Binding Rates - Labor
| Binding Rates of Professional Labor for SubContractor | |
| SubContractor Name: | |
| SubContractor Role(s): | |
| Document: | Appendix I-2: Labor Binding Rates |
Binding Hourly Rates (Unit Price per Hour) Base Year Contract Year 2 Contract Year 3 Contract Year 4 Contract Year 5
| Principal |
| Program Manager |
| Project Manager* |
| Certified Industrial Hygienist |
| Chemist* |
| Senior Chemist |
| Mid-Level Chemist |
| Junior Chemist |
| Senior Environmental Scientist |
| Mid-Level Environmental Scientist |
| Junior Environmental Scientist |
| Process Engineer* |
| Senior Engineer |
| Mid Level Engineer |
| Junior Engineer |
| Senior Geologist |
| Mid Level Geologist |
| Junior Geologist |
| Senior Hydrogeologist |
| Mid Level Hydrogeologist |
| Junior Hydrogeologist |
| Field Operations Leader* |
| Senior Scientist |
| Mid Level Scientist |
| Junior Scientist |
| QCS Manager |
| Site Superintendent* |
| Site Safety & Health Officer |
| Treatment Plant Operator* |
| Senior Technician |
| Mid-Level Technician |
| Junior Technician |
| Geochemist |
| Regulatory Specialist - LSP |
| Senior Contracts Manager |
| Contracts Manager |
| Senior CADD Operator |
| Mid-Level CADD Operator |
| Junior CADD Operator |
| Senior GIS Technician |
| Mid-Level GIS Technician |
| Junior GIS Technician |
| Administrative Staff |
| Word Processor |
| Cost Reporter |
| Legend: |
| * Key Personnel |
| Junior = less than 5 years experience |
| Mid Level = 5-10 years experience |
| Senior = More than 10 years experience |
Labor Calculated
| Calculated Rates of Professional Labor for SubContractor | |
| SubContractor Name: | |
| SubContractor Role(s): | |
| Document: | Appendix I-2: Labor Calculated |
| Government Job Title | Contractor Job Title | Unit | DIRECT RATE $ | DIRECT RATE (OT) $ | Home Office | Home Office OT | Field Office | Field Office OT | ||||
| Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE | Combined Markup % | TOTAL BURDENED RATE |
| Principal | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Program Manager | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Project Manager* | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Certified Industrial Hygienist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Chemist* | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Chemist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid-Level Chemist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior Chemist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Environmental Scientist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid-Level Environmental Scientist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior Environmental Scientist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Process Engineer* | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Engineer | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid Level Engineer | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior Engineer | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Geologist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid Level Geologist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior Geologist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Hydrogeologist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid Level Hydrogeologist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior Hydrogeologist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Field Operations Leader* | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Scientist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid Level Scientist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior Scientist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| QCS Manager | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Site Superintendent* | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Site Safety & Health Officer | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Treatment Plant Operator* | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Technician | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid-Level Technician | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior Technician | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Geochemist | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Regulatory Specialist - LSP | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior Contracts Manager | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Contracts Manager | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior CADD Operator | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid-Level CADD Operator | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior CADD Operator | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Senior GIS Technician | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Mid-Level GIS Technician | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Junior GIS Technician | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Administrative Staff | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Word Processor | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Cost Reporter | Hour | $ - 0 | $ - 0 | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - | 0.00% | $ - |
| Estimator | |||||||||||
| Legend: | |||||||||||
| * Key Personnel | |||||||||||
| Junior = less than 5 years experience | |||||||||||
| Mid Level = 5-10 years experience | |||||||||||
| Senior = More than 10 years experience |
&G &"Arial,Italic"Remedial Action Contract New Bedford Harbor Superfund Site, Solicitation Number: W912WJ-14-R-0003 &D
Markups
| Binding Markups & Indirect Costs for SubContractor | |
| SubContractor Name: | |
| SubContractor Role(s): | |
| Document: | Appendix I-2: Mark-up Development |
| HOME OFFICE LABOR | |
| Markup Type (Provide Description) | % |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| Combined Markup for home office | 0.00% |
| FIELD OFFICE LABOR | |
| Markup Type (Provide Description) | % |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| Combined Markup for field office/site work | 0.00% |
| All Other Indirect Costs | |
| Markup Type (Provide Description) | % |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% | |
| 0.00% |
&G &"Arial,Italic"Remedial Action Contract New Bedford Harbor Superfund Site, Solicitation Number: W912WJ-14-R-0003 &D
Pick List
| Task 1 |
| Task 2 |
| Task 3a |
| Task 4 |
| Task 3b Initial |
| Task 3b Final |