This is a Department of the Army Permit issued by the U.S. Army Corps of Engineers, Jacksonville District, authorizing the City of Plant City to conduct wetland construction and restoration activities at McIntosh Preserve in Plant City, Florida. The permit (SAJ-2024-04226(SP-CM)) authorizes the discharge of dredged material into approximately 88 acres of wetlands to improve an existing stormwater treatment system through grading activities to expand the total wetland footprint and reconfigure existing treatment wetland cells by moving and regrading berms. The project site is located at 775 East Knights Griffin Road (Latitude 28.07001, Longitude -82.12628) in Hillsborough County, Florida, with aquatic resources draining into East Canal, Itchepackesassa Creek, and ultimately Blackwater Creek. The permit was issued on December 19, 2025, with work authorization to commence immediately upon notification to the Corps, and includes a completion deadline of November 30, 2030.
The permit imposes extensive special conditions requiring the City of Plant City to submit commencement notification within 10 days of initiating work, maintain permit copies at the construction site, record a Notice of Department of the Army Authorization with the County Clerk within 90 days, submit as-built certification drawings within 60 days of completion, and comply with erosion control, turbidity barrier, and fill material standards. Additional conditions require adherence to U.S. Fish and Wildlife Service protection measures for Eastern Indigo Snakes, compliance with water quality certification requirements, and immediate notification procedures for any discovery of archaeological or historic remains. The project is partially funded through a State of Florida Department of Environmental Protection grant (Grant Agreement No. LPA0038), and all work must be conducted in accordance with the grant terms and conditions. The permit is issued under Section 404 of the Clean Water Act and does not relieve the permittee of requirements to obtain other necessary Federal, State, or local authorizations.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE ARMY
U.S. ARMY CORPS OF ENGINEERS, JACKSONVILLE DISTRICT
701 SAN MARCO BOULEVARD
JACKSONVILLE, FLORIDA 32207
December 19, 2025
Regulatory Division West Permits Branch Tampa Section
SAJ-2024-04226(SP-CM)
City of Plant City c/o Lynn Spivey 1500 West Victoria Street Plant City, Florida 33563-3059 Sent via email: lspivey@plantcitygov.com
Dear Ms. Spivey:
The U.S. Army Corps of Engineers (Corps) is pleased to enclose the Department of the Army permit, which should be available at the construction site. Work may begin immediately but the Corps must be notified of:
a. The date of commencement of the work,
b. The dates of work suspensions and resumptions of work, if suspended over a week, and
c. The date of final completion.
This information should be emailed to the Enforcement Section of the Regulatory Division of the Jacksonville District at saj-rd-enforcement@usace.army.mil. The Enforcement Section is also responsible for inspections to determine whether Permittees have strictly adhered to permit conditions.
Should any other agency require and/or approve changes to the work authorized or obligated by this permit, it is the responsibility of the Permittee to submit a modification request to the Tampa Permits Section. The Corps will evaluate the request and determine whether it is appropriate to modify the terms and conditions of the permit.
The Permittee must obtain written approval of the requested modifications from the Corps prior to initiation of those changes.
-2-
IT IS NOT LAWFUL TO DEVIATE FROM THE APPROVED PLANS ENCLOSED.
Sincerely, for Shawn H. Zinszer Chief, Regulatory Division
Enclosures cc (w/ encls):
Amy Tracy, Dewberry, atracy@Dewberry.com Scott Knight, Wetland Solutions, Inc., sknight@wetlandsolutionsinc.com SAJ Enforcement, saj-rd-enforcement@usace.army.mil
DEPARTMENT OF THE ARMY PERMIT
Permittee: CITY OF PLANT CITY c/o Lynn Spivey 1500 West Victoria Street Plant City, Florida 33563-3059
Permit No: SAJ-2024-04226(SP-CM)
Issuing Office: U.S. Army Engineer District, Jacksonville
NOTE: The term "you" and its derivatives, as used in this permit, means the permittee or any future transferee. The term "this office" refers to the appropriate district or division office of the U.S. Army Corps of Engineers (Corps) having jurisdiction over the permitted activity or the appropriate official of that office acting under the authority of the commanding officer.
You are authorized to perform work in accordance with the terms and conditions specified below.
Project Description: The project results in the discharge of dredged material into approximately 88 acres of wetlands to improve an existing stormwater treatment system within the McIntosh Preserve. The discharge occurs as a result of grading activities to expand the total wetland footprint on the site and to reconfigure existing treatment wetland cells by moving and regrading existing berms. The work described above is to be completed in accordance with the 44 pages of drawings [and 9 attachments] affixed at the end of this permit instrument.
Project Location: The project would affect aquatic resources associated with wetlands that drain into East Canal, which drains into Itchepackesassa Creek, which drains into Blackwater Creek, a navigable water. The project site is located at 775 East Knights Griffin Road; at Latitude 28.07001°, Longitude -82.12628°; in Plant City, Hillsborough County, Florida.
Directions to site: From Interstate 4, take Exit 21 (State Route 39 / Alexander Street), go north on North Alexander Street (SR-39) approximately 2 miles. Turn right (east) on East Knights Griffin Road and continue approximately 0.9 mile to the McIntosh Preserve entrance and parking lot on the right.
Approximate Central Coordinates: Latitude: 28.07001 North Longitude: -82.12628 West
PERMIT NUMBER: SAJ-2024-04226
PERMITTEE: City of Plant City
Permit Conditions
General Conditions:
1. The time limit for completing the work authorized ends on November 30, 2030. If you find that you need more time to complete the authorized activity, submit your request for a time extension to this office for consideration at least one month before the above date is reached.
2. You must maintain the activity authorized by this permit in good condition and in conformance with the terms and conditions of this permit. You are not relieved of this requirement if you abandon the permitted activity, although you may make a good faith transfer to a third party in compliance with General Condition 4 below. Should you wish to cease to maintain the authorized activity or should you desire to abandon it without a good faith transfer, you must obtain a modification of this permit from this office, which may require restoration of the area.
3. If you discover any previously unknown historic or archeological remains while accomplishing the activity authorized by this permit, you must immediately notify this office of what you have found. We will initiate the Federal and State coordination required to determine if the remains warrant a recovery effort or if the site is eligible for listing in the National Register of Historic Places.
4. If you sell the property associated with this permit, you must obtain the signature and the mailing address of the new owner in the space provided and forward a copy of the permit to this office to validate the transfer of this authorization.
5. If a conditioned water quality certification has been issued for your project, you must comply with the conditions specified in the certification as special conditions to this permit. For your convenience, a copy of the certification is attached if it contains such conditions (Attachment 2).
6. You must allow representatives from this office to inspect the authorized activity at any time deemed necessary to ensure that it is being or has been accomplished in accordance with the terms and conditions of your permit.
Special Conditions:
Special Condition 1: Reporting Address: The Permittee shall submit all reports, notifications, documentation, and correspondence required by the general and special conditions of this permit to either (not both) of the following addresses:
a. For electronic mail (preferred): SAJ-RD-Enforcement@usace.army.mil (not to exceed 15 MB).
b. For standard mail: U.S. Army Corps of Engineers, Regulatory Division, Enforcement Section, P.O. Box 4970, Jacksonville, FL 32232-0019.
The Permittee shall reference this permit number, SAJ-2024-04226(SP–CM), on all submittals.
Special Condition 2: Commencement Notification: Within 10 days from the date of initiating the work authorized by this permit, the Permittee shall submit a completed “Commencement Notification” form (Attachment 3).
Special Condition 3: Posting of Permit: The Permittee shall have available and maintain for review a copy of this permit and approved plans at the construction site.
Special Condition 4: Notice of Permit: The Permittee shall complete and record the “Notice of Department of the Army Authorization” form (Attachment 4) with the Clerk of the County Court, Registrar of Deeds or other appropriate official charged with the responsibility of maintaining records of title to or interest in real property within the county of the authorized activity. No later than 90 days from the effective date of this permit, the Permittee shall provide a copy of the recorded Notice of Permit to the Corps clearly showing a stamp from the appropriate official indicating the book and page at which the Notice of Permit is recorded in the official records and the date of recording.
Special Condition 5: As-Built Certification: Within 60 days of completion of the work authorized by this permit, the Permittee shall submit as-built drawings of the authorized work and a completed “As-Built Certification by Professional Engineer or Surveyor” form (Attachment 5) to the Corps. The as-built drawings shall be signed and sealed by a registered professional engineer or surveyor and include the following:
a. A plan view drawing of the location of the authorized work footprint, as shown on the permit drawings, with an overlay of the work as constructed. The plan view drawing should show all existing water management structures and the completed structures, dredge/fill activities, and wetland impacts.
b. A list of any deviations between the work authorized by this permit and the work as constructed. In the event that the completed work deviates, in any manner, from the authorized work, describe on the attached “As-Built Certification by Professional Engineer” form the deviations between the work authorized by this permit and the work as constructed. Clearly indicate on the as-built drawings any deviations that have been listed. Please note that the depiction and/or description of any deviations on the drawings and/or “As-Built Certification by Professional Engineer” form does not constitute approval of any deviations by the Corps.
c. The Department of the Army permit number on all sheets submitted.
Special Condition 6: Cultural Resources/Historic Properties:
a. No structure or work shall adversely affect, impact, or disturb properties listed in the National Register of Historic Places (NRHP), or those eligible for inclusion in the
NRHP.
b. If, during the ground disturbing activities and construction work within the permit area, there are archaeological/cultural materials encountered which were not the subject of a previous cultural resources assessment survey (and which shall include, but not be limited to: pottery, modified shell, human remains, ceramics, stone tools or metal implements, dugout canoes, evidence of structures or any other physical remains that could be associated with native cultures or early colonial settlement), the Permittee shall immediately stop all work and ground-disturbing activities within a 100-meter diameter of the discovery and notify the Corps at the addresses listed in the Reporting Address Special Condition within the same business day (8 hours). The Corps shall coordinate with the Florida State Historic Preservation Officer (SHPO) to assess the significance of the discovery and devise appropriate actions.
c. Additional cultural resources assessments may be required of the permit area in the case of unanticipated discoveries as referenced in accordance with the above Special Condition and, if deemed necessary by the SHPO or Corps, in accordance with 36 CFR 800 or 33 CFR 325, Appendix C (5). Based on the circumstances of the discovery, equity to all parties, and considerations of the public interest, the Corps may modify, suspend, or revoke the permit in accordance with 33 CFR Part 325.7. Such activity shall not resume on non-federal lands without written authorization from the SHPO for finds under his or her jurisdiction, and from the Corps.
d. In the unlikely event that unmarked human remains are identified on non-federal lands; they will be treated in accordance with Section 872.05 Florida Statutes. All work and ground disturbing activities within a 100-meter diameter of the unmarked human remains shall immediately cease and the Permittee shall immediately notify the medical examiner, Corps, and State Archaeologist within the same business day (8 hours). The Corps shall then notify the appropriate SHPO. Based on the circumstances of the discovery, equity to all parties, and considerations of the public interest, the Corps may modify, suspend, or revoke the permit in accordance with 33 CFR Part 325.7. Such activity shall not resume without written authorization from the SHPO and from the Corps.
e. If prehistoric or historic artifacts such as pottery or ceramics, projectile points, dugout canoes, metal implements, historic building materials, or any other physical remains that could be associated with Native American, early European, or American settlement are encountered at any time within the project site area, the permitted project shall cease all activities involving subsurface disturbance in the vicinity of the discovery.
The applicant shall contact the Florida Department of State, Division of Historical Resources, Compliance Review Section at (850) 245-6333. Project activities shall not resume without verbal and/or written authorization. In the event that unmarked human remains are encountered during permitted activities, all work shall stop immediately and the proper authorities notified in accordance with Section 872.05, Florida Statutes.
Special Condition 7: Eastern Indigo Snake Protection Measures and Inspection:
Permittee shall comply with U.S. Fish and Wildlife Service's “Standard Protection Measures for the Eastern Indigo Snake” dated May 2024, as provided in Attachment 6 of this permit.
Special Condition 8: Proposed Species/Critical Habitat: The action falls within the range for the tri-colored bat (Perimyotis subflavus), which is proposed to be federally listed under the Endangered Species Act. If the species becomes federally listed and the authorized work has not been completed, the Permittee is required to stop work and ask the Corps to re-evaluate the effects of the permitted action on the tri-colored bat, and if needed, complete Section 7 consultation with the U.S. Fish and Wildlife Service to address potential impacts to the tri-colored bat.
Special Condition 9: Erosion Control: Prior to the initiation of any work authorized by this permit, the Permittee shall install erosion control measures along the perimeter of all work areas to prevent the displacement of fill material outside the work area into waters of the United States. The erosion control measures shall remain in place and be maintained until all authorized work is completed and the work areas are stabilized.
Special Condition 10: Turbidity Barriers: Prior to the initiation of any of the work authorized by this permit, the Permittee shall install floating turbidity barriers with weighted skirts around all work areas that are in, or adjacent to, surface waters. The turbidity barriers shall remain in place and be maintained daily until the authorized work has been completed and turbidity within the construction area has returned to ambient levels. Turbidity barriers shall be removed upon stabilization of the work area.
Special Condition 11: Fill Material: The Permittee shall use only clean fill material for this project. The fill material shall be free from items such as trash, debris, automotive parts, asphalt, construction materials, concrete block with exposed reinforcement bars, and soils contaminated with any toxic substance in toxic amounts, in accordance with Section 307 of the Clean Water Act.
Further Information:
1. Congressional Authorities: You have been authorized to undertake the activity described above pursuant to:
( ) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403)
(X) Section 404 of the Clean Water Act (33 U.S.C. 1344)
( ) Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972 (33 U.S.C. 1413)
( ) Section 14 of the Rivers and Harbors Act of 1899 (33 U.S.C. 408)
2. Limits of this authorization.
a. This permit does not obviate the need to obtain other Federal, State, or local authorizations required by law.
b. This permit does not grant any property rights or exclusive privileges.
c. This permit does not authorize any injury to the property or rights of others.
d. This permit does not authorize interference with any existing or proposed Federal projects.
3. Limits of Federal Liability. In issuing this permit, the Federal Government does not assume any liability for the following:
a. Damages to the permitted project or uses thereof as a result of other permitted or unpermitted activities or from natural causes.
b. Damages to the permitted project or uses thereof as a result of current or future activities undertaken by or on behalf of the United States in the public interest.
c. Damages to persons, property, or to other permitted or unpermitted activities or structures caused by the activity authorized by this permit.
d. Design or construction deficiencies associated with the permitted work.
e. Damage claims associated with any future modification, suspension, or revocation of this permit.
4. Reliance on Applicant's Data: The determination of this office that issuance of this permit is not contrary to the public interest was made in reliance on the information you provided.
5. Reevaluation of Permit Decision: This office may reevaluate its decision on this permit at any time the circumstances warrant. Circumstances that could require a reevaluation include, but are not limited to, the following:
a. You fail to comply with the terms and conditions of this permit.
b. The information provided by you in support of your permit application proves to have been false, incomplete, or inaccurate (see 4 above).
c. Significant new information surfaces which this office did not consider in reaching the original public interest decision.
Such a reevaluation may result in a determination that it is appropriate to use the suspension, modification, and revocation procedures contained in 33 CFR 325.7 or enforcement procedures such as those contained in 33 CFR 326.4 and 326.5. The referenced enforcement procedures provide for the issuance of an administrative order requiring you comply with the terms and conditions of your permit and for the initiation of legal action where appropriate. You will be required to pay for any corrective measures ordered by this office, and if you fail to comply with such directive, this office may in certain situations (such as those specified in 33 CFR 209.170) accomplish the corrective measures by contract or otherwise and bill you for the cost.
6. Extensions: General Condition 1 establishes a time limit for the completion of the activity authorized by this permit. Unless there are circumstances requiring either a prompt completion of the authorized activity or a reevaluation of the public interest decision, the Corps will normally give favorable consideration to a request for an extension of this time limit.
Your signature below, as permittee, indicates that you accept and agree to comply with the terms and conditions of this permit.
(PERMITTEE) (DATE)
(PERMITTEE NAME-PRINTED)
This permit becomes effective when the Federal official, designated to act for the Secretary of the Army, has signed below.
________________________ Date:
Brandon L. Bowman Colonel, U.S. Army District Commander
12/10/25
Lynn Spivey
December 19, 2025
When the structures or work authorized by this permit are still in existence at the time the property is transferred, the terms and conditions of this permit will continue to be binding on the new owner(s) of the property. To validate the transfer of this permit and the associated liabilities associated with compliance with its terms and conditions, have the transferee sign and date below.
(TRANSFEREE-SIGNATURE) (DATE)
(NAME-PRINTED)
(ADDRESS)
(CITY, STATE, AND ZIP CODE)
Attachments to Department of the Army Permit Number SAJ-2024-04226
1. PERMIT DRAWINGS: 44 pages, dated June 2023
2. WATER QUALITY CERTIFICATION: Specific Conditions of the water quality permit/certification in accordance with General Condition number 5 on page 2 of this DA permit. 21 pages.
3. COMMENCEMENT NOTIFICATION FORM: 1 page
4. NOTICE OF DEPARTMENT OF THE ARMY AUTHORIZATION FORM: 3 pages
5. AS-BUILT CERTIFICATION FORM: 2 pages
6. STANDARD PROTECTION MEASURES FOR THE EASTERN INDIGO SNAKE:
5 pages
7. SELF-CERTIFICATION FORM: 1 page
8. NOTICE OF ADMINISTRATIVE APPEAL OPTIONS AND PROCESS AND
REQUEST FOR APPEAL FORM: 3 pages
9. PERMIT TRANSFER REQUEST FORM: 1 page