Updated Attachment 2 - SOW and Complete Specs.pdf
PDF 2 MB Posted
- Attached to
- CSC-20019; DSCC BLDG 27 Boiler Conversion Federal contract opportunity
- Solicitation number
- SP4702-21-R-0018
- Issued by
- Defense Logistics Agency
About this file
This federal solicitation seeks proposals for a boiler conversion project at a Defense Logistics Agency facility in Columbus, Ohio. The selected contractor will remove an existing steam boiler system from Building 27 and install a new hot water boiler system, completing all demolition, repair, and construction work in accordance with provided specifications and drawings. Offerors must attend a mandatory site visit on June 30, 2021 and submit any questions by July 6, 2021. Proposals are due by August 15, 2021 and must include all documentation as specified in the performance work statement, contract clauses, and proposal preparation instructions. The contract will be a firm fixed-price award made to the responsible offeror submitting the lowest-priced technically acceptable proposal, with work to be completed within 540 calendar days of notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_SP470221R00180001.pdf | ||
| FinalBldg27ACMUpdate.pdf | ||
| Updated Attachment 10 - Bid Form.pdf | ||
| Attachment 12 - Drawings 4-582.pdf | ||
| RFIs for SP4702-21-R-0018.pdf | ||
| Final Bldg 27 ACM Survey.pdf | ||
| Updated Solicitation SP4702-21-R-0018.pdf | ||
| Attachment 4 - CAC Procedures.pdf | ||
| Attachment 7 - DSCC Excavation Permit.pdf | ||
| Attachment 2 - SOW and Complete Specs.pdf | ||
| Attachment 6 - ENG Form 93.pdf | ||
| Attachment 8 - ENG Form 4025-R.pdf | ||
| Attachment 9 - Contractor Access Badge Request Form.xlsx | XLSX spreadsheet | |
| Attachment 11 - Submittal Register.xlsx | XLSX spreadsheet | |
| Solicitation SP4702-21-R-0018.pdf | ||
| Attachment 1 - Clauses and Evaluation Criteria.pdf | ||
| Attachment 3 - Drawing Package.pdf | ||
| Attachment 5 - Wage Rate Determination OH20210078.pdf | ||
| Attachment 10 - Bid Form.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENT SAFETY REQUIREMENTS
01 35 31 SAFETY SECURITY AND FIRE PROVISIONS
01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 46 00.00 06 HVAC COMMISSIONING
01 57 19 01 62 35
TEMPORARY ENVIRONMENTAL CONTROLS
RECYCLED RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 00.10 REMOVAL AND DISPOSAL OF ASBESTOS
DIVISION 03
- CONCRETE
03 01 30.71 CONCRETE REHABILITATION
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 FIRESTOPPING
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02
23 11 20 23 23 00 23 30 00
BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
CONTROL SYSTEMS
FACILITY GAS PIPING
REFRIGERANT PIPING
HVAC AIR DISTRIBUTION
BUILDING
23 52 00 23 81 00 23 81 29
HEATING BOILERS
DECENTRALIZED UNITARY HVAC EQUIPMENT
VARIABLE REFRIGERANT FLOW HVAC SYSTEMS
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 29 23 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS
-- End of Project Table of Contents --
Boiler Conversions, Building 27 CSC20019
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Utility Outage Requests;G Utility Connection Requests; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes The work includes demolition of existing steam heating system (including steam and condensate piping, steam unit heaters, and steam heating coils in air handling units) and the installation of a new hot water heating system (including boilers, pumps, hot water unit heaters, hot water heating coils in air handling units, and hot water piping) and incidental related work.
1.2.2 Location
The work is located at the Defense Supply Center Columbus, Building 9, Building 27 and Building 61.
1.3 CONTRACT DRAWINGS
The following drawings accompany this specification and are a part thereof.
G-001 COVER SHEET
G-002 HVAC GENERAL NOTES AND LEGEND
G-003 EXISTING CONDITIONS
A-401 FLOOR RESURFACING PLAN - BOILER ROOM
MD-101 HVAC DEMOLITION PLAN - SECTIONS 7-10
MD-102 HVAC DEMOLITION PLAN - SECTIONS 11-13
MD-401 HVAC DEMOLITION PLAN - BOILER ROOM
M-101 HVAC NEW WORK PLAN - SECTIONS 7-10
M-102 HVAC NEW WORK PLAN - SECTIONS 11-13
M-401 HVAC NEW WORK PLAN - BOILER ROOM
M-501 HVAC DETAILS
M-502 HVAC DETAILS
M-601 HVAC SCHEDULES
M-701 BOILER CONTROLS
M-702 HEATER CONTROLS
M-703 CONTROLS NETWORK SCHEMATIC
E-101 POWER PLAN - SECTIONS 7-10
Section 01 11 00 Page 2
E-102 POWER PLAN - SECTIONS 11-13
E-401 POWER PLAN - BOILER ROOM
G-001 COVER SHEET
MD-101 BUILDING 9 SECTION 1 HVAC DEMOLITION PLAN
MD-102 BUILDING 27 SECTION 13 HVAC DEMOLTION PLAN
MD-103 BUILDING 61 HVAC DEMOLITION PLAN
MH-101 BUILDING 9 SECTION 1 HVAC NEW WORK PLAN
MH-101 BUILDING 9 SECTION 1 HVAC NEW WORK PLAN
MH-102 BUILDING 27 SECTION 11 HVAC NEW WORK PLAN
MH-103 BUILDING 27 SECTION 13 HVAC NEW WORK PLAN
MH-104 BUILDING 61 HVAC NEW WORK PLAN
MH-501 HVAC DETAILS
MH-601 HVAC SCHEDULES
EP-101 BUILDING 9 SECTION 1 HVAC POWER PLAN
EP-102 BUILDING 27 SECTION 11 HVAC POWER PLAN
EP-103 BUILDING 27 SECTION 13 HVAC POWER PLAN
EP-104 BUILDING 61 HVAC POWER PLAN
1.4 WORK RESCHEDULING
Normal duty hours for work are from 0700 to 1630, Monday through Friday.
Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.
1.5 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.6 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.7 ON-SITE PERMITS
1.7.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed
Section 01 11 00 Page 3 outside the regular work hours.
Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 17 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.7.2 Borrow, Excavation, Welding, and Burning Permits
ACTIVITY SUBMISSION DATE
Burning Permits 14 calendar days prior to work and every 30 days for renewal
Post permits at a conspicuous location in the construction area.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section --
SECTION 01 20 00.00 20 Page 1
SECTION TABLE OF CONTENTS
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
08/16
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 SCHEDULE OF VALUES
1.3.1 Data Required
1.3.2 Schedule Instructions
1.4 CONTRACT MODIFICATIONS
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
1.5.2 Submission of Invoices
1.5.3 Final Invoice
1.5.4 NO Asbestos - Containing Material (ACM) Certification
1.6 PAYMENTS TO THE CONTRACTOR
1.6.1 Obligation of Government Payments
1.6.2 Payment for Onsite Materials
-- End of Section Table of Contents --
SECTION 01 20 00.00 20 Page 2
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
03/20
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
Schedule of Values; G
SD-07 Certificates
Release of Claims; G
No Asbestos Containing Material (ACM); G
1.3 SCHEDULE OF VALUES
1.3.1 Data Required
Within 14 calendar days of notice to proceed, prepare and deliver to the Contracting Officer a Schedule of Values (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Schedule of Values has been submitted to and accepted by the Contracting Officer.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8.
SECTION 01 20 00.00 20 Page 3
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on ENG Form 93, showing in summary form, the basis for arriving at the amount of the invoice. ENG Form 93 shall include certification by Quality Control (QC) Manager as required by the contract. This form may be provided upon request or is available at the USACE Publications website:
http://www.publications.usace.army.mil/Portals/76/Publications/Eng ineerForms/Eng_Form_93_2014Mar.pdf
b. The Payment Estimate for Contract Performance showing in detail:
the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract
c. Updated Project Schedule and reports required by the contract.
d. Other supporting documents as requested.
e. Updated copy of submittal register.
f. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
g. Materials on Site.
h. Monthly Work-hour report.
i. Solid Waste Disposal Report.
1.5.2 Submission of Invoices
If DFARS Clause 252.232-7003 is included in the contract, the documents listed in paragraph "CONTENT OF INVOICE" shall be provided in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it shall be provided as instructed by the Contracting Officer.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's
Final Release must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release in WAWF.
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_93_2014Mar.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_93_2014Mar.pdf
SECTION 01 20 00.00 20 Page 4
c. Final invoices not accompanied by the Contractor's Final Release will be considered incomplete and will be returned to the Contractor.
1.5.4 NO Asbestos - Containing Material (ACM) Certification
Before final payment to the contractor, the contractor's project engineer/manager will sign and submit to the government, on the contracting firm's letterhead, a dated copy of the following statement:
I hereby certify that to the best of my knowledge no asbestos-containing material (ACM) was used as a building material during this project. Furthermore, I certify that no product containing mineral fibers was used as a building material unless I either:
- Have on file and have submitted to the Government the manufacturer's certification that the material does not contain asbestos, OR
- Have supplied to the Government documentation to show that the material has been microscopically examined by an AIHA- or NVLAP-certified laboratory and the lab has determine that it that it does not contain asbestos.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current.
1.6.2 Payment for Onsite Materials
Progress payments may be made to the contractor for materials delivered on the site under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
SECTION 01 20 00.00 20 Page 5
b. Materials delivered on the site but not installed, including completed preparatory work, shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Values requirement of this contract.
Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
Not Used
Construction Certification Notice to Contractors
For Compliance with 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014).
Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
“I hereby certify, to the best of my knowledge and belief, that-
1. The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
2. All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
3. This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
4. This certification is not to be construed as final acceptance of a subcontractor’s performance.”
(Name)/(Title)
(Date)
(Contract Number)
SECTION 01 32 16.00 20 Page 1
SECTION TABLE OF CONTENTS DIVISION
01 - GENERAL REQUIREMENTS
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
05/19
1.1 SUBMITTALS
1.2 ACCEPTANCE
1.3 SCHEDULE FORMAT
1.3.1 Bar Chart Schedule
1.3.2 Schedule Submittals and Procedures
1.4 SCHEDULE MONTHLY UPDATES
1.5 3-WEEK LOOK AHEAD SCHEDULE
1.6 CORRESPONDENCE AND TEST REPORTS:
1.7 ADDITIONAL SCHEDULING REQUIREMENTS
SECTION 01 32 16.00 20 Page 2
SECTION 01 32 16.00 20
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
05/19
1.1 SUBMITTALS
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
Construction Schedule; G
SD-07 Certificates
Monthly Updates
1.2 ACCEPTANCE
Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of a Bar Chart Schedule in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.
The acceptance of a Baseline Construction Schedule is a condition precedent to:
a. The Contractor starting work on the demolition or construction stage(s) of the contract.
b. Processing Contractor's invoice(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 SCHEDULE FORMAT
1.3.1 Bar Chart Schedule
The Bar Chart must, as a minimum, show work activities, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet program.
1.3.2 Schedule Submittals and Procedures
Submit Bar Chart Schedules and updates in hard copy and on electronic media
SECTION 01 32 16.00 20 Page 3 that is acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.
1.4 SCHEDULE MONTHLY UPDATES
Update the Construction Schedule at monthly intervals or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.
a. Narrative Report: Provide with schedule updates. Identify and justify;
(1) Progress made in each area of the project
(2) Critical Path
(3) Date/time constraint(s), other than those required by the contract
(4) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, and critical path
(5) Status of Contract Completion Date and interim milestones;
(6) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);
(7) Description of current and future schedule problem areas.
Each entry in the narrative report must cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.
1.5 3-WEEK LOOK AHEAD SCHEDULE
Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.
Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Deliver three hard copies and one electronic file of the 3-Week Look Ahead Schedule to the Contracting Officer no later than 8 a.m. each Monday, and review during the weekly CQC Coordination or Production Meeting.
1.6 CORRESPONDENCE AND TEST REPORTS:
All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) must reference Schedule Activities that are being addressed. All test reports (e.g., concrete, soil compaction, weld, pressure) must reference Schedule Activities that are being addressed.
SECTION 01 32 16.00 20 Page 4
1.7 ADDITIONAL SCHEDULING REQUIREMENTS
Any references to additional scheduling requirements, including systems to be inspected, tested and commissioned, that are located throughout the remainder of the Contract Documents, are subject to all requirements of this section.
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
02/19
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (GA)
1.4.2 For Information Only
1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1 Submittals Required from the Contractor
1.5.1.1 O&M Data
1.6 PREPARATION
1.6.1 Transmittal Form
1.6.2 Identifying Submittals
1.6.3 Format for SD-02 Shop Drawings
1.6.4 Format of SD-03 Product Data and SD-08 Manufacturer's
Instructions
1.6.5 Format of SD-04 Samples
1.6.6 Format of SD-05 Design Data and SD-07 Certificates
1.6.7 Format of SD-06 Test Reports and SD-09 Manufacturer's Field
Reports
1.6.8 Format of SD-10 Operation and Maintenance Data (O&M)
1.6.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout
Submittals
1.6.10 Source Drawings for Shop Drawings
1.6.10.1 Terms and Conditions
1.6.11 Electronic File Format
1.7 QUANTITY OF SUBMITTALS
1.7.1 Number of Copies of SD-02 Shop Drawings
1.7.2 Number of Copies of SD-03 Product Data and SD-08
Manufacturer's Instructions
1.7.3 Number of Samples SD-04 Samples
1.7.4 Number of Copies SD-05 Design Data and SD-07 Certificates
1.7.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's
Field Reports
1.7.6 Number of Copies of SD-10 Operation and Maintenance Data
1.7.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11
Closeout Submittals
1.8 INFORMATION ONLY SUBMITTALS
1.9 VARIATIONS
1.9.1 Considering Variations
1.9.2 Proposing Variations
1.9.3 Warranting that Variations are Compatible
1.9.4 Review Schedule is Modified
1.10 SUBMITTAL REGISTER AND DATABASE
1.10.1 Use of Submittal Register
SECTION 01 33 00 Page 2
1.10.2 Contractor Use of Submittal Register
1.10.3 Action Codes
1.10.3.1 Government Review Action Codes
1.10.3.2 Contractor Action Codes
1.10.4 Copies Delivered to the Government
1.11 SCHEDULING
1.11.1 Constraints
1.12 GOVERNMENT APPROVING AUTHORITY
1.12.1 Review Notations
1.13 DISAPPROVED SUBMITTALS
1.14 APPROVED SUBMITTALS
1.15 APPROVED SAMPLES
1.16 WITHHOLDING OF PAYMENT
1.17 PROGRESS SCHEDULE
1.17.1 Bar Chart
1.18 STATUS REPORT ON MATERIALS ORDERS
SECTION 01 33 00 Page 3
SECTION 01 33 00
SUBMITTAL PROCEDURES
02/16
1.1 SUMMARY
The engineering representative may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited
to) catalog cuts, diagrams, operating charts or curves; test reports;
test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
A submittal register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A
- Submittal Register".
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
Submittals which are required prior to start of construction (work), commencing work on site or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
Surety bonds
SECTION 01 33 00 Page 4
List of proposed Subcontractors
List of proposed products
Construction progress schedule
Submittal register
Schedule of values
Health and safety plan
Work plan Contractor Quality Control(CQC) plan Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
Design submittals, design substantiation submittals and extensions of design submittals.
SD-06 Test Reports
SECTION 01 33 00 Page 5
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to
SECTION 01 33 00 Page 6 the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
submittals not having a "G" designation are for Contractor QC approval.
Submit the following in accordance with this section.
Submittal Register; G
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved (GA)
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."
SECTION 01 33 00 Page 7
1.4.2 For Information Only (FIO)
Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring Designer of Record or Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1 Submittals Required from the Contractor
As soon as practicable after award of contract, and before procurement of fabrication, forward to the engineering and the contracting offices submittals required in the technical sections of this specification, including shop drawings, product data and samples.
The engineering representative will review and approve for the Contracting Officer those submittals reserved for Contracting Officer approval to verify submittals comply with the contract requirements.
1.5.1.1 O&M Data
The Facility Engineering Representative will review and approve for the Contracting Officer O&M Data to verify the submittals comply with the contract requirements; submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.
1.6 PREPARATION
1.6.1 Transmittal Form
Use the transmittal form ENG Form 4025-R for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. This form may be provided upon request or is available at the USACE Publications website:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerF orms/Eng_Form_4025-R.pdf
Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.6.2 Identifying Submittals
When submittals are provided by a Subcontractor, the Prime Contractor is to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location.
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_4025-R.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_4025-R.pdf
SECTION 01 33 00 Page 8
b. Construction contract number.
c. Date of the drawings and revisions.
d. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other subcontractor associated with the submittal.
e. Section number of the specification section by which submittal is required.
f. Submittal description (SD) number of each component of submittal.
g. When a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.
h. Product identification and location in project.
1.6.3 Format for SD-02 Shop Drawings
Shop drawings are not to be less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless other form is required.
Drawings are to be suitable for reproduction and be of a quality to produce clear, distinct lines and letters with dark lines on a white background.
Present 8 1/2 by 11 inches sized shop drawings as part of the bound volume for submittals required by section. Present larger drawings in sets.
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location adjacent to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings.
Identify materials and products for work shown. Include the nameplate data, size and capacity on drawings. Also include applicable federal, military, industry and technical society publication references.
Submit drawings PDF format.
1.6.4 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions
Present product data submittals for each section as a complete, bound volume. Include table of contents, listing page and catalog item numbers for product data.
Indicate, by prominent notation, each product which is being submitted;
indicate specification section number and paragraph number to which it
SECTION 01 33 00 Page 9 pertains. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist.
Identify this material as developed specifically for project, with information and format as required for submission of SD-07 Certificates.
Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry and technical society publication references. Should manufacturer's data require supplemental information for clarification, submit as specified for SD-07 Certificates.
Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the engineering representative. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal and marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of construction effort.
Submit manufacturer's instructions prior to installation.
1.6.5 Format of SD-04 Samples
Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as specified:
a. Sample of Equipment or Device: Full size.
b. Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.
c. Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
e. Sample of Non-Solid Materials: Pint. Examples of non-solid materials are sand and paint.
f. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
SECTION 01 33 00 Page 10
g. Sample Panel: 4 by 4 feet.
h. Sample Installation: 100 square feet.
Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.
Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at time of use.
Recording of Sample Installation: Note and preserve the notation of area constituting sample installation but remove notation at final clean up of project.
When color, texture or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
1.6.6 Format of SD-05 Design Data and SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inches paper.
Provide a bound volume for submittals containing numerous pages.
1.6.7 Format of SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Provide reports on 8 1/2 by 11 inches paper in a complete bound volume.
Indicate by prominent notation, each report in the submittal. Indicate specification number and paragraph number to which it pertains.
1.6.8 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.
1.6.9 Format of SD-01 Preconstruction Submittals and SD-11
Closeout Submittals
When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply Contractor's approval stamp to document, but to a separate sheet accompanying document.
1.6.10 Source Drawings for Shop Drawings
The entire set of Source Drawing files (DWG) will not be provided to the Contractor. Only those requested by the Contractor to prepare shop drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award.
1.6.10.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for
SECTION 01 33 00 Page 11 the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic Source Drawing files are not construction documents.
Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.6.11 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the engineering representative. Electronic files must be of sufficient quality that all information is legible. Electronic format shall be in PDF, unless otherwise specified or directed by the engineering representative.
Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic submittal documents fewer than 10MB to an email address as directed by the engineering representative. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the ARL SAFE Web Application located at the following website: https://safe.arl.army.mil/.
Provide hard copies of submittals when requested by the engineering representative. Up to six additional hard copies of any submittal may be requested at the discretion of the engineering representative, at no additional cost to the Government.
1.7 QUANTITY OF SUBMITTALS
1.7.1 Number of Copies of SD-02 Shop Drawings
SECTION 01 33 00 Page 12
Submit two copies of submittals of shop drawings requiring review and approval only by QC organization.
1.7.2 Number of Copies of SD-03 Product Data and SD-08
Manufacturer's Instructions
Submit in compliance with quantity requirements specified for shop drawings.
1.7.3 Number of Samples SD-04 Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.7.4 Number of Copies SD-05 Design Data and SD-07 Certificates
Submit in compliance with quantity requirements specified for shop drawings.
1.7.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.
1.7.6 Number of Copies of SD-10 Operation and Maintenance Data
Submit two copies of O&M Data to the engineering representative for review and approval.
1.7.7 Number of Copies of SD-01 Preconstruction Submittals and SD- 11 Closeout Submittals
Unless otherwise specified, submit two sets of administrative submittals.
1.8 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical
SECTION 01 33 00 Page 13 specifications so prescribe.
1.9 VARIATIONS
Variations from contract requirements require Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.9.1 Considering Variations
Discussion with Contracting Officer and engineering representative prior to submission, after consulting with the engineering representative, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.9.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the engineering representative’s written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.9.3 Warranting that Variations are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.9.4 Review Schedule is Modified
An additional review period will be allowed for consideration by the Government of submittals with variations.
1.10 SUBMITTAL REGISTER AND DATABASE
Prepare and maintain submittal register, as the work progresses. Use electronic submittal register. Upon request the Government may provide the initial submittal register in electronic format. This list may not be all inclusive and additional submittals may be required. The following fields will be used:
Column…
This is the start of the file's text. The full file is on GovTribe.