan (see EDMS website for most current version) EDMS Stakeholder Reference Manual (see EDMS website for most current version) UFP-QAPP titled Impact Area Groundwater Study Program, Final, Generic Quality Assurance

Project Plan (current version TetraTech, February 2012 updated in 2017 and pending Agency approval).

2.0 Types of Services Required

This Task Order includes the following types of environmental services as authorized under the basic contract:

___ Site Characterization/Investigation

___ Studies and Reports

_X_ Long Term Monitoring/Operations

___ Remedial Design

_ X __ MEC Support (recognition only and notification to Army for removal and disposal)

3.0 Task Order Type [select only one]

___ Cost-Plus Fixed-Fee

_X_ Firm-Fixed Price

___ Fixed Price with Award Fee

4.0 Performance Objectives and Standards

This PWS is for a firm-fixed price Task Order with intent to successfully complete all performance objectives and eliminate, as far as reasonably possible, the potential for additional costs and modifications to this Task Order. The Contractor shall furnish all plant, labor, materials, and equipment necessary to successfully complete all performance objectives identified in this PWS and Table 1, Performance Requirements Summary. Achievement of the performance objectives is successfully attained upon the finalization of appropriate documentation certifying that the objectives/tasks have been accepted by the USACE. USACE approval of the Performance Standards will be by the USACE Contracting Officer (KO) or Contracting Officer’s Representative (COR).

Table 1 – Performance Requirements Summary Performance Objective/Task Performance Standard

Task 1 – Project Management/Contract Support Complete contract support activities in accordance with JBCC program requirements and USACE acceptance.

Task 2 – Work Plans Project Work Plan

APP/SSHP

Complete contract support activities in accordance with JBCC program requirements and USACE acceptance.

Task 3 – Demo 1 O&M, System Performance Monitoring

Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Task 4 – J-1 Range South O&M, System Performance Monitoring

Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Task 5 – J-2 Range East O&M, System Performance Monitoring

Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Task 6 – J-2 Range North O&M, System Performance Monitoring

Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Task 7 – J-3 Range O&M, System Performance Monitoring

Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Table 1 – Performance Requirements Summary Performance Objective/Task Performance Standard

Task 8 – J-1 Range North O&M, System Performance Monitoring

Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Task 9 – CIA O&M, System Performance Monitoring

Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Task 10 – Groundwater Monitoring Complete groundwater monitoring in accordance with JBCC program requirements and USACE acceptance.

Task 11 – Central Storage Area O&M Complete annual O&M in accordance with JBCC program requirements and USACE acceptance.

Task 12 – Well Pad Maintenance and Road Repair Complete well pad maintenance and road repair in accordance with USACE direction.

In the event that there may be multiple interim milestones and/or deliverables for each of the performance objective tasks, partial payments will be based on the successful completion of interim milestones. Final decisions regarding the adequacy of milestone and deliverable completion resides with the KO or COR with appropriate acceptance and approval of necessary documentation by regulators consistent with the JBCC Administrative Orders and the Remediation Regulations.

5.0 Requirements

The Contractor shall furnish all necessary labor, equipment, materials, and supplies to complete the tasks listed in Table 1 above and defined in the following paragraphs in support of the Impact Area Ground Water Study Program (IAGWSP) at the JBCC. All work shall be conducted in a safe, secure, cost efficient, and environmentally acceptable manner conforming to existing Federal, State, JBCC, and local regulations. Work shall be completed correctly the first time (no do-overs) in a professional, workmanlike manner, in accordance with approved work plans. Work is to be performed commensurate with the level of effort and quality intended, with appropriately qualified quality control (QC) representation (as part of the contractors overall QC Program) controlling the work.

Specific activities include groundwater sampling; analytical and data management; synoptic water level events; treatment facility O&M; monitoring/periodic reporting (daily, weekly, monthly); meetings and project management; and preparation, maintenance, updating, coordinating and regular submission of schedule to USACE Project Office for planning, controlling, and evaluating work being conducted.

Period of performance for the Seed Task Order is estimated from 1 May 2018 through 31 July 2019.

5.1 Task 1 – Project Management/Contract Support

Task 1.1 – Financial/Project Control Services This task provides for oversight of the below activities to include the project management and administrative staff when engaged in representative non-site specific activities.

Cost and schedule reporting and tracking.

Subcontractor cost and schedule reporting and tracking.

Program resource planning selection and resource conflict resolution.

General Government Property control activities and oversight of task order property control implementation including program-specific audit requirements.

Participation by the Project Manager in twelve monthly meetings at JBCC with Corps, staff, and subcontractors. The Program Manager will attend four monthly meetings at JBCC and eight monthly meetings via conference call.

Contract basis review, verification, and tracking of invoices to ensure conformance to applicable contract requirements.

Preparation of monthly invoices.

Preparation of daily update on sampling field activities for USACE via e-mail.

Preparation of daily update on O&M field activities for USACE via e-mail.

Preparation of weekly field update on sampling and O&M field activities for USACE via e-mail.

Provide cellular service for uploading images to the internet through a cloud service (14 on-base cameras). The Contractor’s Field Lead shall remotely check the cameras once per week.

Yearly maintenance and repair of six (6) cameras (i.e., replacement of up to 6 cameras) shall be included.

Task 1.1.1 (Off-Base Cameras) – Provide cellular service for uploading images to the internet through a cloud service. Contractor’s Field Lead shall remotely check the one off-base camera once per week.

Maintenance of the camera shall be included.

Task 1.2 – Other Direct Costs/Field Office Support These costs shall include, but not be limited to: DigSafe reception and transfer of notices to IAGWSP and USACE and mark out of any potentially impacted utilities; cell phone(s) rental/lease and maintenance; vehicle(s) rental/lease and maintenance; and other equipment and travel.

Approximately 800 SF of office space is available in the Frank Perkins Road treatment plant. In addition, there is an equipment storage room, and ample space to store and calibrate groundwater sampling equipment and process groundwater samples. The Government shall provide electricity at no charge to the Contractor (the electricity will service A/C units in the office space). The Contractor is responsible for heat (natural gas), internet, a garbage dumpster, and bathroom facilities (one combined port-a-john and hand washing unit).

The Contractor is responsible for snow removal to provide vehicle access to the treatment systems for O&M activities, vehicle access to wells for sampling activities, and vehicle access for the USACE UXO parking lot. The Contractor shall provide radios (15 radios) to be utilized by all field crews and provide maintenance/repair as required. The Contractor shall provide DigSafe reception, transfer of notices to IAGWSP, and mark out of any potentially impacted utilities. The Contractor shall provide biweekly cleaning services for the two USACE/IAGWSP office trailers. The Contractor is responsible for potable water for consumption for the Frank Perkins Road treatment plant (one cooler and bottled water for contractor field personnel), USACE office trailer (one cooler) and IAGWSP office trailer (one cooler) (monthly deliveries of water for three coolers).

Task 1.3 – Building Maintenance The Contractor shall provide general building maintenance for the USACE and IAGWSP office trailers. For each of the two trailers, the Contractor should assume a service call once a year for: 1) electrical (one full day for an electrician); 2) plumbing (one full day for a plumber), and; 3) A/C and heating (one full day for a HVAC technician).

5.2 Task 2 – Work Plans

Task 2.1 – Project Work Plan The Contractor is required to submit a Project Work Plan. The Project Work Plan describes the Contractor's activities as outlined in the seed task order. The Contractor will be required to follow existing Environmental Monitoring Plans and Operation & Maintenance Plans, as provided by USACE. The Contractor may be responsible for updating Monitoring Plans and/or O&M Plans as appropriate. The Project Work Plan shall reference these existing plans and shall contain (when relevant), but not be limited to, the following:

Description of available data and contaminant characterization;

Statement of the work to be accomplished including a statement of Data Quality Objective(s);

Discussion on implementation of the project including the method of operation, type of equipment, personnel required, and other special considerations;

A schedule that presents the requirements to complete any required field work and key project milestones;

Permits, licenses, and certificates, identification number, and location of the disposal facility

(IDW decision tree), if necessary;

Key personnel to be used on the project along with their roles and responsibilities;

Site-specific assumptions and clarifications;

Site control measures; and Logs, reports, and record keeping to be utilized.

The Contractor will submit internal draft, draft final and final versions Project Work Plan with response to comments (RTCs) and response to comments letters (RCL). Acceptance of the Contractor's Project Work Plan by the Government is required prior to any field mobilization.

Acceptance is conditional and will be predicated on satisfactory performance during field activities.

Deviations or proposed changes to the approved Project Work Plan must be submitted to the USACE Project Manager or COR for review, comment, and approval. The Government reserves the right to require the Contractor to make changes in his Project Work Plan and operations as necessary. During execution of the seed task order the Contractor shall follow the approved Project Work Plan.

The WP must be submitted within 30 days from award.

Task 2.2 – Accident Prevention Plan (APP)/Site Safety and Health Plan (SSHP)

The Contractor shall prepare a site-specific health and safety plan that specifies employee training, protective equipment, medical surveillance requirements, standard operating procedures, and a contingency plan. Specific requirements are outlined in below.

Accident Prevention Plan

The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include an Activity Hazard Analysis (AHA) as described below. All work shall be conducted in accordance with the APP, the U.S. Army Corps of Engineers Safety and Health requirements Manual (EM 385-1-1, most recent edition), and all applicable federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at Headquarters USACE website under publications using the following link:

http://www.usace.army.mil/library/.

The APP shall detail how safety and health will be managed during the project. The APP shall address the requirements of applicable Federal, State and local safety and health laws, rules, and regulations. The Contractor shall comply with Federal Acquisition Regulation Clause No. 52.236- 13 for Accident Prevention, which is added by reference. Special attention shall focus on the requirements of EM 385-1-1, specifically Section 01.A.11 through 01.A.18, Figure 1-2 AHA, and Appendix A, (Minimum Basic Outline for Accident Prevention Plan). The APP shall be developed by a qualified person. The contractor shall be responsible for documenting the qualified person’s credentials. Work shall not proceed until the APP has been reviewed by the Government Designated Authority (GDA) (the USACE New England District Safety Office for this project) and deemed acceptable for use on the project.

As part of the APP the contractor must prepare a Site Safety and Health Plan (SSHP) that that covers the 14 elements identified in EM385-1-1, Section 33.B.02. The SSHP shall be attached to the APP as an appendix. SSHP elements adequately covered elsewhere in the APP need not be duplicated again in the SSHP.

The APP shall coordinate with the Contractor's existing safety and health program. Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

The Contractor shall conduct a safety meeting at the project site on the first day of work, whenever a new activity or phase of work begins, and daily during the progress of work. All safety meetings shall be documented using USACE safety meeting form or a similar contractor-prepared form.

Records of the safety briefings shall be submitted to the GDA weekly.

Activity Hazard Analysis

An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level.

Work shall not proceed on a phase of work until the AHA has been accepted by the GDA. A preparatory meeting shall be conducted by the contractor to discuss the AHA contents with all engaged in the activity. The preparatory meeting shall be conducted by the prime contractor and shall include all subcontractors and Government on-site representatives. The AHA shall be continuously reviewed and revised to address changing site conditions or operations as appropriate.

Accident Reporting

All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $2,000.00, shall be verbally reported to the GDA within 24 hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D.02 shall be immediately reported to the GDA. ENG Form 3394 shall be completed and submitted to the GDA within five working days of the incident.

The Contractor shall complete the “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (for prime and its subcontractors) and forward the completed form to the GDA no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the GDA shall be electronically.

5.3 Task 3 – Demolition Area 1 (Demo 1) O&M, System Performance Monitoring

Demo 1 is located north of Pocasset Forestdale Road and south of the Impact Area at Camp Edwards, west of Turpentine Road and east of Frank Perkins Road (see Attachments, Figure 1 – IAGWSP Groundwater Treatment System Locations). Demolition training and explosive ordnance disposal at Demo 1 included the destruction of various types of ordnance using explosive charges.

Seven explosive and propellant compounds [hexahydro-1,3,5-trinitro-1,3,5-triazine (RDX), TNT, octahydro-1,3,5,7-tetranitro-1,3,5,7-tetrazocine, 2-amino-4,6-dinitrololuene, 4-amino-2,6-dinitrotoluene, perchlorate, and 2,4-dinitrotoluene] have been consistently detected in groundwater and are identified as the contaminants of concern (COCs) in groundwater for the Demo 1 Groundwater Operable Unit (OU).

The Demo 1 Remedial Action (RA) System consists of four independent treatment systems. The systems are located on Frank Perkins Road, Pew Road, at the JBCC base boundary, and Demo 1 off-base. The Contractor shall be responsible for O&M and performance monitoring of these systems under this task.

The Contractor shall be responsible for executing all O&M activities at the Demo 1 RA treatment systems in accordance with the language outlined in Task 3 and the most recent Demolition Area 1 Environmental and System Performance Monitoring (SPM) Report.

The Frank Perkins Road system is housed in an 11,000-square-foot concrete and metal building installed east of Frank Perkins Road near the junction with Pocasset-Forestdale Road. Groundwater is extracted from two extraction wells. The primary components of the system include ion exchange (IX) – granular activated carbon (GAC) treatment. The treatment train includes two IX resin vessels in parallel, each containing 400 cubic feet of Nitrate Selective IX. These are followed by three vessels in series, each of which contain 20,000 pounds of GAC. The system also includes an influent equalization tank, booster pump, a bag filtration system, a backwash water tank, a backwash pump, and a settling tank. Perchlorate is removed primarily through the vessels containing the IX resin. Once the capacity of the IX resin is reached, the GAC vessels remove the remaining perchlorate until change out of the IX resin occurs. The IX resin is not effective for the removal of explosive compounds. Therefore, the removal of explosives is through the first two GAC vessels in series with the third (guard) GAC vessel available to ensure that all perchlorate and explosives are captured prior to discharge. The treatment system has a total maximum process rate of approximately 500 gpm. The current operating flow rate is 175 gpm. The groundwater is reinjected at two reinjection wells.

The Pew Road treatment system consists of a mobile treatment unit (MTU). Groundwater is extracted from one extraction well. The treatment system consists of six pressure vessels that are arrayed in 3 sequential pairs so that the six-vessel process train is the functional equivalent of three vessels in series.

The first pair of vessels contains IX resin and is the principal treatment stage for perchlorate. The lag (2nd) pair of vessels contains GAC to remove explosives and also perchlorate if there is breakthrough from the IX vessels. Finally, the guard (3rd) pair of vessels contains GAC to provide backup capacity.

This ensures that any breakthrough of contaminants from the lag vessels will be captured prior to effluent discharge. Each IX vessel contains 29 cubic feet of Nitrate Selective IX. Each GAC vessel contains 1,000 pounds of GAC. The treatment system has a total maximum process rate up to 110 gallons per minute (gpm). The current operating flow rate is 105 gpm. Groundwater is reinjected at one reinjection well.

The base boundary treatment system is also a MTU. Groundwater is extracted from one extraction well.

The treatment train consists of a single treatment train of three pressure vessels configured similar to the Pew Road treatment system. The IX vessel contains 35 cubic feet of Nitrate Selective IX. The GAC vessel contains 1,000 pounds of GAC. The treatment system has a total maximum process rate up to 50 gallons per minute (gpm). The current operating flow rate is 65 gpm. The groundwater is reinjected through one reinjection gallery.

An off-base groundwater treatment system was installed in 2016. This leading edge treatment system is designed to pump at a rate of 100 gpm. The treatment system consists of a bag filter, ion exchange vessel, and two granular activated carbon vessels. Each IX vessel contains 58 cubic feet of Nitrate Selective IX. Each GAC vessel contains 3,000 pounds of GAC. The treated groundwater is discharged to a single reinjection gallery.

Task 3.1 – O&M Support – Demo 1 On-Base Systems (Frank Perkins Road and Pew Road Systems)

System and wellfield O&M shall be performed to maintain the treatment systems in the most efficient operational condition and minimize pumping downtime. Monitoring at the treatment systems shall include influent and effluent sampling to demonstrate that the treated water being recharged back into the aquifer through the reinjection wells / reinjection gallery is below the reporting limits for perchlorate and RDX.

Plant visits shall focus on periodic verification of operating parameters, routine and preventative maintenance, media change-out, and responses to unplanned plant shutdown (e.g., power failure).

O&M activities shall also focus on wellfield maintenance, which shall include execution of both a routine and preventative maintenance program for the extraction and reinjection wells / reinjection gallery and piping.

The Contractor shall prepare monthly O&M Reports and submit via upload to the EDMS system with e-mail notification to the USACE.

All O&M activities shall be documented in the project Log Books which shall be maintained at the project field office. The O&M Checklist shall be used to ensure that all required system components are inspected during routine O&M and during media change-out operations. The O&M Checklists shall also note required action items or follow up inspections. The O&M Checklists shall be maintained at each system. An Event Log shall also be maintained at each system to document any downtime, including the reason for the downtime and the duration. All O&M monitoring activities shall be conducted by state-licensed wastewater treatment plant operators.

Table 2 identifies specific O&M activities and their anticipated frequency of completion.

The Contractor shall be responsible for the change-out of treatment media (GAC, IX resin, and bag filters). New media shall be inspected upon receipt to ensure the project specifications are met.

While media vessels are empty, the Contractor shall conduct inspections of the interior of the vessels to validate the integrity of the vessels and document the condition of the interior piping and appurtenances. The results of this inspection shall be documented in the project logbooks and in the O&M Checklist.

Spent media shall be transported off-site for re-generation or disposal at an approved facility.

Waste profiles shall be established, in advance, for each of the media. This expedites the media change-out process and ensures minimal downtime for the treatment units. The spent media shall be shipped off-site as a non-hazardous waste using either a Bill of Lading or a non-hazardous waste manifest. The shipping papers will be signed by the Camp Edwards Environmental Manager, Matt McKay, as the Generator of the waste. The USACE will coordinate with Mr. McKay to obtain his signature on the shipping papers.

System optimization of the treatment systems is an ongoing activity and includes various strategies to improve the efficiency of the systems and reduce energy costs. Optimization strategies include the items listed below.

Adjustments to the VFDs to provide the most efficient flow rates and still achieve remedial objectives.

Recommendations for the reduction in sampling frequency or system sample locations, based on observed influent contaminant levels.

Monitor pump amperages to determine pump efficiencies and make recommendations for more energy efficient operations.

Review of pump sequencing and piping systems to minimize redundancy (i.e., turn off effluent pumps and allow the system to discharge on gravity flow).

Temperature monitoring of vaults to determine the need for heat trace during cold weather periods.

System optimization is a dynamic process, and is a direct result of the Contractor’s observations of the system operational status. Expanded optimization strategies shall be evaluated on an on-going basis throughout execution of the task order.

The Contractor shall perform all in-plant monitoring in accordance with the Final Demolition Area 1 Environmental and System Performance Monitoring Report. Change out of expired IX media shall be initiated when perchlorate is detected at a concentration above 0.35 μg/L. Change out of expired GAC media shall be initiated after RDX is detected at a concentration above 0.25 μg/L.

The Contractor shall assume one system carbon and one system IX change-out during the period of performance. The Contractor shall assume the replacement of five well pumps, five pump motors, and four VFDs during the period of performance. The Contractor shall make programming changes to batch flow at a higher flowrate through the Frank Perkins Road system.

Task 3.2 – O&M Support – Demo 1 Off-Base System (Leading Edge System)

The Leading Edge System for Demo 1 is also an MTU. Groundwater is extracted from one extraction well. The treatment train consists of a single treatment train of three pressure vessels configured similar to the Pew Road treatment system. The IX vessel contains 58 cubic feet of

Nitrate Selective IX. The GAC vessel contains 3,000 pounds of GAC. The treatment system has a total maximum process rate up to 100 gallons per minute (gpm).

System and wellfield O&M shall be performed to maintain the treatment systems in the most efficient operational condition and minimize pumping downtime. Monitoring at the treatment systems shall include influent and effluent sampling to demonstrate that the treated water being recharged back into the aquifer through the reinjection wells / reinjection gallery is below the reporting limits for perchlorate and RDX.

O&M activities shall also focus on wellfield maintenance, which shall include execution of both a routine and preventative maintenance program for the extraction and reinjection wells / reinjection gallery and piping.

All O&M activities shall be documented in the project Log Books which shall be maintained at the project field office. The O&M Checklist shall be used to ensure that all required system components are inspected during routine O&M and during media change-out operations. The O&M Checklists shall also note required action items or follow up inspections. The O&M Checklists shall be maintained at each system. An Event Log shall also be maintained at each system to document any downtime, including the reason for the downtime and the duration. All O&M monitoring activities shall be conducted by state-licensed wastewater treatment plant operators.

Table 2 identifies specific O&M activities and their anticipated frequency of completion.

The Contractor shall be responsible for the change-out of treatment media (GAC, IX resin, and bag filters). New media shall be inspected upon receipt to ensure the project specifications are met.

While media vessels are empty, the Contractor shall conduct inspections of the interior of the vessels to validate the integrity of the vessels and document the condition of the interior piping and change-out process and ensures minimal downtime for the treatment units. The spent media shall be shipped off-site as a non-hazardous waste using either a Bill of Lading or a non-hazardous waste manifest. The shipping papers will be signed by the Camp Edwards Environmental Manager, Matt

Recommendations for the reduction in sampling frequency or system sample locations, based on observed influent contaminant levels.

Monitor pump amperages to determine pump efficiencies and make recommendations for more energy efficient operations.

Review of pump sequencing and piping systems to minimize redundancy (i.e., turn off effluent pumps and allow the system to discharge on gravity flow).

Temperature monitoring of vaults to determine the need for heat trace during cold weather periods.

System optimization is a dynamic process, and is a direct result of the Contractor’s observations of the system operational status. Expanded optimization strategies shall be evaluated on an on-going basis throughout execution of the task order.

The Contractor shall assume one system carbon change-out and one system IX change-out during the period of performance. The Contractor shall assume the replacement of one well pump, one pump motor, and one VFD during the period of performance.

5.4 Task 4.0 – J-1 Range South O&M, System Performance Monitoring

The J-1 Range is located adjacent to and southeast of the Impact Area, and is one of the ranges formerly utilized by military contractors for testing and development of various weapons and systems, and by the military for training purposes (see Attachments, Figure 1). The J-1 South groundwater plume consists primarily of RDX and octahydro-1,3,5,7-tetranitro-1,3,5,7-tetrazocine (HMX), and is believed to have originated in the southeast portion of the J-1 Range. The plume migrates in a southeasterly direction away from the southern end of the J-1 Range.

The objective for the J-1 South Rapid Response Action (RRA) is to mitigate further migration of the plume by capturing and treating contaminated groundwater at the base boundary until the entire plume extent is determined. The J-1 Range South treatment system includes:

two extraction wells (J1SEW0001 and J1SEW0002) located at the base boundary near existing monitoring well cluster MW-398, operating at 125 gallons gpm;

one MTU; and one infiltration trench to return treated groundwater to the aquifer.

There are two parallel treatment trains of three GAC vessels each, the first two serving as lead RDX removal vessels and the last acting as a polishing step. After passing through the GAC-GAC-GAC train, the treated water is reintroduced to the groundwater through an infiltration trench. This trench is located along the base boundary southwest of the proposed extraction well. The system O&M requirements are outlined in the Final SPM Plan for the J-1 South.

The Contractor shall be responsible for executing all O&M activities at the J-1 South RRA system in accordance with the language outlined in Task 4 and the most recent Final J-1 South Rapid Response Action System Performance Monitoring Plan.

Task 4.1 – O&M Support

System and wellfield O&M shall be performed to maintain the treatment system in the most efficient operational condition and minimize pumping downtime. Monitoring at the treatment systems shall include influent and effluent sampling to demonstrate that the treated water being recharged back into the aquifer through the infiltration trench is below the reporting limit for RDX.

O&M activities shall also focus on wellfield maintenance, which shall include execution of both a routine and preventative maintenance program for the extraction and infiltration trench and piping.

The Contractor shall prepare monthly O&M Reports and submit via upload to the EDMS system with e-mail notification to the USACE.

All O&M activities shall be documented in the project Log Books which shall be maintained at the project field office. The O&M Checklist shall be used to ensure that all required system components are inspected during routine O&M and during media change-out operations. The O&M Checklists shall also include areas to note required action items or follow up inspections. The O&M Checklists shall be maintained at each system. An Event Log is also maintained at each system to document any downtime, including the reason for the downtime and the duration. All O&M monitoring activities shall be conducted by state-licensed wastewater treatment plant operators.

Table 2 identifies specific O&M activities and their anticipated frequency of completion.

The Contractor shall be responsible for the change-out of treatment media (GAC and bag filters).

New media shall be inspected upon receipt to ensure the project specifications are met. While media vessels are empty, the Contractor shall conduct inspections of the interior of the vessels to validate the integrity of the vessels and document the condition of the interior piping and appurtenances. The results of this inspection shall be documented in the project logbooks and in the O&M Checklist.

Spent media shall be transported off-site for re-generation or disposal at an approved facility.

Waste profiles shall be established, in advance, for each of the media. This expedites the media change-out process and ensures minimal downtime for the treatment units. The spent media shall be shipped off-site as a non-hazardous waste using either a Bill of Lading or a non-hazardous waste manifest. The shipping papers will be signed by the Camp Edwards Environmental Manager, Matt McKay, as the Generator of the waste. The USACE will coordinate with Mr. McKay to obtain his signature on the shipping papers.

System optimization of the treatment systems is an ongoing activity and includes various strategies to improve the efficiency of the systems and reduce energy costs. Optimization strategies include the items listed below.

Adjustments to the VFDs to provide the most efficient flow rates and still achieve remedial objectives.

Recommendations for the reduction in sampling frequency or system sample locations, based on observed influent contaminant levels.

Monitor pump amperages to determine pump efficiencies and make recommendations for more energy efficient operations.

Review of pump sequencing and piping systems to minimize redundancy (i.e., turn off effluent pumps and allow the system to discharge on gravity flow).

Temperature monitoring of vaults to determine the need for heat trace during cold weather periods.

System optimization is a dynamic process, and is a direct result of the Contractor’s observations of basis throughout execution of the task order.

The Contractor shall perform all in-plant monitoring in accordance with the Final J-1 South Environmental and System Performance Monitoring Report. Change out of expired GAC media shall be initiated after RDX is detected at a concentration above the reporting limit of 0.25 μg/L.

The Contractor shall assume one system GAC change-out during the period of performance. The Contractor shall assume the replacement of two well pumps and two pump motors during the period of performance.

5.5 Task 5.0 – J-2 Range East O&M, System Performance Monitoring

The J-2 Range was used by military contractors for the testing and development of various weapons and systems, and by the military for training purposes (see Attachments, Figure 1). Examples of activities conducted by various contractors include propellant and fuse testing, penetration testing for various munitions, fragmentation testing, obscuration testing, infrared testing of tank heat signatures, propellant and waste burning, munitions disposal, and loading of munitions with explosives.

The COC in the J-2 East plume include perchlorate and RDX. The plume consists of a main body and two lobes - western and eastern lobes. The main body of the plume contains both perchlorate and RDX, while the western and eastern lobes are primarily perchlorate.

The objective of the J-2 East Range extraction, treatment, and infiltration (ETI) system is to minimize downgradient migration of the J-2 East Range plume by capturing and treating contaminated groundwater. The major components of the J-2 Range East ETI system include:

Three extraction wells, in an axial arrangement, pumping at a combined total flow rate of approximately 495 gallons per minute (gpm), with a total maximum flow rate of 500 gpm.

An ex-situ treatment process, housed in four MTUs, consisting of IX resin and GAC media to treat perchlorate and explosives.

Infiltration trenches located along the lateral boundaries of the plume where treated water will enter the vadose zone and infiltrate into the aquifer.

The system O&M requirements are outlined in the Final SPM Plan for J-2 East.

The Contractor shall be responsible for executing all O&M activities at the J-2 Range East ETI system in accordance with the language outlined in Task 5 and the most recent Final J-2 Range East System Performance Monitoring Plan.

Task 5.1 – O&M Support

System and wellfield O&M shall be performed to maintain the treatment systems in the most efficient operational condition and minimize pumping downtime. Monitoring at the treatment systems shall include influent and effluent sampling to demonstrate that the treated water being recharged back into the aquifer through the infiltration trenches is below the reporting limit for perchlorate and RDX.

Plant visits shall focus on periodic verification of operating parameters, routine and preventative maintenance, media change-out, and responses to unplanned plant shutdown (e.g., power failure).

O&M activities shall also focus on wellfield maintenance, which shall include execution of both a routine and preventative maintenance program for the extraction and infiltration trenches and piping.

The Contractor shall prepare monthly O&M Reports and submit via upload to the EDMS system with e-mail notification to the USACE.

All O&M activities shall be documented in the project Log Books which shall be maintained at the project field office. The O&M Checklist shall be used to ensure that all required system components are inspected during routine O&M and during media change-out operations. The O&M Checklists shall also include areas to note required action items or follow up inspections. The O&M Checklists shall be maintained at each system. An Event Log shall also be maintained at each system to document any downtime, including the reason for the downtime and the duration. All O&M monitoring activities are conducted by state-licensed wastewater treatment plant operators.

Table 2 identifies specific O&M activities and their anticipated frequency of completion.

The Contractor shall be responsible for the change-out of treatment media (GAC, IX resin, and bag filters). New media shall be inspected upon receipt to ensure the project specifications are met.

While media vessels are empty, the Contractor shall conduct inspections of the interior of the vessels to validate the integrity of the vessels and document the condition of the interior piping and appurtenances. The results of this inspection shall be documented in the project logbooks and in the O&M Checklist.

Spent media shall be transported off-site for re-generation or disposal at an approved facility.

Waste profiles shall be established, in advance, for each of the media. This expedites the media change-out process and ensures minimal downtime for the treatment units. The spent media shall be shipped off-site as a non-hazardous waste using either a Bill of Lading or a non-hazardous waste manifest. The shipping papers will be signed by the Camp Edwards Environmental Manager, Matt McKay, as the Generator of the waste. The USACE will coordinate with Mr. McKay to obtain his signature on the shipping papers.

System optimization of the treatment systems is an ongoing activity and includes various strategies

Recommendations for the reduction in sampling frequency or system sample locations, based on observed influent contaminant levels.

Monitor pump amperages to determine pump efficiencies and make recommendations for more energy efficient operations.

Review of pump sequencing and piping systems to minimize redundancy (i.e., turn off effluent pumps and allow the system to discharge on gravity flow).

basis throughout execution of the task order.

The Contractor shall perform all in-plant monitoring in accordance with the Final J-2 Range East Environmental and System Performance Monitoring Report. Change out of expired IX media shall be initiated when perchlorate is detected at a concentration above the method detection limit of 0.35 μg/L. Change out of expired GAC media shall be initiated after RDX is detected at a concentration above the reporting limit of 0.25 μg/L.

The Contractor shall assume one system carbon change-out during the period of performance.

5.6 Task 6.0 – J-2 Range North O&M, System Performance Monitoring

The purpose of the J-2 Range North groundwater RRA is to begin removing dissolved contaminant mass from the plume while continuing to evaluate the feasibility of comprehensive remedial actions and determining a comprehensive solution (see Attachments, Figure 1). The J-2 North plume is composed principally of perchlorate and RDX. The overall objective of the J-2 North RRA ETI system is to provide hydraulic capture of the majority of the groundwater plume, to control further migration, and to initiate removal and treatment of dissolved contaminant mass contained within the plume.

Groundwater is extracted from three extraction wells: J2EW0001, J2EW0002, and J2EW0003. The water is treated at two facilities consisting of IX resin and GAC media to treat perchlorate and explosives, respectively. Groundwater extracted from J2EW0001 and J2EW0002 is treated at MTUs E and F located at Wood Road and infiltrated through trenches located on Wood Road. Groundwater extracted from J2EW0003 is treated at a 900-square-foot treatment facility on Barlow Road (Treatment Facility G) and infiltrated through trenches located on Jefferson Road. The major components of the J-2 Range North ETI system include:

three extraction wells pumping at a combined total flow rate of approximately 475 gallons per minute (gpm);

an ex-situ treatment process consisting of IX resin and GAC media to treat perchlorate and explosives with the option of using other treatment media in the future; and four infiltration trenches located along the lateral boundaries of the perchlorate plume where treated water enters the vadose zone and infiltrates into the aquifer.

The system O&M requirements are outlined in the Final System Performance and Ecological Impact Monitoring (SPEIM) Plan for the J-2 North plume.

The Contractor shall be responsible for executing all O&M activities at the J-2 Range North RRA system in accordance with the language outlined in Task 6 and the most recent Final J-2 Range North Groundwater Rapid Response Action Annual Performance Monitoring Report.

Task 6.1 – O&M Support efficient operational condition and minimize pumping downtime. Monitoring at the treatment systems shall include influent and effluent sampling to demonstrate that the treated water being recharged back into the aquifer through the infiltration trenches is below the reporting limit for perchlorate and RDX.

O&M activities shall also focus on wellfield maintenance, which shall include execution of both a routine and preventative maintenance program for the extraction and infiltration trenches and piping.

The Contractor shall prepare monthly O&M Reports and submit via upload to the EDMS system with e-mail notification to the USACE.

All O&M activities are documented in the project Log Books which shall be maintained at the project field office. The O&M Checklist shall be used to ensure that all required system components are inspected during routine O&M and during media change-out operations. The

O&M Checklists shall also include areas to note required action items or follow up inspections.

The O&M Checklists shall be maintained at each system. An Event Log shall also be maintained at each system to document any downtime, including the reason for the downtime and the duration.

All O&M monitoring activities shall be conducted by state-licensed wastewater treatment plant operators.