This is a Project Status Report template for the Delivery of Automated Systems for Healthcare (DASH) Program, a state and local healthcare technology implementation project. The document serves as a standardized weekly reporting mechanism to track project progress across multiple critical areas including project management, contract deliverables, scheduling, resource allocation, system development lifecycle requirements, functional design, configuration and development, testing and software quality assurance, data conversion, data management, implementation and deployment, training, and organizational change management. The report utilizes a traffic light health indicator system (Green for "On Target," Yellow for "At Risk," and Red for "In Jeopardy") to provide visual project status across each functional area, with specific criteria defined for each color rating based on deliverable timeliness, schedule performance indices, resource availability, task delays, risk mitigation status, and issue severity levels.

The report template includes structured sections for documenting action items by completion status, change requests in process with approval dates, approved and pending deliverables, inbox items for change requests and risks, open and closed issues categorized by severity and priority, open and closed risks with response strategies, and detailed project area updates covering activities completed during the reporting week and planned activities for the following two weeks. The template accommodates both vendor and state comments and activities across all project components, enabling collaborative tracking between the implementing vendor and state stakeholders. While the document provides no specific pricing information, incumbent details, funding sources, or contract term information, it establishes the governance and reporting framework necessary for managing a complex healthcare system implementation project requiring coordination across multiple functional disciplines and stakeholder groups.

View the file

Other files

File Type Posted
ATTM 021.pdf PDF
ATTM 022.pdf PDF
ATTM 024(a).docx DOCX document
ATTM 016.pdf PDF
ATTM 014.pdf PDF
ATTM 005.docx DOCX document
ATTM 006.docx DOCX document
ATTM 008.xlsx XLSX spreadsheet
PL 001.docx DOCX document
ATTM 009.xlsx XLSX spreadsheet
ATTM 017.pdf PDF
ATTM 024(b).xlsx XLSX spreadsheet
ATTM 018.pdf PDF
PL 002.pdf PDF
ATTM 003.docx DOCX document
ATTM 013.xlsx XLSX spreadsheet
ATTM 019.pdf PDF
ATTM 011.pdf PDF
ATTM 015.pdf PDF
ATTM 023.xlsx XLSX spreadsheet
ATTM 010.docx DOCX document
ATTM 026.docx DOCX document
ATTM 020.pdf PDF
ATTM 007.docx DOCX document
Solicitation 5400029905.docx DOCX document
ATTM 025.docx DOCX document
ATTM 012.xlsx XLSX spreadsheet
ATTM 004.docx DOCX document
ATTM 001.docx DOCX document
ATTM 002.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Delivery of Automated Systems for Healthcare (DASH) Program

[project acronym] Project Status Report

Submitted by:

Fill in Project Manager Names

Week Ending:

PL 003

[acronym] Project Status Report

V5.0 Page 1 of 11

PROJECT HEALTH INDICATORS

Evaluated Area Current Period

Trending

Comments

Project Management Contract Deliverables Vendor Comments:

State Comments:

Schedule Vendor Comments:

State Comments:

Resources Vendor Comments:

State Comments:

SDLC

Requirements Vendor Comments:

State Comments:

Functional/Design Vendor Comments:

State Comments:

Configuration/Development Vendor Comments:

State Comments:

Test/Software Quality Vendor Comments:

State Comments:

Data Conversion Design Vendor Comments:

State Comments:

Data Management Vendor Comments:

State Comments:

Implementation (Deployment)/Training

Planning Vendor Comments:

State Comments:

Organizational Change Management Planning Vendor Comments:

State Comments:

V5.0 Page 2 of 11

Health Indicator Criteria

Joint Weekly Status Report

On Target Criteria At Risk Criteria In Jeopardy Criteria

G

Y

R

Contract Deliverables

No contract deliverables are currently late for submission, resubmission, or sign-off

Contract deliverable(s) are late for submission, resubmission, or sign-off, but critical path is not impacted

Contract deliverable(s) are late for submission, resubmission, or sign-off and critical path is impacted

Schedule • SPI is ≥ 0.95; and

• Critical path is late by ≤5 working days

• SPI is ≥ 0.9 and ≤ 0.94; or

• Critical path is late by < 15 and > 5 days

• SPI is < 0.9; or

• Critical path tasks is by

> 15 working days

Resources • Planned resources are assigned; and

• Resource levels are sufficient to finish the project under the current schedule and scope

• Work is delayed up to 15 working days due to lack of resources; and

• Resource levels are sufficient to finish the project under the current schedule and scope

Work is delayed more than 3 weeks in 1 or more areas due to lack of resource(s)

SDLC

Requirements • No tasks are late by more than 5 working days; and

• Monitored risks may exist in this area, and mitigation is planned or in progress

• No tasks are more than 15 working days late; and

• All related, monitored risks have mitigation planned or plan is in progress

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or

• Open high severity issues exist

Functional/ Design • No tasks are late by more than 5 working days; and

• Monitored risks may exist in

• All related, monitored risks have mitigation planned or plan is in progress

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or

• Open high severity Issues exist

Configuration/Deve lopment

• No tasks are late by more than 5 working days; and

• Monitored risks may exist in this area, and mitigation is planned or in progress

• No tasks are more than 15 working days late; and

• All related, monitored risks have mitigation planned or plan is in progress

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or issues exist

V5.0 Page 3 of 11

On Target Criteria At Risk Criteria In Jeopardy Criteria

G

Y

R

Test/Software Quality

• No tasks are late by more than 5 working days; and

• Monitored risks may exist in this area, and mitigation is planned or in progress; and

• No severity 1 (showstopper) bugs exist

• All related, monitored risks have mitigation planned or plan is in progress; or

• No more than 1 severity 1 bug exists

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or

• Open high severity issues exist; or

• More than one severity 1 bug exists

Data Conversion

Design • No tasks are late by more than 5 working days; and

• Monitored risks may exist in

• All related, monitored risks have mitigation planned or plan is in progress

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or

• Open high severity issues exist

Data Management • No tasks are late by more than 5 working days; and

• Monitored risks may exist in

• All related, monitored risks have mitigation planned or plan is in progress

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or

• Open high severity issues exist

Implementation (Deployment)/Training

• No tasks are late by more than 5 working days; and

• Monitored risks may exist in

• All related, monitored risks have mitigation planned or plan is in progress

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or

• Open high severity issues exist

ORGANIZATIONAL CHANGE MANAGEMENT

• No tasks are late by more than 5 working days; and

• Monitored risks may exist in

• All related, monitored risks have mitigation planned or plan is in progress

• One or more tasks are late by more than 15 working days; or

• Monitored risks exist in this area without mitigation plans; or issues exist

V5.0 Page 4 of 11

Trending column indicators:

= No change from previous reporting period

= Positive change from previous reporting period

= Negative change from previous reporting period

ACTION ITEMS

Action Items by Status

[Insert statistics table]

Completed Action Items

[Insert list of completed action items]

Overdue Action Items

[Insert list of overdue action items]

Action Items Due in the Next 2 Weeks

[Insert list of action items due in the next 2 weeks]

CHANGE REQUESTS

[See Change Management Plan for Additional Details on Change Request Metrics]

Change Requests In-Process

[Insert Data Only from “Status Report In-Process Change Request” View] ID Title Change

Request Owner

Status Approval Date

Deferred Until Date

Closure Date

V5.0 Page 5 of 11

DELIVERABLES

Approved Deliverables [Insert table of approved Deliverables]

Deliverables in Review

[Insert table of Deliverables in Review; include on-schedule indicator]

Deliverables Due to the State in the Next 2 Weeks

[Insert table of deliverables due to the State in the next 2 weeks]

Deliverables Due to Vendor in the Next 2 Weeks

[Insert table of deliverables due to the Vendor in the next 2 weeks]

INBOX ITEMS FOR THIS REPORTING PERIOD

[Insert statistics and list of InBox items; the InBox is the entrance point for change requests, risks, issues, and deliverables]

ID Title State Created Notes Submitter

ISSUES

[See Issue Plan for Additional Details on Issue Metrics]

Issues by Severity and Priority

[Insert Data Only from Pivot Table]

V5.0 Page 6 of 11

Open Issues*

[Insert Data Only from “Status Report Open Issues” View]

ID Issue Title Issue Severity

Issue Priority

Issue Owner Issue Status

Issue Resolution

Date

* Excludes Closed and Rejected Status

Issues Closed Since Last Report*

[Insert Data Only from “Status Report Closed Issues” View] ID Issue Title Issue

Severity Issue

Priority Issue Owner Issue

Status Issue

Closure

* Includes Closed and Rejected Status with Issue Closure Date since last report

RISKS

[See Risk Plan for Additional Details on Risk Metrics]

Risks by Priority and Status

Open Issues Severity

High Medium Low Grand Total

Pr io rit y High 4 4

Medium 1 1 2

Low

Grand Total 5 1 6

Open Risks Priority

V5.0 Page 7 of 11

[Insert Data Only from Pivot Table]

Open Risks*

[Insert Data Only from “Status Report Open Risks” View]

ID Risk Title Risk Owner Risk Priority

Risk Response Strategy

Risk Trigger

Risk Status

* Excludes Closed and Rejected Status

Risks Closed Since Last Report*

[Insert Data Only from “Status Report Closed Risks” View] ID Risk Title Risk Owner Risk

Priority Risk

Response Strategy

Risk Closure Date

Closure Reason

* Includes Closed and Rejected Status with Risk Closure Date since last report

PROJECT AREA UPDATES

This section includes the Vendor and State activities worked during the status week, the activities planned for the next two weeks, metrics for the ongoing work, and items of importance or interest for the project team.

High Medium Low Grand Total

St at us

Assigned 1 1

Draft 1 1

Monitoring 1 1

Pending Approval 1 1

Planning 1 1

Grand Total 1 2 2 5

V5.0 Page 8 of 11

PMO

Vendor Activities during the Week

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

State Metrics and/or Additional Information

QUALITY ASSURANCE

Vendor Activities during the Week

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

State Metrics and/or Additional Information

Infrastructure (Hardware and Software)

Vendor Activities during the Week

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

V5.0 Page 9 of 11

State Activities during the Week

State Activities Planned for Next Two Weeks

State Metrics and/or Additional Information

REQUIREMENTS AND DESIGN

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

State Metrics and Additional Information

Configuration/Development

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

V5.0 Page 10 of 11

TEST/SOFTWARE QUALITY

Vendor Activities during the Week

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

DATA CONVERSION

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

ORGANIZATIONAL CHANGE MANAGEMENT

State Activities during the Week

State Activities Planned for Next Two Weeks

V5.0 Page 11 of 11

IMPLEMENTATION (DEPLOYMENT)/TRAINING

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

FEDERAL CERTIFICATION

Vendor Activities Planned for Next Two Weeks

Vendor Metrics and/or Additional Information

State Activities during the Week

State Activities Planned for Next Two Weeks

PROJECT HEALTH INDICATORS
ACTION ITEMS
CHANGE REQUESTS
DELIVERABLES
INBOX ITEMS FOR THIS REPORTING PERIOD
ISSUES
RISKS
PROJECT AREA UPDATES