B.08.W912J2-19-B-6004-0005.pdf
PDF 299 KB Posted
- Attached to
- MSA Cold Storage - XGFG162010 Federal contract opportunity
- Solicitation number
- W912J2-19-B-6004
About this file
Update drawings and specifications
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XGFG162010
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to modify the Draw ings and Addendum-1 (w hich w as put out w ith the original solicitation package.) See summary of changes.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Feb-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912J219B6004
X 9B. DATED (SEE ITEM 11)
14-Jan-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Feb-2019
CODE
USPFO FOR WISCONSIN CONTRACTING OFFICE
3110 MITCHELL STREET
MADISON WI 53704-2591
W912J2 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912J219B6004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 5
The amendment herein modifies the Drawings and Addendum-1 with regard to the water-main relocation for the above project. This amendment only applies to the item(s) specifically as stated herein and shall be incorporated as clarifying and revising Addendum-1 dated 10 December 2018; Para. 3 and project drawing set dated December 2018:
1. The existing water-main to be relocated around the new building is shown on Govt. “As-Built” drawings to be 10” ductile iron pipe installed in 2006.
2. Delete requirement to perform wet connections and taps.
3. Delete requirement to furnish and install curb stops and risers.
4. Where new water-main connections are shown on the drawings:
(a) Contractor shall furnish and lay as much new pipe as possible; make preparations to extent possible; plan for disinfection and testing; and schedule the work in coordination with the facility users; all prior to cutting-off existing pipe and taking water out of service to minimize out of service down time and inconvenience to the Govt.
(b) New connections shall be DI fittings with thrust blocks in accordance with standard practice and direction from Madison Water Utility.
(c) Backflow from severed pipe to drain the water-main between valves. The contractor shall be responsible for, and pay all costs, associated with backflow water and provide pumping and drainage to de-water excavations as result.
5. Amendment-4 dated 13 February 2019; Para. 4 is un-changed.
End of Amendment 5
W912J219B6004
(End of Summary of Changes)