Specification Section 01 33 29 Attachment 1 HPSB Checklist

View the file

Other files for this federal contract opportunity

Other files attached to Construction of a Instrument Development Facility, newest first.
File Type Posted
IDF_Selection_Statement_Signed.pdf PDF
IDF_Amendment_0007.pdf PDF
20171214_Perf_Drain_System_and_Waterproofing.pdf_--_kms.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_MH-101_-_FIRST_FLOOR_MECHANICAL_HVAC_PLAN_revised.pdf_kms2.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_M-801_-_MECHANICAL_SCHEDULES_revised.pdf_-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_22_26_revised.pdf_-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_22_13_revised.pdf_-_kms.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_MH-101_-_FIRST_FLOOR_MECHANICAL_HVAC_PLAN_revised-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_00_00_revised.pdf_-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_22_25_revised.pdf_-_kms.pdf PDF
NASA_GSFC_IDF_Amendment_0006.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_05_93_revised.pdf_-_kms.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_M-801_-_MECHANICAL_SCHEDULES_revised.pdf_-_kms.pdf PDF
IDF_RFP_No._80GSFC17R0009_-__Amendment_0005.pdf PDF
NASA_IDF_Duct_Tables.pdf PDF
IDF_RFP_Amendment_0004.pdf PDF
IDF_RFP_No._80GSFC17R0009_Amendment_0003.pdf PDF
QL_drawings_Showing_Furniture_for_Installation_TS.pdf PDF
Section_09_06_90_Attachment_A__Finish_Legend_Alternatives_Inspected_TS.pdf PDF
Attachment_2_Drawings_Informational_Purposes_Only.pdf PDF
Specification_Section_01_33_29_Attachment_2_TPC_Checklist_Inspected_TS.pdf PDF
IDF_Site_Visit_Sign_in_Sheet.pdf PDF
IDF_Site_Visit_Question_and_Answers-Clean.pdf PDF
RFP_No._80GSFC17R0009_IDF_Questions_and_Answers_1-73.pdf PDF
Question_Due_Date_Extension.pdf PDF
IDF_Amendment_0002.pdf PDF
ATTACHMENT_4_General_Wage_Decision_MD170058,_Modification_No._10.pdf PDF
RFP_No._80GSFC17R0009_Amendment_000001.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_COMPILED_-_final.pdf PDF
SF1442_final.pdf PDF
Goddard_IDF_Site_Visit_Registration_Form_final.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_1_COMPILED_final.pdf PDF
Enclosure_1_-_IDF_QASP-Scanned_-_final.pdf PDF
ATTACHMENT_9_NASA_Instrument_Development_Facility_Geotechnical_Report_-_final.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_COMPILED_-_final.pdf PDF
IDF_RFP_No._80GSFC17R0009_-_Sections_B-M_FINAL.pdf PDF
ATTACHMENT_8_MDE_Permit_-_Final.pdf PDF
ATTACHMENT_7_PIV_Attachment-Cleaned_-_final.pdf PDF
ATTACHMENT_3_BUILDING_INFORMATION_MODELING_SCOPE_OF_SERVICES_-_Final.pdf PDF
Exhibit_1-Pricing-Cleaned_-_final.pdf PDF
IDF_RFP_Cover_Letter_Scanned_final.pdf PDF
Exhibit_2-Subcontracting_Goals-_Cleaned_-_final.pdf PDF
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NASA FEDERAL SUSTAINABILITY METRICS

NASA SSPP (FY 2013) EO 13514 EO 13423 EISA 2007 HPSB MOU EPACT 2005

COMPLY WITH MOU HPSB Yes Yes Yes ‐‐‐‐‐‐‐ N/A ‐‐‐‐‐‐‐

INTEGRATED DESIGN PROCESS Yes Yes Yes ‐‐‐‐‐‐‐ Yes ‐‐‐‐‐‐‐

GHG REDUCTION Yes Yes Yes ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐

Scope 1 & 2 Reduce 18.3% by

FY2020, as compared to

Agency to set 2020 reduction target (2008 baseline)

Yes ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐

Scope 3 Reduce 12.6% by

FY2020, as compared to

Agency to set 2020 reduction target (2008 baseline)

Yes ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐

ENERGY EFFICIENCY

Energy Reduction • Reduce energy consumption/GSF of building area 3% annually from FY2003 baseline for FY2006‐

FY2015

• Procure EPEAT equipment

Sustainable acquisition of efficient (Energy Star or FEMP) products, where meet performance requirements

• Reduce 3% annually through 2015, 30% by end of FY2015 (2003 baseline)

• 30% below ASHRAE/

IESNA Standard 90.1‐

• By 2015 from 2003 baseline:

• 30% reduction energy usage

• 65% reduction in fossil‐fuel generated consumption

• Energy‐efficient lighting fixtures and bulbs

30% below ASHRAE/

IESNA Standard 90.1‐

• 30% below ASHRAE/

IESNA Standard 90.1‐

• Section 104:

procurement consistent with Energy Star

Measurement & Verification ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Annual reporting Meter all utilities, including natural gas and steam

• Install building level utility meters

• Enter data into the HPB database (FEMP)

Section 103, requires all federal agencies to install metering and advanced metering where found to be cost‐ effective

Benchmarking ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Yes Verify building meets design target after 1 year

Commissioning Yes Yes Yes Yes Yes ‐‐‐‐‐‐‐

RENEWABLE ENERGY For FY2013 and beyond, renewable energy is

7 5% of electricity consumption

Implement renewable energy generation projects on agency property for agency use to extent feasible

Implement renewable energy generation projects on agency property for agency use, when LCC effective

(Section 523) 30% of hot water demand from solar hot water, when

LCC effective

• 30% of hot water demand from solar hot, when LCC effective

• Renewable energy per

EO 13423

7 5% produced and used on a federal facility

WATER CONSERVATION

Reduce Potable Water Use 26% (FY2020)

Reduce potable intensity

(gal/sf) by 2% annually, compared to FY2005

• ≥ 12% below 2007 baseline (for 2013 delivery date) (2% ↑ per year)

• Water‐efficient and low‐flow fixtures

• efficient cooling towers

12% below 2007 baseline (for 2013 delivery date)

‐‐‐‐‐‐‐ • Indoor water: 20% below building baseline after meeting EPACT

1992, UPC/IPC 2006

fixture performance requirements.

• Water meters encouraged

• WaterSense products

• Reuse (harvested rainwater, treated wastewater, AC condensate) should be used where feasible

IRRIGATION

Reduce industrial, landscaping, and agricultural water use

20% (FY2020)

Reduce use by 2% annually, compared to

FY2010)

6% below 2010 baseline

(for 2013 delivery date)

50% ‐‐‐‐‐‐‐ • 50% below baseline

(conventional means)

• Water meters encouraged

• Use WaterSense certified contractors

STORMWATER RUNOFF ‐‐‐‐‐‐‐ Per EISA 2007 Section

‐‐‐‐‐‐‐ Restore the predevelopment hydrology of the site to maximum extent technically feasible

(METF)

• Employ design and construction strategies to reduce stormwater runoff and polluted site runoff

• Restore the predevelopment hydrology of the site to

METF

FEDERAL SUSTAINABLE REQUIREMENTS

NASA FEDERAL SUSTAINABILITY METRICS

NASA SSPP (FY 2013) EO 13514 EO 13423 EISA 2007 HPSB MOU EPACT 2005

INDOOR ENVIRONMENTAL QUALITY

Ventilation & Thermal Comfort ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Meet ASHRAE 55‐2004 and ASHRAE 62.1‐2007

Moisture Control ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Establish and implement a moisture control strategy to prevent building damage and mold contamination

Daylighting ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Daylight factor of 2%

(excluding direct sunlight) in 75% of all occupied spaces OR lighting controls for 50% of regularly occupied spaces

Lighting Controls ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Yes ‐ automatic dimming or accessible manual controls; and glare control

Low‐Emitting Materials ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Yes (adhesives, sealants, paints, carpet systems, and furnishing)

IAQ during Construction ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ • Follow SMACNA 2007 guidance

• Conduct a minimum 72 hour flush‐out, with RH ≤

60%

• After occupancy, continue flush‐out as necessary

Environmental Tobacco Smoke

Control

‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Prohibit smoking w/n building and w/n 25 ft of entrances & intakes

RECYCLED CONTENT ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ • Use products that meet or exceed EPA's recycled content recommendations

• Sum of post‐consumer plus 1/2 pre‐consumer content ≥10% of the total value of materials for the project

WASTE MANAGEMENT

Divert Construction Waste 50% ≥ 50% by 2015 ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ≥ 50% ‐‐‐‐‐‐‐

BIOBASED CONTENT Yes

Biobased Products ‐‐‐‐‐‐‐ 95% of new contract actions for products and services are bio‐based, where they meet performance requirements

Agency level: Acquire and use bio‐based products and services

‐‐‐‐‐‐‐ • For USDA‐designated products, ≥ USDA's biobased recommendations

• Other: use biobased from rapidly renewable materials

Certified Sustainable Wood ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Yes ‐‐‐‐‐‐‐

OZONE DEPLETING COMPOUNDS ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐ Eliminate use of ozone depleting compounds, consistent with the

Montreal Protocol and

Title VI of the Clean Air

Act Amendments of

THIRD PARTY CERTIFICATION (TPC) Required: Silver

Goal: Gold