Q&A_35-42.docx

DOCX document 15 KB Posted

Attached to
MSA Cold Storage - XGFG162010 Federal contract opportunity
Solicitation number
W912J2-19-B-6004
Issued by
Department of the Army Wisconsin Army National Guard

About this file

Questions and Answers 35-42

View the file

Other files for this federal contract opportunity

Other files attached to MSA Cold Storage - XGFG162010, newest first.
File Type Posted
Attendance_Sheet_for_Bid_Opening.pdf PDF
Abstract_of_Offers_1419_MSA_Cold_Storage.pdf PDF
Bid_Opening_FBO_Instructions.docx DOCX document
B.08.Q&A_33-34.docx DOCX document
B.08.W912J2-19-B-6004_Conform_Through_Amenement_5.pdf PDF
B.08.W912J2-19-B-6004-0005.pdf PDF
W912J2-19-B-6004-0004.pdf PDF
XGFG162010_MSA_ACCESS_PLAN.pdf PDF
XGFG162010_Amendment-1_Drawing.pdf PDF
B.08.Q&A_20-32.docx DOCX document
W912J2-19-B-6004-0003.pdf PDF
W912J2-19-B-6004-0002.pdf PDF
B.08.Q&A_14-19.docx DOCX document
B.08.Q&A_4-13_Clarifications.docx DOCX document
Overall_Site_2.PNG PNG image
Overall_Site_PIC.PNG PNG image
Q&A_4-12.docx DOCX document
Overall_Site_1.PNG PNG image
W912J2-19-B-6004-0001.pdf PDF
W912J2-19-B-6003-0001.pdf PDF
Site_Visit_Attendance_Sheet.pdf PDF
Q&A_1-3.docx DOCX document
W912J2-19-B-6004.pdf PDF
XGFG162010_Project_Specs_DEC_2018.pdf PDF
XGFG162010_-_Project_Drawings_DEC_2018.pdf PDF
XGFG162010_Addendum-1.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q35: PLEASE PROVIDE PROPER PROTOCAL FOR SIGNING INTO THE FENCED IN AREA AT THE PROJECT LOCATION THAT WAS MENTIONED AT THE SITE VISIT.

A35: No person is allowed to work at Truax Field without having first been approved for entry access and listed on the EAL (Entry Access List). Persons on the EAL will NOT be allowed access to the site without escort. A Truax Field person with proper authority will check each one in and out of the work-site every time they move through the work-site gate throughout the day. “Operations” are discussed in document W912J2-19-B-6004-0004.

Q36: WILL ALL CONTRACTORS BE REQUIRED TO BE ESCORTED TO THE PROJECT SITE UPON ARRIVAL TO THE GATE?

A36: See number 35

Q37: PLEASE PROVIDE WORK HOURS FOR THIS PROJECT

A37: “Operations” are discussed in document W912J2-19-B-6004-0004.

Q38: PLEASE PROVIDE LOCATION OF STAGING / LAY DOWN AREA FOR MATERIALS. SPECIFICATIONS MENTION CHAIN LINK FENCE, PLEASE CONFIRM IF REQUIRED

A38: See document W912J2-19-B-6004-0004.

Q39: WHAT ARE THE REQUIREMENTS FOR THE DUCTBANK? IS THIS CONCRETE INCASED?

A39: See document t W912J2-19-B-6004-0004. No concrete encasement.

Q40: PLEASE SPECIFY WHO DOES TERMINATIONS FOR THE SECURITY / LVS WIRING?

A40: See document W912J2-19-B-6004-0004. Your subcontractor.

Q41: WHO IS THE PREFERRED FA VENDOR ON SITE?

A41: None

Q42: IN REGARDS TO THE OVERALL SITE 1 IMAGE - WHAT WIRE IS EXISTING IN THE 4" CONDUITS?

A42: See document W912J2-19-B-6004-0004.