QA-RFQ27006893- Response.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- URI Carothers Library Critical Power Upgrade
- Solicitation number
- RFQ27006893
- Issued by
- Providence County, Rhode Island
About this file
QA-RFQ27006893 Response Summary
This is a Request for Quotation response document prepared by the University of Rhode Island for a critical power infrastructure upgrade at the Carothers Library on its Kingston Campus. The scope encompasses replacement of main transformers, switchgear, and emergency/standby power systems; installation of temporary power distribution; construction of a decorative screen wall around the equipment yard; and civil site work for underground ductbank conduit routing. The project includes a new 2500 kVA pad-mounted transformer with oil containment and a 550 kW diesel generator with sound attenuation enclosure. Quotations were due September 4, 2026, with a non-mandatory pre-bid meeting held on August 12, 2026 at the Carothers Library site. The contract period begins approximately December 1, 2026, with construction anticipated to start in May 2027, substantial completion targeted for June 2029, and final completion in August 2029. The project is structured in multiple phases due to extended equipment lead times of approximately 110 weeks, extending through a one-year post-construction warranty period ending in August 2030.
The base bid includes $950,000 in allowances for unforeseen mechanical, electrical, architectural, civil/structural, and permit/code compliance conditions, with liquidated damages assessed at $5,000 per day. Two add alternates are available: a five-year generator warranty and a screen wall mockup. Unit pricing is required for additional ductbank installation on a per linear foot basis. The contractor must provide bid and performance bonds and comprehensive insurance including general liability of $2,000,000 per occurrence, workers compensation of $1,000,000, automobile liability of $1,000,000, crime insurance of $500,000 or fifty percent of contract amount (whichever is greater), builder's risk equal to the contract face amount, and excess insurance of $5,000,000 per occurrence and aggregate. Progress payments are made monthly with five percent retainage through substantial completion. The Owner reserves the right to withhold three percent of the Contract Sum if the contractor does not maintain a regular place of business in Rhode Island, until thirty calendar days after final completion.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFQ27006893 - URI Carothers Library Critical Power Upgrade | |
| Question | Answer |
| Are we reusing the existing underground raceways for the generator? | We are using a portion of the underground conduits for the generator. Please see Keynotes 2, 3, and 4 on dwg ED-100.1. |
| Is the expectation to put all conduits in the slab? | See Key Note 1 on Drawing E-101 for location of conduits that are to be installed below the slab. See Drawing E-501 for underslab conduit details. |
| A-401 requires removal, salvage, and reinstallation of exterior ribbon-window glazing. The |
hazardous-material schedules identify Room 041 door glazing/caulk but do not clearly address the exterior window sealants or glazing compounds. Confirm survey status and
| abatement/disposal requirements before disturbance | The window glazing should be assumed to contain asbestos and PCBs and should be abated. Revise note on A-401 to state that the exterior ribbon-window glazing shall be removed and replaced in kind after the termination of the electrical scope. |
| A-601 schedules D-03 as a 45-minute Type V door at a 2-hour emergency electrical closet, |
while Section 08 80 00 specifies only 1/4-inch tempered glass. Confirm required door, frame,
| and vision-lite ratings and provide the required listed glazing assembly | Revise Door D-03 to utilize Type F door, instead of Type V door, to remove vision panel for rated door. In addition, change 45min fire-rating to 90 min on door schedule. |
| Section 02 82 13 requires the two Room 041 entry doors with ACM/PCB glazing and caulk to |
be removed and disposed, while A-101 directs doors previously removed to be reinstalled.
| Identify each affected door and confirm which doors/frames are new, reused, or reinstalled | Existing interior doors indicated to be removed shall be removed and disposed of properly by the abatement contractor. Exterior doors indicated to be removed and reinstalled shall be handled in the following way: It is assumed that the doors are asbestos or PCB containing. Abatement contractor shall remove PCB and asbestos containing sealant and glazing. Remove existing doors and frames, and clean in preparation for reinstallation by general contractor. |
| Section 02 84 33 treats existing exterior CMU paint as assumed PCB bulk-product waste and |
limits masonry removal to disturbed work; Section 09 91 00 requires removal of all existing paint before repainting. Confirm removal limits, containment/disposal, and the approved
| encapsulation or overcoat system | Removal limits are areas required to be repainted due to the construction activity including areas directly impacted by modifications and incidental areas effected during construction. | |
| Section 09 91 00, Paragraph 3.7, calls for acrylic polymer finish coats over existing CMU, while Schedule 09 91 00-B lists an epoxy system for CMU/brick. Confirm the governing preparation, primer, and finish system | Follow the Schedule 09 91 00-B epoxy system | |
| Section 09 91 00 refers to Schedule 09 91 00-C for piping color coding, but Schedule C is not included. Provide Schedule C and identify the piping/equipment surfaces, locations, and limitsto be painted | Color coding shall be coordinated with the University during Construction. HVAC piping is not required to be painted. | |
| Drawings show slab cuts/trenches and concrete repair in Rooms 039, 041, and Corridor 040. |
Confirm final floor-finish restoration at each cut, including material, limits, patching, and
| transition requirements | For bidding purposes, assume the new concrete flooring shall be polished, however final floor finish to match existing floor finish, demolition limits to be determined based on quantity to be removed for installation of new conduit. | |
| Section 02 82 13 requires removal of approximately 775 SF of flooring in Process Room 044 to the concrete slab, but the drawings do not identify replacement flooring. Provide the required finish, product/color, base, transitions, and installation limits, or establish a flooring allowance if these selections are deferred. | Flooring in Room 044 shall be protected per Drawing AD-101 and shall not be removed other than what is required for the door infill. | |
| The hazardous-material specifications identify abatement items not associated with work shown on the drawings, please Confirm whether the base bid shall include all materials listed in Sections 02 82 13, 02 84 33, and 02 87 13, or only materials requiring disturbance to complete the work indicated on the drawings. | The base bid shall include all materials listed in the project manual and drawings. Not all materials to be abated may be indicated on the drawings. | |
| Division 26 describes its construction sequence as a general guide subject to change, while Division 01 requires the Contractor to submit the detailed sequence before site work begins. Given continuous building occupancy and extensive temporary-power requirements, please confirm that deviations necessary to maintain service are permissible after Engineer/URI approval and identify any sequence steps that are mandatory and may not be reordered. | Confirmed, deviations are permissible after the Engineer/URI approval. | |
| Section 26 05 00 states equipment locations are approximate and locations moved more than 5 feet require Engineer approval. Please confirm whether associated feeder/raceway changes resulting from an Engineer-directed relocation exceeding the contract-document routing are considered Base Bid coordination or a change where they materially increase quantity/length. | The design drawings are diagrammatic in nature. The Contractor shall coordinate the location of feeder/raceway with field conditions. If a change in location is within five feet, it should be considered base bid. If the location is greater than five feet the Contractor shall submit the new location for review via RFI. | |
| The Scope provides a $400,000 unforeseen electrical conditions allowance covering feeder rerouting, additional breakers/boards/panels, lighting/circuitry, temporary equipment and labor. Please confirm the required authorization/documentation procedure before drawing against this allowance and clarify that conditions not reasonably identifiable from the Contract Documents/required pre-bid observations will be handled through this allowance rather than Base Bid contingency. | ||
| The $400,000 Unforeseen Electrical Conditions Allowance covers conditions not reasonably identifiable from the Contract Documents or required pre-bid observations. |
Before drawing against the Allowance, the Contractor must submit written notice to the Owner's Project Manager/Engineer describing the condition, why it wasn't reasonably discoverable pre-bid, and an itemized cost breakdown. No Allowance work may proceed without prior written authorization, documented via CCD, per Contract procedures. Unused Allowance balances are credited back to the Owner at closeout; costs exceeding the Allowance require separate written authorization.
| Section 01 50 00 requires temporary utilities/equipment to be removed before Substantial Completion and underground temporary installations removed to at least 2 feet below grade. Please clarify whether the temporary 5kV ductbank/conduits, transformer pads, temporary feeder supports and associated underground electrical infrastructure are to be completely removed or may be abandoned below the specified depth. | Temporary utilities shall be completely removed upon cutover to new system. This work will be coordinated with URI. |
| Regular work is generally limited to 6:00 AM–5:00 PM, outside-hours work requires advance approval, and work is prohibited during final examinations. Because major electrical cutovers may need to occur outside occupied hours, please identify which planned electrical outages/cutovers are required to be performed nights/weekends and confirm whether required premium-time labor is to be included in Base Bid. | The Contractor will be responsible for identifying the number and duration of all planned outages and recommending when they occur to URI for review and approval. Outages during winter and/or summer break when classes are not in session during regular working hours may be submited to the University for consideration. All costs, including premium time labor should be included in the base bid. |
| Temporary Facilities requires Owner notification before construction that could activate the existing fire detection system. Please identify the required fire-alarm impairment procedure, authorized system operator and required fire watch, and clarify whether associated fire-watch cost is by the EC when impairment results from electrical work. | |
| The procedure and authorized system operator will be discussed with the Contractor once the project is awarded. Fire watch costs shall be by the Electrical Contractor. | |
| Division 01 specifically includes fire alarm in the electrical modifications, and separate FAD-101/FA-101 drawings are included in the contract set. Please confirm whether the EC is responsible for the complete fire-alarm demolition/modification scope, including devices, wiring, programming, testing and acceptance, or whether portions will be performed by URI's fire-alarm vendor. | |
| Confirmed. Fire alarm work indicated in the drawing set shall be the responsibility of the electrical contractor. | |
| Section 26 24 13 requires switchboard metering to interface with BAS and directs the Contractor to coordinate the BAS point of interconnection before providing CAT6 in 3/4-inch EMT to the nearest IT closet. Please identify the designated IT closet/BAS connection point and clarify whether the EC is responsible for furnishing/terminating/testing CAT6 or only raceway and cable, with BAS programming by others. | |
| Terminate the cable and raceway for connection into the BAS to the nearest wall next to the meter for a future connection. | |
| Section 26 05 00 acknowledges that power/control wiring shown is based on specific manufacturers and actual wiring may differ. Please confirm that material changes to feeder size, circuit count, conduit quantity or controls resulting from approved equipment differing from the basis-of-design will be addressed through the submittal/RFI process rather than assumed in the EC's Base Bid. | |
| If the Contractor decides to use an alternate manufacturer that results in changes to feeder size, circuit count, etc. the EC will be responsible to include those costs in the base bid. | |
| Division 01 identifies an electrical-room cooling system as mechanical work, while Division 26 requires the EC to verify final equipment locations and electrical requirements of equipment furnished under other sections. Please provide final electrical characteristics and connection requirements for all new electrical-room HVAC equipment, including voltage, MCA/MOCP, disconnect, controls/BAS interfaces and source panel/circuit. | |
| Please refer to Drawings E-100 and E-101 for HVAC equiment circuitry and panel schedule DP21B on Drawing E-004. | |
| The EC is directed to confirm whether existing generator fuel, fuel lines and the separate fuel tank are included in demolition. Please clarify the responsible trade for fuel removal, tank/line demolition, environmental handling and disposal, and identify the EC's termination/disconnection limits. | |
| The demolition of the fuel tank, lines, and associated environmental handling and disposal shall be the responsibility of the Contractor responsible for the work identified on civil Drawing C-100. Key notes 5 and 6 on Drawing ED-100.1 shall be deleted. | |
| Section 26 05 05 directs coordination of disposal of the existing 120/208V and 277/480V pad-mounted transformers and associated oil, but also states transformers are to be turned over to URI upon written request. Please confirm final disposition of each transformer and whether the EC should carry transportation/disposal, salvage turnover, oil testing and oil disposal in Base Bid. | |
| The existing transformers are to be demolished by the EC. URI shall be provided the opportunity to observe each and decide if they wish to retain one or more for future projects requiring temporary services.. The EC shall be responsible for their removal, transportation and disposal, but also include the option of transportation to a URI designated storage area on campus. | |
| The asbestos specification requires electrical isolation, temporary GFCI panels for HEPA equipment/tools/lighting, and a licensed electrician on call during abatement. Please confirm whether these temporary panels, feeders and electrician standby services are included in the Electrical Contractor's Base Bid or the abatement subcontractor's scope. | |
| All electrical connections and disconnections shall be performed by the licenced EC. | |
| The selective-demolition specification identifies internal electrical components within MCCs as assumed asbestos-containing material, and painted equipment/building components may contain lead/PCBs. Please identify which electrical equipment scheduled for EC demolition requires abatement by the hazardous-material contractor before the EC may disconnect, dismantle or handle the equipment, and clarify the scope boundary between EC electrical isolation/disconnection and abatement contractor removal. | |
| The abatement contractor shall assume the switchboards and electrical panels shown to be demolished require abatement. The electrical contractor shall disconnect and make the equipment safe before removal by the abatement contractor. | |
| Section 26 05 05 requires certain abandoned horizontal conduits to be removed to a junction box 40 feet outside the electrical rooms or to the vertical transition. Please clarify which condition governs where both are present and identify whether concealed conduit beyond accessible areas is intended to remain abandoned in place. | |
| EC shall comply with section 260505 for equipment affected within the scope of work for this project. | |
| Civil drawings state that not all utility services are shown and require field verification/test pits, while the electrical sequence requires GPR or other approved methods. Please confirm the extent of GPR, test pits and subsurface investigation included in Base Bid, and whether rerouting caused by undocumented utilities is to be addressed under the applicable unforeseen electrical/civil allowances. | |
| The extent of the GPR scanning shall be confined to areas indicated within the scope of work where proposed feeders and ductbanks are shown. Confirmed, rerouting of ductbanks and feeder due to unforeseen site conditions shall be processed via the allowances. | |
| The sequence requires trenching between Rooms 041 and 039 and references newly abandoned electrical conduits scheduled for reuse. Please identify on the drawings which existing conduits are specifically intended for reuse and provide known sizes/routes, or confirm that reuse is contingent on contractor investigation and mandrel/testing with unsuitable conduits addressed by RFI/allowance. | |
| Conduits scheduled for reuse are indicated on Dwg ED-004. Exact routing is not shown | |
| The sequence requires loads ultimately connected to DP41B to be temporarily intercepted in pullboxes and backfed from an exterior temporary 480V panel before final cutover. Please provide a definitive schedule identifying all DP41B loads requiring temporary interception, existing feeder sizes, proposed interception locations and final circuit assignments. | |
| The EC shall review the construction documents in their entirety, to include the panel schedule for panel DP41A and DP41B for required temporary connections that will allow the existing 277/480V switchboard to be demolished. Please see the panel schedule for DP41B on dwg E-003. Proposed interception locations will be a means and methods process by the EC, that provides temporary cutover to allow the library to avoid extended outages during temporary and permanent cutover. | |
| Section 26 05 00 requires extensive field data and photographs of breakers, panels, disconnects, wiring and utility information at least 8 weeks before energization. Please confirm whether this survey is limited to equipment affected by the new distribution system or applies to all downstream existing panels/equipment fed from the replaced service, and identify inaccessible equipment that URI will make available for survey. | |
| Confirmed. The survey only applies to equipment affected by the scope of work indicated on the drawings. | |
| Section 26 05 00 states that the Engineer will provide arc-flash labels for installation by the Contractor, while Section 26 24 13 requires the Contractor's short-circuit/coordination/arc-flash analysis. Please confirm the division of responsibility for performing the arc-flash calculations, generating label data, printing labels, and physically installing labels. | |
| The EC is responsible for the arc flash study and labels and label installation. The engineer shall provide review and approval of the study and proposed labels only. The statement regarding the Engineer providing the labels shall be removed from the specification. | |
| Section 26 24 13 requires the short-circuit/coordination study prior to release of the replacement switchboard. Please confirm whether preliminary equipment data may be submitted and the study completed using manufacturer-proposed impedances/trip units prior to approved equipment release, and identify the required review sequence so this requirement does not delay long-lead switchboard procurement. | |
| Confirmed. The EC shall provide the selected equipment manufacturer proposed transformer size and standard impedance, switchboard and panel sizes, circuit breakers, trip unit makes and models, estimated feeder lengths for the purposes of completing the study. | |
| The coordination study requires utility short-circuit current, impedance, X/R ratio, transformer information and related data. Please confirm that URI/utility will provide the required upstream 5kV system data and identify the point of contact and anticipated date the information will be available to the EC/study provider. | |
| Confirmed, URI utilities group shall provide require 5KV system data for the completion of the study. The EC shall coordinate with URI for this information. | |
| Section 26 05 05 requires temporary 5kV cable, splices, separable connectors and J-series wall-mounted connection points to minimize outages during replacement of the existing pad-mounted switches. Please provide/confirm the intended temporary 5kV switching/cutover arrangement, required switching authority, URI utility involvement, and whether the EC or URI performs actual medium-voltage switching. | |
| The EC shall own all medium-voltage switching. The EC shall schedule individual outages for the (2) 5KV circuits. The EC shall coordinate connector installation and outages with URI to minimize impact to the operation of the Library. The EC shall propose J series connectors in existing manhole that facilitates future cabling associated with this project and that provides the manhole future flexibility for utility cabling at the completion of the project. | |
| Section 26 05 00 indicates that installation of the permanent generator requires relocation of the existing temporary roll-up generator and its connections. Please provide the required temporary-generator relocation location, routing, cable lengths, protection requirements and anticipated number of relocations, or confirm that the EC is to propose the temporary location/routing for approval. | |
| EC shall coordinate with the General Contractor to relocate the temporary generator in a location that will not impede the work of the project. EC or GC shall provide URI proposed temporary generator locations for approval, that facilitate the scope of work while maintaining generator power to the building. If the generator must be relocated multiple times, that cost should be included in the base bid. | |
| Section 26 05 05 requires temporary cables to the existing generator-backed standby panel/ATS and 24/7 refueling for the duration of the project or until the new system is approved. The Scope states that a temporary generator is already installed adjacent to the equipment yard. Please identify who owns/provides the existing temporary generator, its rating and fuel capacity, and confirm whether the EC is responsible for all fuel, maintenance, servicing and 24/7 refueling from NTP until permanent emergency/standby acceptance. | |
| Please see dwg ED-100.1 for the removal of the existing temporary generator. URI will maintain temporary generator service and refueling until such time the permanent system is energized. | |
| The specifications require the EC to identify loads associated with existing 120/208V contactors and submit a reconnection list before work. Please confirm whether the Engineer will issue the final reconnection destinations and circuit assignments after review of the field survey, rather than requiring the EC to determine final life-safety/standby distribution design. | |
| Confirmed, engineer will issue circuit assignments after the review of the Contractor's field survey. | |
| Section 26 05 05 requires existing generator-backed contactor loads serving emergency egress lighting to be reconnected to the life-safety system, while other generator-backed loads are to be connected to the standby system. Please provide a definitive schedule identifying each existing generator-backed circuit/contact load and its required final classification as Life Safety, Legally Required Standby, or Optional Standby, including final source panel/ATS. | |
| Refer to the panel schedules for life safety and optional standby loads. | |
| Selective demolition requires a minimum two weeks' notice for demolition affecting Owner operations, while electrical demolition requires 72 hours' permission before disabling electrical systems. Please clarify the required notice period and approval procedure for planned electrical shutdowns so the EC can incorporate the correct shutdown schedule and premium-time requirements. | |
| Demolition work shall be identified and submitted to URI and the GC 2 weeks in advance of work, with a minimum of 72hrs of approval time before work can commence. | |
| Section 26 05 00 states that the building may not be shut down for more than 8 hours, while Section 26 05 05 requires 72-hour Owner notification before disabling existing electrical systems. Please confirm whether 8 hours is the absolute maximum outage for every individual electrical system, including 5kV service, 480V normal, 208V normal, life safety and standby systems, and identify any loads requiring a shorter or zero-interruption transfer. | |
| Confirmed, outages may not exceed 8 hours in duration. Contractor must receive approval of outages 72 hour prior to commencing the outage. | |
| Please confirm how the EC is to proceed when field investigation identifies an active existing load that is not identified on the demolition drawings, one-lines, or panel schedules but originates from equipment scheduled for demolition. Shall such loads be maintained temporarily pending written direction from the Engineer, and will permanent rerouting/reconnection not indicated by the Contract Documents be addressed through the electrical unforeseen-conditions allowance? | |
| Active loads discovered in the field by the contractor shall be identified and the engineer and URI notified of their existence. URI, the engineer, the general contractor and the electrical contractor shall coordinate and develop a process and procedure on how to proceed. If the circuit is deemed essential and must be relocated, rerouted and re-energized, this work shall be itemized and submitted via the RFI and change order process for approval. | |
| The contract requires the EC to field verify the loads on the existing 120/208V switchboards in Rooms 039 and 041 and the 277/480V switchboard in Room 039 and submit a list of defunct loads. Please confirm whether the existing panel directories and feeder designations shown on the drawings are informational only and that final disposition of unidentified/ambiguous circuits will be directed by the Engineer/URI following the contractor's field survey. | |
| Confirmed. The existing panel directories are informational only. | |
| Section 26 05 00 requires all equipment to remain operational except during switchovers and limits building shutdowns to 8 hours. Section 26 05 05 requires temporary feeders to the existing 480V, 208V, standby and emergency systems. Please provide/confirm the complete list of existing feeders and loads that must be temporarily fed, including feeder ampacity, source/destination, required temporary breaker size, and whether temporary feeder routing shown on the demolition drawings is intended to be complete or diagrammatic. | |
| The contract documents indicate the latest listing of feeders and circuits for the 480V, 208V, standby/emergency system. The contractor shall backfeed existing circuits and feeders, as coordinated with URI, the general contractor and the engineer, that avoids outages exceeding 8 hours. | |
| The project Scope of Work states that a temporary transformer is to be procured and installed to maintain building power “if required.” However, Section 26 05 05 specifically requires a temporary 1000 kVA 277/480V pad-mounted transformer, temporary 1200A 480V distribution, a temporary 500 kVA 480-208Y/120V transformer, and temporary 1200A 208V distribution. Please confirm that the complete temporary distribution system described in Section 26 05 05 is required Base Bid work and clarify which, if any, portions are conditional. | Confirmed, it shall be included in the base bid. The electrical contractor shall provide the temporary power system as indicated. |
| The RFQ drawings are 8.50 x 11 inch. Will a full-size and to scale set be issued? | The State office can only post the drawings in 81/2 by 11 for the on line portal. |