Questions_and_Answers_-_6-14-16.pdf
PDF 7 KB Posted
- Attached to
- EDGAR Redesign (ERD) Requirements Gathering
- Solicitation number
- SECHQ1-16-R-0017
- Issued by
-
Securities and Exchange Commission
About this file
Questions and Answers - 6/14/16
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Document Reference
Section Reference Paragraph Pages Question Answer
Solicitation L.3.1 1 59 Does the Go/No-Go requirements for each factor need to be met by a single project or can it span multiple projects? Does the vendor need to pass both factors to be considered for this solicitation?
Offerors shall only submit one project for each Go/No-Go factor. Multiple projects cannot be combined to meet the criteria of a factor.
Solicitation L.3.1 1 59 Does the vendor need to pass both factors to be considered for this solicitation?
Yes, Offerors must pass both Go/No-Go factors to partcipate in the RFP response and submit the Technical and Price Proposals.
Solicitation M.3.1 1 66 For a given factor, is a 'Yes' required for all requirements to be considered a 'pass'?
Yes, Offerors must meet all of the Go/No-Go criteria in order to receive a "Pass" rating.