This statement of work outlines requirements for renovations to cardio rooms and surrounding areas at a military facility. The scope of work includes replacing windows, removing and replacing flooring, updating electrical systems, replacing mirrors and ceiling tiles, installing concrete pads and LED lighting, and renovating HVAC systems. Specific requirements include installing new padded polyurethane flooring covering over 1,600 square feet and 1,200 square feet in two rooms; adding and relocating over 20 electrical outlets to floor-mounted locations in dedicated circuits; replacing three 36,000 BTU split AC units; and installing concrete pads and LED lighting in exterior areas. The contractor must follow all applicable building codes and regulations and dispose of waste according to the facility's guidelines.
This notice announces a competitive set-aside award for a multiple award task order contract for real property repair, maintenance, and minor construction services on military installations in Hawaii. The North American Industry Classification System code assigned is 236220. The contracting agency intends to award a minimum of four contracts under this solicitation to women-owned small businesses. The base period of each contract is one year with four optional one-year extensions. The minimum guarantee for each awardee is $20,000 annually, and offerors must provide a $3 million bid guarantee to be eligible for award. The total value of task orders to any one contractor cannot exceed $92.4 million.
Attachment 2 Seed Project
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
January 8, 2018
BLDG 488, SB
STATEMENT OF WORK
Site Location SB, Bldg. 488
FEWR NO: MM440018J Renovate Cardio Rooms POC: Rey Ben 864-0834 Facility POC: Darold Homan (DFMWR) 656-0088 Mary Burghardt 655-8006
West Cardio Room 121
Remove and Replace existing louvers with new awning windows. Awning window shall have aluminum framing and shall be the same locking mechanism as the weight room.
Remove the entire flooring and replace with a (monolithic), dual-durometer, padded polyurethane athletic flooring system. SIGNAFlor or approved equal. Floor is approximately 1681 SF.
Replace 8 each existing duplex receptacles along the walls and add 6 each new receptacles. See electrical layout.
Install new 20 amps dedicated circuit single receptacle recessed on the floor. Receptacle shall have cover that can be close when plug is inserted to the receptacle. See electrical layout.
Remove and replace 8 feet x 4 feet mirror with wooden frame. New mirror shall be the same size with metal trim.
6. Repaint the entire interior with the same scheme and color including trusses. interior surfaces shall be prepare, prime, and paint with 2 coats.
Install large ceiling fan (BigAss 10’ POWERFOIL X 3.0) or approved equal. Controller shall comply with NEC and UL standards, and shall be labeled as required by code. See fan layout.
STATEMENT OF WORK
Red machine needs dedicated circuit receptacle.
Orange machine needs 20 amps receptacle.
Moving, reinstalling, and purchasing of equipment is not included in the SOW.
Room 121 Equipment New Layout
Floor Mount Dedicated Circuit Receptacle Existing Duplex Receptacle Room 121 Receptacle Layout
New Duplex receptacle Not To Scale
Remove louvers and replace with awning windows.
Remove louvers and replace with awning windows.
The lower awning window shall be at least 3 feet above the ground.
The rest of the opening shall be block off with CMU.
Remove and replace flooring.
Demo wall and recessed all receptacles on the floor.
Install 2 each bigass ceiling fans.
Remove wall
East Cardio Room 118
Replace all louvers with aluminum frame awning windows on the east side of the room. Remove all louvers where AC located and block the area with drywall inside and Masonite siding outside side.
2. Remove the entire flooring to include raised floor and replace with a (monolithic), dual-durometer, padded polyurethane athletic flooring system. SIGNAFlor or approved equal. Floor is approximately 1225 SF.
Replace 9 each existing duplex receptacles along the walls and add 1 each new receptacles. See electrical layout.
Install 10 each new 20 amps dedicated circuit single receptacle recessed on the floor. Receptacle shall have cover that can be close when plug is inserted to the receptacle. See electrical layout.
Remove all existing TV monitors receptacles. Install 4 each new 20 amps duplex receptacle for a new TV monitors to the adjacent wall. Receptacle shall be 3 feet apart at center of the wall and the same height as the existing
6. Replace 1 each 10 sectional 20 feet x 8 feet wall mirrors with 5 sectional 20 feet x 4 feet wall mirror. Replace 2 each 4 feet x 8 feet wall mirror with 4 each 4 feet x 4 feet. Replace 1 each 5 feet x 5 feet with 4 feet x 4 feet.
Mirrors shall be installed in the same location but above the soffit line.
Repaint the entire exterior with the same scheme and color including trusses. Exterior surfaces shall be prepare, prime, and paint with 2 coats.
8. Replace all drop ceiling tiles approximately 1225 SF. Ceiling grids and Light fixtures to remain.
Remove and replace 3 each 36,000 BTU split AC system to include piping, wirings and 30 amps disconnects.
New disconnect shall be NEMA 4X.
STATEMENT OF WORK
Room 118 Receptacle Layout Floor Mount Dedicated Circuit Receptacle Existing Duplex receptacle New Duplex receptacle
Not To Scale
Red machine needs dedicated circuit receptacle.
Yellow machine needs 20 amps receptacle.
Moving, reinstalling, and purchasing of equipment is not included in the SOW.
January 8, 2018 Room 118 Equipment New Layout
Remove and replace flooring.
Remove louvers and replace with aluminum frame awning windows.
Remove and replace 3 each 36,000 BTU Split AC.
Remove louvers and block off area.
Room 118 Remove raised floor
STATEMENT OF WORK
Court Area
Remove existing water fountain immediately outside of weight room and replace with two each side by side. Water fountains shall have automatic water dispenser. See picture below.
Install 3 concrete pads (outside the women's locker room, east of the RB court #9, and west of RB court #1) approximately 2000 SF. Concrete pad shall be 4 inches thick, broom finish, and reinforced with 10/10 welded wire mesh.
Replace 6 inches wide interior courtyard drain covers approximately 520 feet long. Drain cover shall be 6 inches by 12 inches sections and can stand traffic load of 35,000 lb.
Install 5 each Lumecon LED flood lights, yoke mounted, 80-120W range. Light shall be installed on the top edge of the Gym overhang. Power supply from weight room panel and switch beside the panel.
New Water Fountain
Install concrete pad Install concrete pad Install concrete pad
Install 5 each LED flood lights
NOTE:
1. The entire installation shall comply with all applicable requirements of the current versions of the International Building Code, Plumbing Code, National Fire Protection Association, NFPA 90A, ASME Pressure Piping Code, Federal OSHA codes, National Electrical Code, DPW AC guide lines and all other agencies having jurisdiction.
2. The Contractor shall verify all equipment sizes, weights, connection locations and required clearances for installation and maintenance at the jobsite and coordinate their requirements with the manufacturer. All equipment supports and piping shall not obstruct equipment access areas for maintenance service and repairs.
Repair any damage to existing construction resulting from the installation of window and mechanical items. The areas repaired shall match the adjacent surfaces in texture and color.
All new equipment shall be labeled with the same nomenclature as the replaced equipment. Labels shall follow ASME
(ANSI) Standard A13.1-2007 for label color, text color, and label size and text.
The SOW is intended to cover the complete installation of systems to function as described and specified. The omission of reference to any necessary item of labor or material shall not relieve the contractor from providing such labor and material.
7, All equipment must be capable of fitting into the spaces allocated while meeting the manufacturer's recommended access requirements. Review all spaces where equipment is to be installed prior to ordering of equipment and notify the project manager of any inadequate clearances or conditions that will prevent the proper installation, maintenance and operation of the equipment.
8. Properly firestop all penetrations through fire rated walls, floors, or partitions with a UL approved system appropriate for the penetration type and fire rating.
Contractor shall dispose all recyclable materials according to DPW C&D waste guide line. Form attached.
Contractor shall submit a project specific AHA. Contractor to provide pertinent certifications that were not submitted in the Master Safety Plan & AHA and also indicate which certifications were included in the Master Safety Plan & AHA.
11. Contractor shall submit AC Unit Specifications, Awning windows, and flooring specification and color selection chart.
Fax this form and corresponding weight receipts to: (808) 656-1039 Revised 2/2/2012 ATTN: Solid Waste/Recycling Program Manager, DPW Environmental
Project Title:
Project #:
Asphalt Concrete Dirt Metals Wood Waste Green Waste Corrugated Cardboard Deconstruction Total % Diversion:
Other: ________________ (a+c)/(a+b+c) x 100 Total (tons)
1. Were deconstruction options considered for this project as outlined in PWTB 200-1-23? YES / NO If not, please provide justification:
2. Was 50% of the material diverted from the landfill per EO 13514 and Army Regulation 420-1? YES / NO If not, please provide justification:
Name of company:
Person completing form: Signature:
Period covered: From: To:
Type of Material Name of Disposal Facility (a) Recycled (tons)
(b) Class III Landfill Disposal (tons)
(c) Reused (tons)
Summary of Solid Waste Disposal and Diversion
Sheet1