W911XK20R0010 Amendment 0002 11 December 2020.pdf

PDF 399 KB Posted

Attached to
Medium Voltage Switchgear, Saint Marys River, MI
Solicitation number
W911XK20R0010
Issued by

About this file

This solicitation requests construction services for replacing medium voltage switchgears at a hydroelectric power plant in Sault Sainte Marie, Michigan. The project involves replacing two 5kV switchgears and a dry type transformer located in the New Power Plant with new equipment. Additional work includes cabling, generator transformer installation, benchboard modifications, metering, control switches, wiring, protective relaying for new feeders, and surge arrestors. The plant provides power to the local community, so outages will be limited or phased. The site is remotely located and waterbound, requiring over-water transport by the Government or contractor. The procurement is full and open with a HUBZone 10% price evaluation factor. The estimated cost is between $1,000,000 to $5,000,000. The NAICS code is 238210. Site visits will be scheduled individually between November 18, 2020 from 0700 to 1530 Eastern Time. The contractor must self-perform 25% of the work. Interested parties must register in SAM to conduct business with the Federal Government.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W56MES92982895

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Medium Voltage Sw itchgear Amendment 0002 This amendment is issued to:

1. Revise the specif ications and plan as described in Section SF 30 Block 14 Continuation Page

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Dec-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911XK20R0010

X 9B. DATED (SEE ITEM 11)

10-Nov-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Dec-2020

CODE

U.S.ARMY ENGINEER DISTRICT, DETROIT

477 MICHIGAN AVENUE, 7TH FLOOR

DETROIT MI 48226-4523

W911XK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911XK20R0010

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

AMENDMENT 0002

SUMMARY OF CHANGES

CERTIFIED FINAL DOCUMENTS – W911XK20R0010 TECHNICAL DRAWINGS

The following Sheets have been revised:

E-801 CABLE AND CONDUIT SCHEDULE, 5 KV SWITCHGEAR, INSTALL

Removed fiber optic cable requirements.

CERTIFIED FINAL DOCUMENTS – W911XK20R0010 TECHNICAL SPECIFICATIONS

The following Sections have been revised:

26 13 26.00 METAL-CLAD SWITCHGEAR

Paragraph 1.2 REFERENCES Deleted reference to IEEE C37.013.

Paragraph 2.1.2 CODE COMPLIANCE Deleted reference to IEEE C37.013.

Paragraph 2.2.2 CIRCUIT BREAKER RATINGS Revised Closing and Latching Capability from 137 kA to 65 kA peak.

Paragraph 2.3.2 CONFIGURATION Revised width from 36-inch to ‘26-inch width sections as shown or as determined by manufacturer’.

Paragraph 2.4.1 CIRCUIT BREAKER Deleted reference to IEEE C37.013.

Paragraph 2.4.3 RATED TRANSIENT RECOVER VOLTAGE Deleted sentence ‘For generator rated circuit breakers the transient voltage withstand shall meet the requirements as described in IEEE C37.013.

Paragraph 2.4.6.3.a. OPERATING CAPACITY Revised reference from IEEE C37.013 to IEEE C37.09.

Paragraph 3.1.3 Deleted reference to IEEE C37.013.

Paragraph 2.2.2 CIRCUIT BREAKER RATINGS Revised BIL from 95 kV to 60 kV and withstand current from 50kA to 25kA.

Solicitation Issued November 10, 2020 Solicitation #

W91XK20R0010

Questions Received from 03 December

2020 to 08 December 2020 5 kV Switchgear

Number Question Answer 55 There appears to be missing run lengths for cables 3AF-1, 3AF2-1, SP-c1-RP0, and SP-c3-RP4. Can these values be provided?

Cable 3AF-1 is 1400'; 3AF2-1 is 1650'; SP- C1-RP0 is 75'; SP-C3-RP4 is 75'

There appears to be missing conductor quantities for cables 3AF3-1, 3AF3-2, and 3AF4-1. Can this information be provided?

3AF3-1 is 3-1/C; 3AF3-2 is 3-1/C; 3AF4-1 is 3-1/C

57 Note #5 on E501 states to remove unused pilot cables in the conduit between the manhole and the gear. Are these cables to be cut and capped and abandoned in the manhole?

If no plan to tie in to plant SCADA, etc.

recommend have cables cut and capped as suggested.

58 Sheet E801 cable tag #’s TA-C3 indicate single strand fiber. Is there any specifications on the fiber cable needed?

Interconnections to transformer TA will be hard-wired only. See amended drawing E801.

59 Per the addendum #1 drawing E101 you have added replacing the CT’s for U3A.

Do you have a part number, size, etc. for the existing CT’s so that we can match them.

Existing CTs are 3-ph Y, 400/5.

Manufacturer, Westinghouse Style 1294077, per reference drawing 30-A-4589 (pdf sheet 4).

60 Will there be a time post bid to do a preliminary shut down of the 5KV gear and turbine to do research on the equipment? If so how long of a duration can we shut this gear down?

One day outage is permissible before 01 Jun 2021.

61 What are the allowed working hours? Working hours can be found in spec 01 12

16.00 26 para 1.5 and 01 35 00 paraagraph1.6.17.

62 Will we be allowed to work two shifts in order to meet the POP? If so, will the Superintendent and Quality Control Manager need to on site during the second shift?

The work hours are limited to 12 hours a day per spec 01 12 16.00 26 para 1.5 and 01 35 00 para 1.6.17. Whether that is done in one or two shifts is up to the contractor.

The Superintendent, QC Manager and SSHO must be on site whenever any work is being performed per specs 01 35 13, 01 35 26, and 01 45 00.00

63 Sheet E101; based on scale noted on drawing it appears that overall depth is drawn as 84”. Please confirm.

Switchgear design depth is 85" and is conceptual and based on commercially available switchgear footprint.

64 E601; fuse(s) shown to feed existing Excitation PPT transformer. Please confirm amp rating required. Max fuse ampacity rating available is 25A. This would be configured as a PT drawer/compartment but with only fuses.

In Metal Clad switchgear design, this is the only fuse option.

Fuses are rated at 20A.

65 E201; please confirm that “panel detail” is for components to be mounted in first structure (left side) of the 5kva switchgear. Noted as control panel on elevation view.

The location of the detail showing the SEL 587Z and associated devices is subject to manufacturer design and Government submittal approval.

66 26 13 26 – 1.2, 2.1.2, 2.4.1, 2.4.3, 2.4.6.3, 3.1.3 – Standard C37.13 is referenced in each of these sections.

C37.13 applies specifically to generator rated breakers. Breakers meeting this standard are not available to be installed into a 26” wide structure. Breakers that can be supplied in 26” wide (narrow) structures comply with C37.09. Please clarify if C37.13 is to be met. And note, if this is required. The proposed switchgear will be wider than shown in bid documents.

IEEE C37.13 was removed from amended Section 26 13 26.00 26. Appropriate references to IEEE C 37.09 were added to amended Section 26 13 26.00.

67 26 13 26 – 2.3.2 – First sentence in spec section references the new switchgear to be supplied with 36” wide sections but sheet E201 and E101 appear to show 26” wide structures. Please clarify which width is required.

26 inch wide structures are acceptable. See related response to amendment 0002, RFI item 66.

68 26 13 26 – 2.2.2.e; Closing and Latching Capability has 137kA peak listed. This is not offered in 26” wide narrow design (and does not match the new ratings in Ammend 001 (25kA and 60kVBIL).

Breakers at the revised ka kVBIL rating would have the following closing ratings:

(97kA crest at 2.7K times rated short circuit current and 58kA rms sym at 1.6K times rated short circuit current. Please advise if these closing and latching ratings are acceptable.

Per referenced standard IEEE C37.04 the closing and latching maximum peak capability has been amended to 65,000 A.

See amended Section 26 13 26.00 26.

69 Drawings ED713 and E-713 appear to be missing cabling designations. Can this information be provided?

See note 5 on subject drawing. The comment missing information is non-biddable, therefore will be provided post-award.