About this file

This is a Request for Quotation (RFQ) issued by the State of Rhode Island's Office of Energy Resources (OER) for LED lighting retrofit services at two state facilities. OER seeks a qualified vendor to retrofit 435 existing lighting fixtures to LED at the Louis Pasteur Building (25 Howard Ave, Cranston, RI) and 132 existing lighting fixtures to LED at the RI Army National Guard Middletown Armory (106 Airport Access Road, Middletown, RI). The project scope includes providing all necessary labor, materials, equipment, supervision, and installation services to complete the work professionally and timely. A non-mandatory pre-bid conference is scheduled for August 19, 2026, at 9:00 AM, with the Middletown Armory site visit first, followed immediately by the Louis Pasteur Building site visit. The initial contract period will commence approximately August 2026 for 12 months, with an option to renew for up to one additional 12-month period based on vendor performance and fund availability.

The base bid must incorporate pre-approved utility incentives totaling $37,955.00 for the Louis Pasteur Building retrofit and $14,305.00 for the Middletown Armory retrofit, which are to be subtracted from the total project price. The vendor must provide a three-year warranty for all labor in addition to manufacturer warranties, complete as-built documentation, and closeout procedures. Required insurance coverage includes general liability with combined single limits of $1,000,000 per occurrence, workers' compensation with $100,000 per accident, and automobile liability with $1,000,000 per occurrence. The awarded vendor must execute a Rhode Island custom AIA A104-2017 contract and submit a copy of their Rhode Island Master Electrician License. All substitutions must be submitted in writing and approved through an addendum. Liquidated damages are assessed at $100 per day for non-compliance.

View the file

Other files

File Type Posted
RFQ27006897_Oct_16_26_solicitation_doc.pdf PDF
RFQ27006897_Oct_8_26_solicitation_doc.pdf PDF
RFQ27006897_Oct_27_26_solicitation_doc.pdf PDF
RFQ27006897_Oct_2_26_solicitation_doc.pdf PDF
VendorChangeDetailsReport_RFQ27006897_v2_Sep_3_26.pdf PDF
RFQ27006897_Sep_17_26_solicitation_doc.pdf PDF
RFQ27006897_Sep_16_26_solicitation_doc.pdf PDF
RFQ27006897_Oct_28_26_solicitation_doc.pdf PDF
Q&A Center Items - RFQ27006897 - Addendum # 1.pdf PDF
RFQ27006897_Sep_11_26_solicitation_doc.pdf PDF
RFQ27006897_Sep_7_26_solicitation_doc.pdf PDF
RFQ27006897_Oct_1_26_solicitation_doc.pdf PDF
RFQ27006897_Aug_7_26_solicitation_doc.pdf PDF
RFQ27006897_Sep_8_26_solicitation_doc.pdf PDF
RFQ27006897 A2.doc DOC document
Attachment C - Supplemental Conditions - V2.docx DOCX document
RFQ27006897_Oct_15_26_solicitation_doc.pdf PDF
RFQ27006897_Sep_10_26_solicitation_doc.pdf PDF
RFQ27006897_Oct_6_26_solicitation_doc.pdf PDF
RFQ27006897_Aug_10_26_solicitation_doc.pdf PDF
RFQ27006897 prebid sign in sheet.pdf PDF
RFQ27006897_Oct_9_26_solicitation_doc.pdf PDF
RFQ27006897 RI Army National Guard Middletown Armory Incentive Letter.pdf PDF
RFQ27006897 Attachments A B C- Louis Pastuer_ Middletown Armory.pdf PDF
RFQ27006897 Louis Pasteur Bldg - Incentive Letter.pdf PDF
RFQ27006897_Oct_23_26_solicitation_doc.pdf PDF
RFQ27006897_Sep_24_26_solicitation_doc.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2021-1.B Page 1 of 3 Revised 01/17/2023

RFQ – AGENCY SOLICITATION SPECIFICATIONS

HEADER

TITLE: RFQ27006897 OER Lighting Retrofit Louis Pasteur Building and Middletown Armory Building

DESCRIPTION: OER is seeking a vendor for retrofitting 435 existing lighting fixtures to led fixtures at the Louis Pasteur Building at The Pastore Complex in Cranston as well as retrofitting 132 existing lighting fixtures to led fixtures at the RI Army National Guard Middletown Armory

PRE-BID CONFERENCE: Yes MANDATORY: No Date: August 19, 2026 @ 9:00 AM

1. RI Army National Guard Middletown Armory, 106 Airport Access Road, Middletown, RI.

Cranston will follow Immediately after Middletown

2. Louis Pasteur Building, 25 Howard Ave, Cranston, RI

CONTRACT TERMS

The initial contract period will begin approximately August 2026 for 12 Months. Contracts may be renewed for up to [1] additional 12-month periods based on vendor performance and the availability of funds.

Insurance Requirements In accordance with this solicitation, or as outlined in Section 13.19 of the General Conditions of Purchase, found at https://rules.sos.ri.gov/regulations/part/220-30-00-13 and General Conditions - Addendum A found at https://www.ridop.ri.gov/documents/general-conditions-addendum-a.pdf, the following insurance coverage shall be required of the awarded vendor(s):

General Requirements:

13a) ☒ Liability - combined single limit of $1,000,000 per occurrence, $1,000,000 general aggregate and $1,000,000 products/completed operations aggregate.

13b) ☒ Workers compensation - $100,000 each accident, $100,000 disease or policy limit and $100,000 each employee.

13c) ☒ Automobile liability - $1,000,000 each occurrence combined single limit.

AIA Requirements:

The selected Vendor must submit a fully executed Rhode Island custom AIA contract. If awarded the contract, Vendor shall be required to purchase, complete and submit the specified AIA documents; more information and link to custom Rhode Island AIA website at https://ridop.ri.gov/vendors/public-works-aia-custom-state-rhode-island-documents.

For authorized change orders, Design Agents must obtain and utilize the custom Rhode Island AIA-G701-2017, AIA-G714-2017, and/or AIA-G802-2017, which can also be located at the above link. Full instructions will be included in the Tentative Selection Letter.

https://rules.sos.ri.gov/regulations/part/220-30-00-13 https://www.ridop.ri.gov/documents/general-conditions-addendum-a.pdf https://ridop.ri.gov/vendors/public-works-aia-custom-state-rhode-island-documents

2021-1.B Page 2 of 3 Revised 01/17/2023

9b) ☒ AIA A104-2017 Standard Abbreviated Form of Agreement Between Owner and Contractor with State of Rhode Island.

SECTION A. BACKGROUND

Proposed work will include converting existing lighting fixtures to LED fixtures. The lighting upgrades will improve security and support the Governor’s Executive Order 23-06, State Agencies to Lead by Example and Act on Climate.

The project consists of LED lighting upgrades at the following two (2) State properties:

1. Louis Pasteur Building – 25 Howard Ave, Cranston, RI

2. RI Army National Guard Middletown Armory at 106 Airport Access Road, Middletown, RI.

SECTION B: SCOPE OF WORK AND REQUIREMENTS

The project must provide the following:

1. Upgrade the existing lighting fixtures and lighting controls as listed in Attachments A – Fixture Schedule and Attachments B – Installation Schedule for each of the two buildings referenced.

2. Provide all necessary supervision, installation personnel, equipment, and materials to complete the work in a professional and timely manner as defined in Attachments A – Fixture Schedule, Attachments B – Installation Schedule, Attachments C - Supplemental Condition across each of the two buildings.

3. Provide a 3-year warranty for all labor in addition to any manufacturer warranties associated with the project.

4. Provide As-Built Documentation and Closeout Procedures as defined in Attachments C - Supplemental Conditions.

The Bases Bid must incorporates the following:

(1) Utility incentives for Louis Pasteur Building lighting retrofit is pre-approved, as indicated in the attached pre-approval letter. Please subtract the combined pre-approved incentives in the amount of $37,955.00 from the Total Project Price.

(2) Utility incentives for the Middletown Armory lighting retrofit is pre-approved, as indicated in the attached pre-approval letter. Please subtract the combined pre-approved incentives in the amount of $14,305.00 from the Total Project Price

Any utility incentives received are considered a form of payment by the State. Any future changes to the incentives would remain a form of payment by the State towards the total cost of the project.

Base Bid:

Provide all labor, equipment, and material for the complete workmanlike installation of the listed fixtures, your quote should include but not be limited to the following:

All luminaires, retrofit kits, wire, conduit, junction boxes, handholes, connectors, panels and appurtenances that are required to make fixtures operational.

Interconnection with existing power sources.

All protective safety equipment and barriers.

All staging, lifts and miscellaneous equipment necessary to complete the work.

All waste and storage containers are required.

Removal of all waste materials and trash.

2021-1.B Page 3 of 3 Revised 01/17/2023

All permits, pre and post inspections required.

Include cost of a 3-year warranty for all labor in addition to any manufacturer warranties associated with the project.

Additional Requirements:

1. All substitutions must be requested in writing as a separate attachment to the Q&A in OSP. Substitutions must be approved as part of a posted addendum, and no other substitutions will be accepted.

2. Vendor must upload a copy of there RI Master Electrician License.

Liquidated Damages: $100 per day