NOAA Standard Specification AMC-533-1 Potable Water Tank System Disinfection.pdf

PDF 111 KB Posted

Attached to
MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS Federal contract opportunity
Solicitation number
1305M226Q0100REF
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

Summary of Standard Specification 533-1A: Potable Water Tank and System Disinfection

This is a NOAA Marine Operations standard specification document that establishes requirements for disinfecting potable water tanks and systems on NOAA ships. The specification references the Vessel Sanitation Program 2011 Construction Guidelines from the U.S. Department of Health and Human Services (section 22.10) and supersedes MOC-533-1 from August 1991.

The disinfection procedure consists of two primary phases. For potable water tank disinfection, contractors must isolate tanks, rinse and drain interiors, then fill with potable water and add chlorine solution to achieve a minimum of 100 parts per million (ppm) Free Available Chlorine (FAC). Contractors must monitor FAC content hourly for at least four hours, maintaining levels at or above 50 ppm; if levels drop below 50 ppm, additional chlorine is added and the four-hour monitoring period restarts. For multiple tanks, the same water may be reused if the initial FAC is increased to 100 ppm. Following this initial phase, tanks are drained and refilled, then disinfected again with a starting FAC of 1.0 ppm or greater, monitored for 30 minutes until FAC remains at or above 0.2 ppm for that period. Finally, tanks are drained and refilled until FAC falls below 1.0 ppm. For potable water system disinfection, contractors must disinfect the entire system including tanks per the tank requirements, monitor FAC at various plumbing fixtures across all vessel decks (forward, aft, port, starboard) to confirm 50 ppm circulation, verify post-disinfection FAC levels are below 1.0 ppm at distant sampling points, and submit a written Condition Report to the Contracting Officer's Representative within 24 hours documenting sample locations and FAC readings. Appendix A provides guidance checklists for both tank and system disinfection procedures.

View the file

Other files for this federal contract opportunity

Other files attached to MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS, newest first.
File Type Posted
TJ-573-01 Cranes Deck and Boom O M.pdf PDF
TJ_FY2027 DD_Fire System Inventory_Fixed Semi-Cylinders.pdf PDF
NOAA Standard Specification MOC-167-1 Refurbishment of Water Tight Closures.pdf PDF
NOAA Standard Specification MOC-100-1A_Abs Load Line Survey.pdf PDF
NOAA Standard Specification AMC-505-1B_Valve Overhaul and Tests.pdf PDF
48026A-GI INDUSTRIAL-NOAA T JEFFERSON-POTBD_UTT.pdf PDF
1102-35 - Safe Use of Rigging Equipment (public).docx DOCX document
NF 57-07-12 - DryDock-UWILD Inspection Checklist (public).pdf PDF
Steyr Motors Marine Engines Manual.pdf PDF
TJ-233-03 EMD Engine 12-645F7B.pdf PDF
TJ-311-03 EDG Alternator.pdf PDF
Capstan_SA-1128 Manual for SA1014.pdf PDF
436-6634707 Machinery Alarm and Monitoring System Dk Pln - redline.pdf PDF
528-6634786E Plumbing and Deck Drains Arrangement and Details_130709483.pdf PDF
512-6634856_HVAC Arr and Details FCSLE Deck Fr 19-50.pdf PDF
TJ-079-03E Trim and Stability Booklet_101947795.pdf PDF
525-6634754E Fills Vents and Soundings Arrngmnt and Details.pdf PDF
TJ-528-009A - Grey Water and Sewage Modifications.pdf PDF
612-6634889D Lifelines Handrails and Stanchions.pdf PDF
TJ-611-6634891F DECK FITTINGS ARRANGEMENT and DETAILS.pdf PDF
163-6634821_Seachest Details.pdf PDF
243-6634740_Propeller Shafting Arrangement and Details.pdf PDF
TJ-582-002A New Transom Mooring Chock Inst.pdf PDF
636-6634911 Acoustic Tile Installation Arr.pdf PDF
601-6634921 Joiner Arrangement Main Deck.pdf PDF
320-6634691 Cable Wtrtight Penetrations - redline.pdf PDF
TJ_985_985-6634639_RevP_Sht1 THRU 3_ABS_FIRE CONTROL PLAN.pdf PDF
259-6634767 Diesel Engine Exhaust Arrangement.pdf PDF
514-3275003-12_91762335.pdf PDF
512-6634850F HVAC ARRNGMNT ENGRM_124644191.pdf PDF
TJ-583-022A Platform and Grating Mods.pdf PDF
101-6634867 Structural Module 8.pdf PDF
512-3275003-7 HVAC MODS 01 LVL AND ABV REV B.pdf PDF
801-6634641_Table of Offsets.pdf PDF
101-6634866_Structural Module Assembly No 7.pdf PDF
TJ-529-001A Cross Flooding Piping Installation.pdf PDF
TJ-562-001A Rudder Arrangment and Details_102457373.pdf PDF
562-6634741D Rudder Arrangement and Details.pdf PDF
073-6634629_Resilient and Dim Mounting List.pdf PDF
101-6634864 Structural Module 5.pdf PDF
259-6634766 Engine Exhaust System.pdf PDF
TJ-437-004 TLI Electrical Modifications.pdf PDF
TJ_FY2027 DD_Fire System Inventory_SCBA Tanks.pdf PDF
NOAA Standard Specification 997-1B Drydocking-Routine_Drydock-Work.pdf PDF
NOAA Standard Specification MOC-573-2 Overhaul Repair of Hydraulic Cylinders.pdf PDF
NOAA Standard Specification AMC-300-1_Overhaul of Electrical Rotating Machinery.pdf PDF
NOAA Standard Specification MOC-300-3 General Requirements for Electrical_Electronic Items.pdf PDF
NOAA Standard Specification MOC-631-3B Underwater Body Ablative Coating System.pdf PDF
NOAA Standard Specification AMC-634-1A_Deck Coverings.pdf PDF
Lufkin Marine Gears Spare Parts List RS2719S_LM584 RevB.pdf PDF
Show all 50

MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

533-1A August 2018

Superseding

MOC-533-1

AUGUST 1991

STANDARD SPECIFICATION

POTABLE WATER TANK and SYSTEM DISINFECTION

1. SCOPE

1.1 This specification contains the general requirements for disinfecting the potable water tanks and system on NOAA ships.

2. REFERENCES

2.1 “Vessel Sanitation Program, 2011 Construction Guidelines, U.S. Department of Health and Human Services, section 22.10, Disinfection of the Potable Water System”.

3. DEFINITIONS

3.1 Free Available Chlorine (FAC) - Concentration of residual chlorine in water present as dissolved gas (Cl2), hypochlorous acid (HClO), and/or hypochorite ion (CIO-). A test kit which measures free chlorine will indicate the combined concentrations of HCLO, ClO-, and Cl2.

4. REQUIREMENTS

4.1 Potable Water Tank Disinfection

4.1.1 General Requirements

a. Isolate the potable water tanks to be disinfected from the rest of the potable water service system. Thoroughly rinse and drain each tank’s interior.

b. The chlorine solution used to disinfect the tank must be diluted and added through a sounding tube or threaded connection. Immediately after adding the chlorine solution, rinse the sounding tube or threaded connection with at least five gallons of potable water.

4.1.2 Disinfection Procedure

a. Fill the tank with potable water until it starts to overflow, then stop. Exercise care not to pressurize the tank. As the tank fills, add chlorine solution to achieve at least 100 parts per million (ppm) Free Available Chlorine (FAC) content in the completely filled tank.

b. Monitor the FAC content hourly for at least four hours. If the FAC content drops below 50 ppm at any time, add additional chlorine solution to raise the FAC content back to 100 ppm and restart the four hour monitoring period. Continue monitoring and raising the FAC content until the FAC content remains at or above 50 ppm for a four hour period.

c. If disinfecting more than one tank, repeat the above procedure for each tank. At the contractor’s discretion, the same water may be used to disinfect each consecutive tank, as long as the initial FAC content is increased to 100 ppm at the start of the four-hour monitoring period.

d. Drain each tank and refill with potable water. Repeat the above disinfection procedure, except start with an initial FAC content of at 1.0 ppm or greater and monitor the FAC content for 30 minutes. Continue monitoring and raising the FAC content until the FAC content remains at or above

0.2 ppm for a 30 minute period.

e. Drain each tank and refill with potable water until the total FAC content falls below 1.0 ppm.

4.2 Potable Water System Disinfection

4.2.1 Disinfect the entire Potable Water System, including the potable water tanks, in accordance with reference 2.1 and the potable water tank disinfection requirements in 4.1 above.

4.2.2 Monitor the FAC at various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the 50 ppm free residual chlorine has circulated throughout the distribution system to include the distant sampling points.

4.2.3 After completion of the disinfection process, take additional samples at the same distant plumbing fixtures to validate that the FAC levels at these points are below 1.0 ppm.

4.2.4 Within 24 hours, submit a written Condition Report to the Contracting Officer’s Representative (COR) with the sample locations and FAC readings.

APPENDIX A

The following checklists are for guidance only. The Contractor is required to meet all requirements in the specification, whether or not they are captured accurately or fully in the checklists.

Potable Water Tank Disinfection Checklist

Check Delivery Period Action Service 1 Prior Tank Disinfection Perform Isolate the Potable Water Tank (s) from the rest of the system.

2 Prior Tank Disinfection Perform Rinse and drain the Potable Water Tank(s) interiors.

3 Tank Disinfection Perform Fill tank with potable water until it starts to overflow.

Do not pressurize tank.

4 Tank Disinfection Perform Add diluted chlorine solution to tank through a sounding tube or threaded connection until FAC is above 100 ppm.

5 Tank Disinfection Perform Rinse sounding tube or threaded connection with at least 5 gallons of fresh potable water.

6 Tank Disinfection Monitor Each hour, measure the FAC. If the FAC drops below 50 ppm, add additional chlorine solution until it is above 100ppm, and rinse the sounding tube or threaded connection. Continue this process until the FAC stays above 50 ppm for four consecutive hours.

7 Tank Disinfection, if more than one tank

Perform Repeat steps 3 – 6 for each tank.

8 Tank Disinfection Perform Drain each tank and fill with potable water until the FAC falls below 1.0 ppm.

Potable Water System Disinfection Checklist 1 System Disinfection Perform Clean, Disinfect, and Flush potable water tanks and potable water system using potable water with 50 ppm FAC for a minimum of 4 hours.

2 System Disinfection Monitor Monitor various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the 50 ppm FAC has circulated throughout the distribution system to include distant sampling points.

3 System Disinfection Perform Flush the tanks and system with potable water until the FAC drops below 1.0 ppm.

4 System Disinfection Monitor Monitor various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the FAC is below 1.0 ppm throughout the distribution system to include distant sampling points.

5 System Disinfection Submit Submit to the COR a Condition Report that includes the sampling locations and FAC measurements taken in steps 2 and 4.

1. SCOPE
1.1 This specification contains the general requirements for disinfecting the potable water tanks and system on NOAA ships.
2. REFERENCES
2.1 “Vessel Sanitation Program, 2011 Construction Guidelines, U.S. Department of Health and Human Services, section 22.10, Disinfection of the Potable Water System”.
3. DEFINITIONS
3.1 Free Available Chlorine (FAC) - Concentration of residual chlorine in water present as dissolved gas (Cl2), hypochlorous acid (HClO), and/or hypochorite ion (CIO-). A test kit which measures free chlorine will indicate the combined concentration...
4. REQUIREMENTS
4.1 Potable Water Tank Disinfection
4.1.1 General Requirements
a. Isolate the potable water tanks to be disinfected from the rest of the potable water service system. Thoroughly rinse and drain each tank’s interior.
b. The chlorine solution used to disinfect the tank must be diluted and added through a sounding tube or threaded connection. Immediately after adding the chlorine solution, rinse the sounding tube or threaded connection with at least five gallons of...
4.1.2 Disinfection Procedure
a. Fill the tank with potable water until it starts to overflow, then stop. Exercise care not to pressurize the tank. As the tank fills, add chlorine solution to achieve at least 100 parts per million (ppm) Free Available Chlorine (FAC) content in th...
b. Monitor the FAC content hourly for at least four hours. If the FAC content drops below 50 ppm at any time, add additional chlorine solution to raise the FAC content back to 100 ppm and restart the four hour monitoring period. Continue monitoring an...
c. If disinfecting more than one tank, repeat the above procedure for each tank. At the contractor’s discretion, the same water may be used to disinfect each consecutive tank, as long as the initial FAC content is increased to 100 ppm at the start of ...
d. Drain each tank and refill with potable water. Repeat the above disinfection procedure, except start with an initial FAC content of at 1.0 ppm or greater and monitor the FAC content for 30 minutes. Continue monitoring and raising the FAC content u...
e. Drain each tank and refill with potable water until the total FAC content falls below 1.0 ppm.
4.2 Potable Water System Disinfection
4.2.1 Disinfect the entire Potable Water System, including the potable water tanks, in accordance with reference 2.1 and the potable water tank disinfection requirements in 4.1 above.
4.2.2 Monitor the FAC at various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the 50 ppm free residual chlorine has circulated throughout the distribution system to include the distant samplin...
4.2.3 After completion of the disinfection process, take additional samples at the same distant plumbing fixtures to validate that the FAC levels at these points are below 1.0 ppm.
4.2.4 Within 24 hours, submit a written Condition Report to the Contracting Officer’s Representative (COR) with the sample locations and FAC readings.
4.3
APPENDIX A
The following checklists are for guidance only. The Contractor is required to meet all requirements in the specification, whether or not they are captured accurately or fully in the checklists.