S02 - ATTACHMENT 10 - 556-21-701 EHRM West Const SOW 20 DEC22.pdf

PDF 187 KB Posted

Attached to
EHRM Infrastructure Upgrades West Campus – North Chicago - Construction Federal contract opportunity
Solicitation number
36C77623B0019
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This statement of work outlines the requirements for a construction project to upgrade infrastructure at the Edward Hines, Jr. VA Hospital West Campus located in North Chicago, Illinois. The scope of work includes renovations to telecommunications cabling, electrical systems, physical security and access control systems, and HVAC upgrades across 48 buildings totaling 1.8 million square feet. The contractor will be responsible for all labor, materials, quality assurance and safety compliance to deliver a complete and functional project. The performance period is 244 calendar days. The solicitation was issued by the Department of Veterans Affairs Technology Acquisition Center Austin as solicitation number 36C77623B0019.

View the file

Other files for this federal contract opportunity

Other files attached to EHRM Infrastructure Upgrades West Campus – North Chicago - Construction, newest first.
File Type Posted
36C77623B0019 0010 - EHRM N Chicago West - Conference Line_Wage Rates_52.204-27.pdf PDF
Updated Wage Rates - Lake County - 06.30.23.pdf PDF
36C77623B0019 0009 - Note and Site Visit 2 Sign In Sheet.pdf PDF
Site Visit 2 Sign-In Sheet - 556-21-701 EHRM West Campus.pdf PDF
S02 - 36C77623B0019 0008 - Extension and Additional Site Visit.pdf PDF
Revised Drawing Sheet GS007 - Item 133.pdf PDF
556-21-701 EHRM West PreBid RFIs 20JUN23.pdf PDF
36C77623B0019 0007 - EHRM North Chicago (West) - Revised RFI Responses.pdf PDF
36C77623B0019 0006 - EHRM North Chicago (West) - Technical Questions.pdf PDF
36C77623B0019 0005 - EHRM North Chicago (West) - Extension 6.26.23.pdf PDF
36C77623B0019 0004 - EHRM North Chicago (West) - Extension 3.16.23.pdf PDF
36C77623B0019 0003 - EHRM North Chicago (West) - Extension.pdf PDF
36C77623B0019 0003 - Updated Wage Rates - Lake County - 05.12.23.pdf PDF
36C77623B0019 0002 - Site Visit Sign-In Sheet - North Chicago (West).pdf PDF
West Campus Site Visit sign in sheet May 15 2023.pdf PDF
27 05 33 Raceways and Boxes for Communication Systems.pdf PDF
27 52 23 Nurse call.pdf PDF
36C77623B0019 0001 - EHRM North Chicago (West) - Addendum 01.pdf PDF
Addendum 001.pdf PDF
00 01 10- Table of Contents.pdf PDF
01 35 26 Safety Requirements.pdf PDF
01 35 33 Infection Control Requirements.pdf PDF
26 05 33 Raceway and Boxes for Electrical Systems.pdf PDF
27 51 16 Public Address and Mass Notification.pdf PDF
01 45 29 Testing Laboratory Services.pdf PDF
01 00 00 General Requirements.pdf PDF
01 33 23 Shop Drawings Product Data and Samples.pdf PDF
01 91 00 General Commissioning Requirements.pdf PDF
S02 - SOLICITATION - 36C77623B0019_1 North Chicago EHRM (West Campus).pdf PDF
S02 - ATTACHMENT 1 - 556-21-701 Bid Specifications - Final.pdf PDF
S02 - ATTACHMENT 2 - Chicago EHRM - Design Narratives.pdf PDF
S02 - ATTACHMENT 6 - Safety Requirements.pdf PDF
S02 - ATTACHMENT 11 - Combined Drawings 1 of 6 - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 14 - Combined Drawings 4 of 6 - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 17 - Brand Name Justification - Redacted.pdf PDF
S02 - ATTACHMENT 5 - 01 35 33 Infection Control Requirements FHCC 15NOV22.pdf PDF
S02 - ATTACHMENT 8 - Mechanical Calculations - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 16 - Combined Drawings 6 of 6 - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 22 - Illinois Tax Memo - 1.26.2023.pdf PDF
S02 - ATTACHMENT 3 - EHRM North Chicago-100 Cost Narrative.pdf PDF
S02 - ATTACHMENT 18 - Limitations on Subcontracting - Jan 2023.pdf PDF
S02 - ATTACHMENT 19 - Contractor Safety - Environmental Form.pdf PDF
S02 - ATTACHMENT 20 - Wage Rates - Lake County - 01.20.23.pdf PDF
S02 - ATTACHMENT 4 - Environmental Comb - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 7 - Mechanical Equipment - EHRM Upgrade Chicago.pdf PDF
S02 - ATTACHMENT 9 - ICRA Form - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 12 - Combined Drawings 2 of 6 - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 13 - Combined Drawings 3 of 6 - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 15 - Combined Drawings 5 of 6 - EHRM Upgrades Chicago.pdf PDF
S02 - ATTACHMENT 21 - Site Visit Instructions.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EHRM INFRASTRUCTURE UPGADES, WEST CAMPUS (revised) 12-19-22

CONSTRUCTION STATEMENT OF WORK

Project Name: EHRM Infrastructure Upgrades, West Campus – North Chicago, IL - Tier 1 Project Number: 556-21-701 Date: December 19, 2022 Location:

Captain James A. Lovell FHCC

3001 Green Bay Rd, North Chicago, IL 60064

Date: December 19,2022 Part 1: Project Scope of Work Overview:

FHCC West Campus is comprised of 94 acres, 48 Buildings that range in size (single to 5 levels) and construction age from 1926 until 2021 totaling 1.8 million square feet, but with significant clinical facilities of modern construction.

Primary project work locations include tele-data rooms throughout Buildings 1, 3, 4, 5, 6, 7, 9, 11, 32, 36, 37, 46, 48, 66, 92, 131, 132, 133, 133EF, 133CA, 134, 135, 138, 140, 187, 188, 195, 201, 202, 205, 206, Green Bay Road Guard Shack, Lewis Guard Shack, Tramway, and site.

The scope of this project includes but is not limited to the following infrastructure improvements:

Contractor shall provide all tools, materials, labor, quality assurance, and supervision for renovations resulting in a complete, compliant, and fully-functional project, including proactive safety and infection control compliance, selective demolition, installation, testing, and certification of significant volume of Cat6a and fiberoptic telecom cabling throughout all buildings as well as between each, normal and emergency electrical distribution system improvements (i.e. power distribution panels, lighting, controls, receptacles, grounding-bonding, UPS, etc.), physical security and access control system upgrades, HVAC system improvements (upgrades, new systems, etc.), finishes including walls, floors, and ceilings of new or altered rooms, and more as described in the design and specification documents, throughout all buildings.

This SOW presumes the contractor will need access to the FHCC LAN and some VA Sensitive Information to execute the contract. The awarded Contractor will adhere to all codes, standards, guidelines, and design requirements found in the VA Technical Information Library (TIL)

Part 2: Period of Performance:

1. Complete all work including submittals, reviews, quality assurance, and closeout within two hundred forty-four (244) calendars days from PCAC issuance of Award. (PCAC does not issue Notice to Proceed) A. Failure to complete all work, including submission of compliant closeout documents, before the end of the Period of Performance can result in adverse contract action.

B. Accommodate the Period of Performance by including accelerated material and or equipment delivery costs as well as adjusting crew sizes.

2. VA is open to opportunities to accelerate the Period of Performance of this construction project.

Part 3: Detailed Project Requirements:

1. Project Objectives:

A. At no time during this project cause any outage of telecom for any user.

B. Construct new telecom infrastructure to meet or exceed VA requirements associated with the EHRM program prior to removal of outdated infrastructure which will no longer be needed as a result of the upgraded systems.

C. Complete the work without causing operational issues to the hospital or its administrative support network, or safety incident involving any contract or VA staff, or patients and general public.

D. Meet or exceed all Code, technical, and programmatic requirements adopted, established, revised, and or published by VA.

E. Expedite the delivery of a highly functional, complete, compliant, and safe workspace for the user service.

2. List of A/E-generated documents to be included in this Contract:

A. See: 00 01 10 Table of Contents and the entire Project Manual B. See: 00 01 15 List of Drawing Sheets and the entire volume of drawings

3. FHCC-specific Specifications not included in the A/E-generated documents, but required to be part of this contract include:

A. 01 35 26 Safety Requirements B. 01 35 33 Infection Control Requirements C. 01 40 00 Quality Requirements

D. 01 41 00 Regulatory Requirements E. 01 42 16 Definitions and Abbreviations F. 01 57 19 Temp Environmental Controls G. 01 74 19 Construction Waste Management

4. Pre-Bid Conference:

A. VA shall schedule one pre-bid conference required to be attended by prospective bidders to observe current conditions within the work area(s).

B. The A/E, USACE, CxA, and other supporting organizations will provide limited support to

VA for the pre-bid event.

C. All prospective contractors shall follow the RFI process described in the Solicitation.

D. Prospective bidders shall not attempt to contact the A/E or VA facilities engineering staff during the solicitation and bidding period. The AE and VA facilities engineering staff are instructed to ignore all such inquiries and report them to the VA Contracting Officer. All inquiries regarding this project shall be presented as complete and coherent Requests for Information (RFI) specifically citing design or specification sections, pages, paragraphs, notes, details, etc. to enable responses to RFI’s. Follow the instructions provided by the Contracting Officer within the Solicitation regarding submission of RFI’s.

VA will post responses developed to enable all prospective bidders to receive the same information at the same time. RFI’s lacking required information, substantive technical detail, or aren’t actually questions will not be responded to. This will be true for RFI’s regarding subjects clearly included in the documents.

5. Mobilization on Site:

A. The contractor shall not mobilize on site until all required Kick-Off Meeting and

Documentation deliverables are submitted, reviewed, and accepted by the VA COR. Kick-Off Meeting Documentation is described at Part 4.

B. Approval to mobilize shall be in writing by the Contracting Officer in consultation with the COR and Facility Safety Manager.

C. Mobilization will not begin unless and until all administrative, initial phase, and long-lead material/systems submittals have been verified for compliance by the contractor PM as required and described at 01 33 23 Shop Drawings, Product Data, and Samples, the VA Contracting Officer’s Representative (COR), and also the A/E (generally Division 02+). Significant time for this essential requirement is already accounted for in the Period of Performance.

D. Post and maintain at each work area all current emergency contact information, VA Infection Control Risk Assessment (ICRA)/Permit, Interim Life Safety Measures (ILSM), and other information required by VA, on the wall at all entry points to the work area.

E. For facility access and badging, submission of personnel data required for background checks well in advance of need is imperative (weeks, not days).

4. Performance of the Work:

A. Erect and maintain a dust-tight containment around the work area which complies with applicable Code associated with UL-Rated wall assemblies and maintenance of egress paths.

B. Containment shall enable access to the work, without obstructing access to adjacent suites or rooms. Establish HEPA air purification. Review and follow specification 01 35 33 Infection Control Requirements as applicable to each work location. Follow each Project Risk Assessment (PRA) & ICRA plan generated and issued by VA. Remove only upon completion and approval of the VA COR.

C. After establishing and gaining approval of the temporary modular hard plastic dust-tight construction dust control barrier system, including lockable door. Where this is the sole containment, include differential pressure monitoring for the work area, with monitor located adjacent to the temporary entry door.

D. Where fire or smoke-rated wall assemblies are planned for alteration – even if temporarily, provide a dust-tight 1-hour rated temporary construction wall with locking door to isolate the area of work, finished with one coat of paint on the outside were indicated.

E. The 1-hour temporary wall shall include differential pressure monitoring for the work area, with monitor located adjacent to the temporary entry door.

F. The 1-hour temporary wall and differential pressure monitoring must be complete and approved prior to removal of the (outer) temporary modular wall barrier, and commencement of demolition within the space.

G. Prior to removal of a temporary fire or smoke-rated walls, completely restore rated wall assemblies required of the work, and then re-erect the temporary modular hard plastic, dust-tight, barrier system.

H. In no case shall any containment be removed unless and until the work area, including the inside of the ventilation system(s), has been thoroughly cleaned and approved for progress toward activation.

I. Immediately prior to turnover, remove from the ventilation system(s) all air filters used during construction, and supply and install new specified filters. Supply case quantities of each filter to VA with the system.

5. Perform selective demolition and construction as described in the specifications and drawings.

6. Special Acceptance Criteria for the work shall include:

A. HVAC system shall not be acceptable in whole or in part unless and until Testing, Adjusting, and Balancing (TAB) is completed and accepted in accordance with the Specifications, Drawings, and the current edition ASHRAE 170 Ventilation of Health Care Facilities (and errata) requirements specific to the room/suite type and purpose.

VA reserves the right to conduct, or have conducted, verification testing, and deduct its cost from the contract if noncompliant conditions are found. The GC may also be required to replace the subcontract TAB provider due to demonstrated lack of competence.

B. The contractor shall provide EIA/TIA testing and certification of all new Cat 6e communications cable.

7. Restore all finishes damaged during the work – match existing.

8. Thoroughly clean all surfaces using HEPA-filtered vacuum cleaner and anti-bacterial wipes.

Part 4: Meetings, Submittals, and Deliverables:

1. Kick-Off Meeting and Documentation

A. The contractor’s Project Manager and Field Supervisor shall attend a Preconstruction Safety and Coordination Meeting to discuss project details.

B. Kick-Off Meeting Documentation:

1) Prepare and submit for review and acceptance a proposed baseline schedule reflecting each phase of the work beginning with Mobilization, including each critical activity, and each essential task required to optimally meet the objectives of the project. It is expected that this timeline will be shorter than that presented in the Period of Performance from Mobilization to Closeout. Upon acceptance, this will become the Baseline Schedule from which subsequent progress updates are developed and reported, and how progress payment applications are objectively reviewed.

2) To enable objective assessment of costs and progress, submit a fully-loaded time and cost schedule using Critical Path Method (versus Network Analysis) along with a corresponding Schedule of Values with harmonized category values – each totaling the contract value.

a. Develop the CPM schedule in sufficient detail to enable readers to understand all planned activities, their predecessors and successors, who is performing the work, durations, and costs. Activity durations shall not exceed two calendar weeks.

b. Indicate resource SDVOSB status.

c. Not less than one item per subcontractor at any tier. Subcontractors, by definition, are contributing work in the field to the project, and therefore must be accounted for in planning. Pass-through subcontractors are not acceptable.

d. Use of the Project Manual index of specifications is a useful guide for starting the CPM schedule and Schedule of Values in sufficient detail. For example:

Simply listing “HVAC” is unacceptable for projects including more than basic work in this category. The inclusion of specifications for an AHU, controls, ductwork, demolition of each, testing and balancing, etc. also prompt their inclusion as categories of activities and tasks in the schedule. In fact, for larger work categories, breaking down the cost by system/material and installation and testing enables partial payment for higher cost items upon delivery into the facility work area.

e. Include all expected utility system shutdowns, road closures, crane lifts, and off-hours work.

f. Preparation and processing of submittals are not work activities contributing to the compensable work in the field. Should the contractor elect to include submittal planning in their internal use schedule for their own purposes, do not show those line items in the schedule submitted to VA for consideration in the Baseline Schedule, and do not assign dollar values to them.

g. Do not include costs associated with non-work administrative activities inherent in the listed work items. Examples include mobilization, preparation of submittals, development of schedules and progress reports, general and activity-specific safety compliance, attendance of meetings, and similar administrative activities which would not occur without the line-item listed work items. 52.246-12 Inspection of Construction defines Work as “…materials, workmanship, and manufacture and fabrication of components”. Inherent in these are planning, communicating, procuring, and quality assurance and quality control, among other inputs. The Government cannot pay for what it has not inspected and accepted as compliant, or for activities which add no value to VA facilities. Front-loading proposals, bids, schedules of values, and line item costs of cost-loaded CPM schedules with all manner of non-work items puts the Contractor, the Government, and the Bonding Company at otherwise avoidable risk associated with paying out more than the value of work in place should the work stop prior to completion. Administrative and managerial activities associated with each Work line item are to be included in each line item, along with prorated overhead and profit.

3) The contractor shall prepare and submit SF-1413,s for each subcontractor to the CO, copying the COR. Provide a list of all subcontractors and suppliers, including: Company names, office address, and main point of contact name with telephone number, and SDVOSB status.

4) As required at 01 35 26 Safety Requirements: Develop and submit a Project- Specific Construction Safety and Accident Prevention Plan with project-specific procedures, processes, analysis, and details, including but not limited to:

a. Access and use the U.S. Army Corps of Engineers EM 385-1-1 Safety and

Health Requirements and its Appendix A – Minimum Basic Outline for Accident Prevention Plans for development of meaningful, effective, and compliant project safety plans.

b. Submission of generic, non-project specific safety plans will be rejected, resulting in a contractor-caused delay in commencement of the work.

c. Project-specific Activity Hazard Analysis (AHA), which forms the basis of the Construction Safety and Accident Prevention Plan highlighting identified risks such as isolation of stored energy (Lock-Out*), fall protection, or confined space access.

(*) Note that tag-out is not an acceptable form of isolation, therefore it was intentional not to use the term LOTO.

d. Do not include instruction to users of a safety plan to dial 9-1-1 as would be typical in the commercial world. The VA COR will provide direct phone numbers to the VA Police and the Great Lakes Fire Department (US Navy). 9- 1-1 only works with in-house land-line phones. Dialing 9-1-1 from a cellular device will reach the regional emergency operator center, but delay response.

e. Submit an electronic copy of the GC and all subcontractor designated competent persons OSHA 30-hour Construction Safety Training certificates or cards, as well as any other required training certifications (trade and activity dependent) with project-specific Construction Safety and Accident Prevention Plan.

f. Submit an electronic copy of all workers OSHA 30-hour Construction Safety Training certificates or cards prior to allowing entry to the site.

g. Assist the COR in completing project-specific VA Infection Control Risk Assessment (ICRA) and Interim Life Safety Measures (ILSM) documentation.

h. Do not ask VA to issue permits for regulated activities. It is the employer’s responsibility to manage their safety and health program. VA requires submission of contractor-generated permits to ensure that such activities are known to VA, and that the affected employer has properly planned its safe conduct.

C. Public Safety Compliance Requirements:

1) The following applies to all VA and Navy properties, including leased facilities, regardless of building occupancy or current use and does not differentiate between medical or administrative spaces as all are occupied by people we are collectively working to protect from harm – including contractor staff.

2) Contractors shall adhere to and ensure compliance with federal laws, regulations, and Executive Orders including TB and COVID-19 screening, vaccinations, and or testing designed to protect contractor employee and general public health and safety, as well as all associated with protection of private health information and personally identifiable information.

3) All contractor staff share a common moral responsibility to stay away from the facility when feeling ill.

4) Contractor employees who work in or travel to this facility must comply with its health and safety policies while on VA or Navy property. Contractor employees are not considered patients or visitors while at this facility for work-related purposes – even if they are a Veteran who gets care here. The same remains true for VA staff.

5) As the current pandemic evolves, so too does the science and subsequent policy response. The assigned COR is the local source for current policy.

6) Obviously, as the employer, the GC retains primary responsibility for the health and safety of its employees and consultants, and may elect to exceed any applicable law, regulation, or policy.

7) Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA and or Navy facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the following website: COVID-19 Screening Tool. Regularly check the website for updates.

8) Contractor employees shall always properly wear FDA-cleared personal protective equipment while on VA or Navy property – in addition to physical distancing.

Commonly worn cloth masks, gators, scarves, bandanas, construction dust masks, any mask with a built-in valve, etc. are not compliant face coverings. Review and comply with 1910.502(f)(1).

Exception: Respiratory protection associated with work activities must be used.

Health safety-related face coverings cannot be used for dust protection, or in addition to dust protection. Contractor employees shall don health safety-related respiratory protection immediately following doffing dust protection masks.

D. Quality Control Plan and Quality Assurance Plan:

1) 01 40 00 Quality Requirements is included in its entirety in this contract. This specification is brief but very informative and enabling to those who approach it as an opportunity.

2) Submittal Register (aka submittal log) is described in Quality Assurance of the above specification, and the Project Manual at 01 33 23.

a. Submittal Register must list each and every submission listed in each and every specification. Because each project is different, do not recycle submittal logs from other projects.

3) (Dis)Approval of a submittal never constitutes a change to the quantity, quality, cost, or duration of a contract. The General Contractor is solely responsible for submitting and delivering complete and compliant work. Defective work shall be removed and replaced at the contractor’s expense. The Government has the right and responsibility to withhold funds equivalent to the cost for the Government to complete the work should the contractor fail to promptly act in executing the work, or remedying defective work.

4) To help prevent (unfortunately) common shortcomings and mistakes with submittal preparation and submission, as well as ensure that the installation of systems is complete and compliant, the GC shall provide the services of at least one licensed professional engineer to pre-review and certify as compliant all submittals and subsequent systems prior to requests for VA or its AE to review for compliance. For projects requiring alteration or replacement of mechanical systems, the GC consulting engineer is required to be a licensed mechanical engineer. Similarly, for projects with significant electrical scope, retain a licensed electrical engineer. The consulting https://www.va.gov/covid19screen/ engineers may be employed by the same firm. Engaging a verified SDVOSB firm is always encouraged. The consulting engineer (or firm) cannot be the AE of-Record or part of their consulting team. Upon issuance of Notice to Proceed, GC shall immediately submit to VA for review and information the contact information and credentials of the contracted consulting engineer.

2. Construction Progress Meetings:

A. The Contractor’s Project Manager and Field Supervisor shall provide on-site weekly construction progress meetings with the COR for the entire period of performance.

B. Include preparation of meeting agendas, and subsequent minutes of the meeting for each event not later than 1 day (next business day) after each meeting.

C. Construction Progress Meeting Agenda’s and Minutes shall include: List of invitees/attendees, list of past/ongoing and new issues or concerns, indicate days remaining per the contract, detail any safety incidents, and include current updated copies of the RFI Log, the Shop Drawing Log, and a detailed 2-week look-ahead and utility shutdown schedule.

3. Daily Reports:

A. The Contractor shall provide a Daily Report each day, along with accompanying digital photos and other supporting documents. The Daily Report shall include: List of issues or concerns, days remaining per the contract, detail regarding any safety incidents, detail of daily safety inspections (including items checked and corrective actions taken), notations regarding any visitors to the work area.

B. Use of VA Form 10101 Contractor Production Report (fillable PDF at https://www.va.gov/vaforms/va/pdf/VA10101.pdf) is required each day – even on days with no contractor activity, which is what to report on such days. Contractor may and should provide more information than shown in the standard form, but the standard form is required.

C. The report must be accompanied by relevant time and date-stamped photos of construction progress of sufficient quantity and detail to enable viewers to clearly see the progress of all work to-date, all issues discovered (including those which become the subject of RFI’s). Email the VA Form 10101 Contractor Production Report and photos to the COR not later than 9 AM the next working day.

1) No photography on VA premises is allowed without written permission of the COR.

2) In no case shall the GC allow any team member to take photographs with patients, visitors, or employees in the picture.

4. Acceptance and Closeout:

A. Acceptance criteria for the work:

1) Schedule demonstration of new equipment and systems at least 21 calendar days in advance with the COR.

2) Provide factory startup and certification of all systems.

3) Demonstrate the operation of the system.

4) Newly installed water or medical gas piping and distribution system components shall be flushed and disinfected prior to being placed in service.

https://www.va.gov/vaforms/va/pdf/VA10101.pdf

Include documenting completion/certifications.

5) Startup and testing of new systems or equipment, or moving in VA purchased equipment or furnishings, or their use, does not constitute any form of Acceptance (or Beneficial Occupancy). The project is planned around the complete, complaint, and unconditional fulfillment of all requirements of the contract which enable the work to be complete – by definition. Please work with VA to expedite this process.

B. Closeout Records: Provide one full-size, and one half-size printed set of as-built drawings, as well as CD-ROM or DVD-ROM media containing a complete archive of all project documents and files, including but not limited to:

1) As-built record drawings of the installed condition as CAD and PDF files.

2) Approved shop drawings.

3) Operations and Maintenance Manuals.

4) Spare parts lists.

5) All photographs.

6) All daily reports.

7) All communications.

8) All pay applications.

9) All communication, change, and cost data.

10) All safety records.

11) A project Warranty for Construction written by the General Contractor, projected to start upon Final Acceptance by VA (typically within a business week of receiving a complete and compliant closeout package).

a. Where manufacturer’s warranties exceed one year, provide all documentation necessary for VA to exercise warranty rights beyond the standard GC warranty.

b. Where specified, such as with roofing systems, provide the warranty written by the manufacturer to VA for the term specified or greater (typically 20 years).

c. Note that moving furnishings or equipment into the space does not constitute occupancy or acceptance, however, damage to completed work during these activities shall be the responsibility of VA to correct.

12) Lien Waivers and other documents required by the Contracting Officer.

Part 5: Applicable Performance Standards

1. All work shall comply with

A. All VA and FHCC policies including and not limited to: VA Construction Safety and VA Infection Control Policies.

B. Codes, Standards and Executive Orders (Topic 1) found at http://www.cfm.va.gov/til/cPro.asp and 01 41 00 Regulatory Requirements

2. Coordinating with VA-retained Commissioning Agent (CxA), U.S. Army Corps of Engineers (USACE), and Architect-Engineer (A/E) as applicable.

http://www.cfm.va.gov/til/cPro.asp

A. VA has retained the services of the U.S. Army Corps of Engineers in support of this project for multiple roles, including acting as independent CxA. Other design professionals and commissioning experts may also be engaged in support of this project.

B. A/E field-verification and documentation of compliant systems remains an essential part of Construction Period Services.

C. The General Contractor is responsible for communication and cooperation with the A/E, CxA, and VA to enable compliant execution of contracts.

D. No action or inaction by the A/E, CxA, USACE, VA, or other supporting organizations ever relieves the GC from responsibility to deliver 100% of the project requirements as specified and designed. Only the assigned Contracting Officer can make changes to any contract.

3. The General Contractor shall have a Competent Supervisory Person on site at all times when any worker(s) or subcontractor(s) are present. The General Contractor is also required to maintain on site a competent Site Safety and Health Officer (see 01 35 26 Safety Requirements when any worker(s) or subcontractor(s) are present.

The VA COR may, at his or her discretion, may allow the Competent Supervisory Person to also act at the SSHO, based on demonstrated competency and performance in the two roles. If demonstrated lack of competency or effectiveness in either role is observed, the VA COR may revoke the privilege.

4. Safety:

A. Prior to any activity, review the following with all project and craft team leaders: 01 35 26

Safety Requirements.

B. The Contractor shall provide a proactive and complaint Construction Safety and

Accident Prevention plan in accordance with the Occupational Safety and Health Act, 01 35 26 Safety Requirements, and site-specific policies:

C. All persons working on any electrical systems rated 50 volts or more shall have the minimum qualification as a State Licensed Master Electrician or Registered Journeyman Electrician, and all activities shall follow the safe work practices in compliance with NFPA 70E Electrical Safety in the Workplace.

D. 01 35 26 Safety Requirements is included in its entirety in this contract. Each contractor-employer is required to be solely responsible for the health and safety of its employees in accordance with 29 CFR 1910, 1926, & 1960 of the Occupational Safety and Health Act of 1970, as amended.

E. Because each contractor-employer is required to be solely responsible for the health and safety of its employees, part of a compliant and effective safety management program requires each employer to plan and implement their own compliant permit-required work – including written permits. DO NOT rely on, or request that VA generate required permits such as Hot Work or Confined Space documents.

F. Prior to the beginning of any work, fire extinguisher(s) complying with NFPA 10 shall be pedestal-mounted in the work area. Inspection of the work area includes verification that inspection tags are current. Where non-compliant, the contractor may be required to remove and replace the unit(s) before resuming work activity.

G. All work in crawl spaces shall be planned and carried out as OSHA Permit-Required Confined Space.

H. Immediately stop work and notify the COR if asbestos is noticed or suspected in the area of work.

Exception: The above will not necessarily apply to areas where the documents call for abatement activities. This item is concerned with unplanned locations.

I. Fire-seal all penetrations made or discovered through any wall or floor assembly with UL Listed fire-rated products or systems.

5. Infection Control:

A. 01 35 33 Infection Control Requirements is included in its entirety in this contract. Its construct is enabling for each condition experienced through each phase of the work.

The following are high-level requirements most often found deficient during inspections, yet required.

B. Prior to any activity, review the following with all project team leaders: 01 35 33 Infection Control Requirements.

C. Review and comply with containment construction and sequence described in the design and specification documents.

D. Provide a modular dust-tight system designed and manufactured specifically to be used as a temporary construction isolation barrier.

E. Before the start of work provide pressure differential monitoring system at the entry door to the construction area to prove that the construction area is under negative pressure. Maintain daily logs of readings and submit to the COR weekly. Remove at the completion of construction.

F. Walk-off sticky mats are required at all times inside and outside all entry / exit points to all workspaces. Sticky mats must be changed at least once per shift, or more as required by the construction or COR. Size sticky mats to match the width of the door opening and ensure that no less than 24” depth is provided.

G. Block off all HVAC return ductwork and louvers to prevent introduction of dust into the HVAC system.

1) Where existing HVAC ducts are being removed, immediately, permanently, and compliantly seal off the opening.

H. Provide High-Efficiency Particulate Air Filtration (HEPA) recirculating air equipment inside the workspace. Size the air filtration system sufficiently large enough to ensure that negative pressure remains effective when doors are opened.

I. When working above the ceiling outside of the work area, such as in a corridor, open only one ceiling tile at a time, and provide dust containment tent or portable containment cube, with HEPA filtering negative air system to seal the one opening.

J. Broom-sweep the work area at the end of each day (or shift during days with multiple shifts). Provide HEPA vacuum and damp (not wet) mop daily where broom sweeping creates airborne dust.

K. Provide fire-sealing of all existing wall and ceiling openings in area of work needed to allow the HEPA filtration equipment to effectively generate negative air pressure within the work area, with respect to the surrounding area.

L. Provide HEPA-filtered vacuum cleaning of all surfaces, and damp mop the work area every day.

M. Do not allow corrugated carboard to be stored for any period of time within the hospital.

Upon arrival, unpack, and transfer all products from cardboard containers to sealed plastic containers, and immediately dispose of the cardboard – outside of the building.

Part 6: Site-Specific Requirements

1. Project number and the contract number in the subject line of all emails and documents.

Example: “556-21-701 EHRM INFRASTRUCTURE UPGADES, WEST CAMPUS

2. NORTH CHICAGO ,” and then specific subject such as Pay App, RFI, Submittal, Meeting, etc. Transmissions deviating from this focused and simple standard may be rejected, or simply lost because recipients could not readily-acquire their subject or importance over the plethora of ambiguous emails received each day.

3. Comply with all site-specific requirements and SOPs including and not limited to: Key Policy, Badging Policy, Rules of Behavior, and Smoking Policy.

4. Normal construction work hours are 7:00 AM to 3:30 PM Monday through Friday.

A. No work in stairs, corridors, lobbies, or other interior / exterior public areas shall be performed during the above-designated work hours.

B. Normal work hours can be modified only by written approval of the COR, and at no additional cost to VA.

C. No work by the Contractor on Federal Holidays, and no work during weekend adjacent to Federal Holidays occurring on Monday or Friday.

D. Do not plan critical activities, or activities requiring support from VA staff on weekdays occurring between weekends and Tuesday’s or Thursdays due to expectable reduction in staff resources.

E. Any work including and not limited to noise, vibration, dust, odors, core drilling, hammer-drilling, saw cutting, equipment moving in public corridors, soil compaction, and the like shall be performed during the above-designated work hours only.

F. Crane lifts, or any work that closes drive isles, closes building entries, or closes public corridors shall be during low patient times and performed between Saturday 6 PM through midnight concluding by 6 PM on the following Sunday, and then only after twenty-one (21) days’ notice, and submission of required planning documents no less than fourteen (14) days in advance.

5. All building systems shall be maintained in full operation at all times:

A. Request utility system shutdowns in writing not less than 21 calendar days in advance and scheduled with the COR at times least impacting patient care.

B. Shutdown work shall be during low patient times and performed between Saturday 6 PM through midnight concluding by 6 PM on the following Sunday.

6. Wherever demolition is planned, ceiling tiles are to be removed, or the sprinkler system is to be disabled, GC shall first provide uniform heat detection throughout the work area, connected to the existing supervised building master fire alarm system, for the duration of the work. New permanent fire and or smoke detection devices, installation, and programming shall be provided at contractor expense prior to turnover and acceptance.

7. Deliveries, Parking, Elevators:

A. Deliveries only at the dock, and pre-coordinated with the COR. At time of delivery:

Provide vehicle information to the VA Police. Remove the vehicle as soon as delivery is complete. Move materials in public corridors only during low patient times between 6 PM through midnight, concluding by 6 AM the following day.

B. No parking in the VA garages. As part of the Mobilization Plan submission, indicate where workers are to park.

C. Contractor shall use freight elevators. Do not move materials and employees in passenger elevators without written approval of the COR, and never within elevators occupied by staff or patients.

8. The Mobilization Plan submission shall indicate if and where a construction dumpster(s) is (are) intended to be placed. The contractor shall provide a construction dumpster with a locked safety fence surrounding it, at a location submitted to and approved by the COR.

Pavement, concrete surfaces, and landscaping shall be protected from damage resulting from delivery and retrieval, loading and unloading, and dumpster weight.

A. Construction Waste Diversion Reports are required for every dumpster removed from every construction site at every VA facility. Provide these reports to VA COR immediately after the waste hauler removes each dumpster to comply with VA GEMS Policy.

B. No trash, used packaging, or construction spoils shall be stored in the work area. Never use dumpsters other than those rented for this work. Severe penalties, including potential criminal charges, may be levied for use of government-rented or owned containers, or those of other contractors.

C. Trash removal from indoor work areas shall be within gondolas which have sealed covers (completely enclosed), and during non-business hours, via the freight elevators.

9. No on-site office or storage container shall be allowed. Provide “just-in-time” delivery and pickup. Coordinate with the COR for staging within the area of work.

10. No music radios within work areas.

11. No noise generated within the work area can be allowed to leave it.

12. The use of powder-actuated fasteners is forbidden.

13. Performing demolition using motorized equipment, whether tracked or wheeled, pushed or driven, is forbidden.

14. Two-way communications radios are allowed where transmit/receive frequencies will not disrupt any hospital system.

15. Before starting work the contractor shall give 21 days’ notice to the COR to enable security coordination and notification. This notice is separate from any notices required for utility shutdown described elsewhere in this scope.

16. VA reserves the right to close or shut down the project site and or require Contractor employees to leave the premises in the event of a civil emergency or operational requirement. In these rare circumstances, the Contractor may return to the site only with the written approval of the COR

17. Compatible system procurements shall include the following:

A. Locks and Keys: Temporary and permanent door hardware shall be compatible with

Best® 7-pin, G-keyway, interchangeable core. Prior to commencement of work, the contractor shall provide VA with blank cores; quantity matching the number of openings planned. VA shall then provide final pinout and keying. During construction, the GC shall remain responsible for security of their workspaces, including provision of temporary lock cores and keys.

B. Exit Signs: All exit signs shall be City of Chicago approved specification red letters on white edge-lit LED fixtures continuously illuminated 90 mins. after loss of power, push-to-test switch and LED pilot light on the housing, available as single or double-sided models, and meeting UL924.

C. 27 15 00 Communications Cabling (and other specifications which include telecom cabling): All new telecom cabling shall only be Cat 6a. Cat 6a telecom cable, termination punch-down T-568-(B.1, B.2, C.2, etc.), tested and certified (submit result to COR), 6-port modular wall jacks with two RJ45 on top and bottom and two blanks in middle. While VA facilities generally do not include plenum return spaces above ceilings, it nonetheless requires plenum-rated teledata cabling complying with codes pertaining to plenum environments.

18. Sole Source Procurement, the contractor shall provide fully functional complete systems, including the following sole source procurements for the following special systems:

A. Fire Alarm: Components, programming, and start up within the West Campus is by

Johnson Controls/Simplex.

B. Building Automation: Components, programming, and start up: Automated Logic

Company of Chicago.

C. Proximity card reader and door lock release entry system: Components, programming, and start up: eNorman

Date: December 19,2022
Part 4: Meetings, Submittals, and Deliverables:
Part 5: Applicable Performance Standards
Part 6: Site-Specific Requirements