00_73_15.15_Time_Extensions_for_Unusually_Severe_Weather.pdf

PDF 22 KB Posted

Attached to
FY 2013 ITALY Multiple Award Task Order Contract (MATOC)
Solicitation number
W912GB13R0007
Issued by

About this file

SECTION 00 73 15.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER dated 01/09

View the file

Other files

File Type Posted
13-R-0007 _Pre-Proposal_Conference_sign-in_sheet _07_February_2013.pdf PDF
C-5_13-R-0007_Amend_0006_25Feb2013.pdf PDF
Italy2013presentation07FEB2013.pdf PDF
C-5 _13-R-0007 _Amendment_0004 _11_February_2013.pdf PDF
C-02 _13-R-0007 _Attachment_4 _BankLetterAssuranceSample.docx DOCX document
C-5 _13-R-0007 _Amendment_0003 _05_February_2013.pdf PDF
C-05 _MATOC-D_Section_00_41_00_Pricing_Schedule111.xlsx XLSX spreadsheet
C-02 _13-R-0007 _Attachment_2 _ExperienceInfoSheet.docx DOCX document
C-5 _13-R-0007 _Amendment_0002 _22_January_2013.pdf PDF
01_78_00_Completion_Procedures.pdf PDF
02_82_14.00_10_Asbestos_Hazard_Control_Activities.pdf PDF
01_00_15_Design_After_Award.pdf PDF
02_41_00_Demolition_and_Deconstruction.pdf PDF
01_33_00_Submittal_Procedures.pdf PDF
Construction_Signs.pdf PDF
00_73_16.02_Special_Conditions_for_Projects_in_Italy.pdf PDF
01_45_01_USACE_Quality_Control.pdf PDF
01_32_01.00_10_Project_Schedule.pdf PDF
01_35_26.15_Additional_Safety_and_Occupational_Health_Requirements_for_Projects_in_Italy.pdf PDF
01_45_01.10_USACE_QUALITY_CONTROL_SYSTEM_(QCS).pdf PDF
01_35_26_Safety_and_Occupational_Health_Requirements.pdf PDF
01_78_23_Operation_and_Maintenance_Data.pdf PDF
00_73_15_General_Conditions.pdf PDF
C-05 _13-R-0007 _Solicitation_FY13_Italy_MATOC _20_DEC_2012.pdf PDF
C-02 _13-R-0007 _Attachment_2 _ExperienceInfoSheet.docx DOCX document
C-02 _13-R-0007 _Attachment_3 _PastPerformanceClientForm.docx DOCX document
C-02 _13-R-0007 _Attachment_5 _BankLetterGuaranteeSample.docx DOCX document
C-02 _13-R-0007 _Attachment_4 _BankLetterAssuranceSample.docx DOCX document
C-02 _13-R-0007 _Attachment_1 _ExperienceOverviewSheet.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 73 15.15

TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

01/09

1. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

c. The delay must occur during the contractual performance period.

Weather delays occurring after the required completion date, prior to Notice to Proceed, or during other non-working days are not excusable under the Defaults clause.

2. The following schedule of monthly anticipated adverse weather delays will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather lays in all weather dependent activities. de

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Projects Located in Africa 3 3 4 5 7 6 7 4 4 4 3 3

Projects Located in Israel 5 5 4 1 0 0 0 0 0 1 3 5

All Other Countries and Locations 8 6 7 6 5 5 5 4 4 6 7 8

Monthly anticipated adverse weather delays shall be adjusted proportionately should the actual work week be based on more or less than 5 work days (i.e.

if a 6 day work week, the anticipated adverse weather delay work days for a month would be adjusted by multiplying the number shown above by 6/5).

3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract performance period, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Impacted activities shall be identified by name and activity id on the CQC report.

Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.

The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather

SECTION 00 73 15.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

01/09 delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".

4. When the contract performance period, or any extension thereof, has passed, no extensions for unusually severe weather will be granted.

-- End of Section --