ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_1_COMPILED_final.pdf

PDF 4 MB Posted

Attached to
Construction of a Instrument Development Facility Federal contract opportunity
Solicitation number
NNG17607163R
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

ATTACHMENT 1 NASA IDF FINAL Specifications Vol 1 COMPILED

View the file

Other files for this federal contract opportunity

Other files attached to Construction of a Instrument Development Facility, newest first.
File Type Posted
IDF_Selection_Statement_Signed.pdf PDF
20171214_Perf_Drain_System_and_Waterproofing.pdf_--_kms.pdf PDF
IDF_Amendment_0007.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_MH-101_-_FIRST_FLOOR_MECHANICAL_HVAC_PLAN_revised.pdf_kms2.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_M-801_-_MECHANICAL_SCHEDULES_revised.pdf_-_kms.pdf PDF
NASA_GSFC_IDF_Amendment_0006.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_05_93_revised.pdf_-_kms.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_M-801_-_MECHANICAL_SCHEDULES_revised.pdf_-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_22_26_revised.pdf_-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_22_13_revised.pdf_-_kms.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_NASA_-_Sheet_-_MH-101_-_FIRST_FLOOR_MECHANICAL_HVAC_PLAN_revised-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_00_00_revised.pdf_-_kms.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_Section_23_22_25_revised.pdf_-_kms.pdf PDF
IDF_RFP_No._80GSFC17R0009_-__Amendment_0005.pdf PDF
NASA_IDF_Duct_Tables.pdf PDF
IDF_RFP_Amendment_0004.pdf PDF
IDF_RFP_No._80GSFC17R0009_Amendment_0003.pdf PDF
QL_drawings_Showing_Furniture_for_Installation_TS.pdf PDF
Section_09_06_90_Attachment_A__Finish_Legend_Alternatives_Inspected_TS.pdf PDF
Attachment_2_Drawings_Informational_Purposes_Only.pdf PDF
Specification_Section_01_33_29_Attachment_2_TPC_Checklist_Inspected_TS.pdf PDF
Specification_Section_01_33_29_Attachment_1_HPSB_Checklist_Inspected_TS.pdf PDF
IDF_Site_Visit_Sign_in_Sheet.pdf PDF
IDF_Site_Visit_Question_and_Answers-Clean.pdf PDF
RFP_No._80GSFC17R0009_IDF_Questions_and_Answers_1-73.pdf PDF
Question_Due_Date_Extension.pdf PDF
IDF_Amendment_0002.pdf PDF
ATTACHMENT_4_General_Wage_Decision_MD170058,_Modification_No._10.pdf PDF
RFP_No._80GSFC17R0009_Amendment_000001.pdf PDF
ATTACHMENT_3_BUILDING_INFORMATION_MODELING_SCOPE_OF_SERVICES_-_Final.pdf PDF
Exhibit_1-Pricing-Cleaned_-_final.pdf PDF
IDF_RFP_Cover_Letter_Scanned_final.pdf PDF
Exhibit_2-Subcontracting_Goals-_Cleaned_-_final.pdf PDF
ATTACHMENT_2_NASA_IDF_FINAL_Drawings_COMPILED_-_final.pdf PDF
SF1442_final.pdf PDF
Goddard_IDF_Site_Visit_Registration_Form_final.pdf PDF
Enclosure_1_-_IDF_QASP-Scanned_-_final.pdf PDF
ATTACHMENT_9_NASA_Instrument_Development_Facility_Geotechnical_Report_-_final.pdf PDF
ATTACHMENT_1_NASA_IDF_FINAL_Specifications_Vol_2_COMPILED_-_final.pdf PDF
IDF_RFP_No._80GSFC17R0009_-_Sections_B-M_FINAL.pdf PDF
ATTACHMENT_8_MDE_Permit_-_Final.pdf PDF
ATTACHMENT_7_PIV_Attachment-Cleaned_-_final.pdf PDF
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NASA Goddard Space Flight Center Final Submission Instrument Development Facility December 8, 2016

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 23 00 ALTERNATES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 34 PRODUCT OUTGASSING REQUIREMENTS FOR CLEANROOM CONSTRUCTION

01 35 43 ENVIRONMENTAL PROCEDURES

01 41 00 SPECIAL INSPECTIONS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 20 CONTRACTOR QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 50 13 GENERAL CLEAN ZONE CONSTRUCTION PROCEDURES

01 56 39 TEMPORARY TREE AND PLANT PROTECTION

01 58 00 PROJECT IDENTIFICATION

01 65 00 PRODUCT DELIVERY AND GOMAR TAGS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CONTRACT CLOSEOUT

01 78 23 OPERATION AND MAINTENANCE DATA

01 81 21 INDOOR AIR QUALITY MANAGEMENT (IAQ) DURING CONSTRUCTION

01 81 22 INDOOR AIR QUALITY PROTECTION BEFORE OCCUPANCY

01 86 12 RELIABILITY CENTERED ACCEPTANCE FOR MECHANICAL SYSTEMS

01 91 13 GENERAL COMMISSIONING REQUIREMENTS

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 MASONRY

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED STUD FRAMING

05 45 23 CHANNEL SUPPORT GRID SYSTEM (CSGS)

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

05 72 00 DECORATIVE METAL SPECIALTIES - BUILDING ID NUMBERS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 41 16.00 10 LAMINATE CLAD ARCHITECTURAL CASEWORK

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

PROJECT TABLE OF CONTENTS Page 1

07 11 13 BITUMINOUS DAMPPROOFING

07 17 00 BENTONITE WATERPROOFING

07 21 13 BOARD INSULATION

07 21 16 BLANKET INSULATION

07 22 00 ROOF AND DECK INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 18 SELF-ADHERING AIR BARRIER - VAPOR PERMEABLE

07 42 13 PREFORMED AND COMPOSITE METAL WALL PANELS

07 44 53 GLASS-FIBER-REINFORCED CONCRETE COLUMN COVERS (GFRC)

07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING

07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING

07 60 00 FLASHING AND SHEET METAL

07 81 00 SPRAY-APPLIED FIREPROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS

08 14 00 WOOD DOORS

08 33 23 OVERHEAD COILING DOORS

08 41 13 INTERIOR ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES

08 71 00 DOOR HARDWARE

08 71 13 AUTOMATIC SWINGING DOOR OPERATORS

08 81 00 GLAZING

08 84 14 RESIN PANELS (ER-1)

08 91 00 METAL LOUVERS

DIVISION 09 - FINISHES

09 06 90 FINISH LEGEND ALTERNATES

09 22 00 SUPPORTS FOR GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 13 CERAMIC TILING / PORCELAIN TILE (CT-1, CT-4, CT-5, CT-6,

CT-7)

09 51 00 ACOUSTICAL CEILINGS TYPES (ACT-1, ACT-2)

09 61 10 CONCRETE FLOOR TREATMENT (SC)

09 62 38 STATIC-CONTROL FLOORING TYPES - RUBBER (RS-2)

09 65 00 RESILIENT FLOORING TYPES - RUBBER SHEET (RS-1, RS-2),

LINOLEUM SHEET (RF-1, RF-2), AND RUBBER TREAD, RISER AND

LANDINGS (RT-1)

09 66 16 TERRAZZO FLOOR TILE (TT-2, TT-3)

09 67 23.13 RESINOUS FLOORING (RES-1)

09 83 13 WALL TREATMENT PANELS (AWP-1)

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 10 00 VISUAL COMMUNICATIONS SPECIALTIES TYPES - WALL PANEL

SYSTEM WITH BACKPAINTED WRITABLE/MAGNETIC GLASS (WG-01),

BACKPAINTED GLASS BACKSPLASH (WG-02), RAIL AND CABLE

DISPLAY SYSTEM

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 26 13 CORNER GUARDS (CG)

10 28 13 TOILET ACCESSORIES

PROJECT TABLE OF CONTENTS Page 2

10 44 16 FIRE EXTINGUISHERS (FE) AND CABINETS (FEC)

DIVISION 11 - EQUIPMENT

11 13 10 DOCK LEVELERS AND BUMPERS

11 52 00 AUDIO VISUAL EQUIPMENT

11 53 13 LABORATORY FUME HOOD AND EXHAUST DEVICES

11 53 33 LASER SAFETY EQUIPMENT

11 53 43 LABORATORY SERVICE FITTINGS AND FIXTURES

DIVISION 12 - FURNISHINGS

12 24 13 ROLLER WINDOW SHADES TYPES - MOTORIZED SOLAR SHADES

(WS-1, WS-2)

12 35 53 LABORATORY CASEWORK AND OTHER FURNISHINGS

12 36 65 ENGINEERED QUARTZ FABRICATIONS (QUARTZ COUNTERTOPS, SS-1)

12 48 13 ENTRANCE MATS (MAT-1)

12 93 00 SITE FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

13 60 13 CLEAN ZONE CONSTRUCTION REQUIREMENTS

13 60 16 CLEANROOM PROTOCOL AND CLEANING

13 60 19 CLEANROOM CERTIFICATION

13 61 19 CLEANROOM PASS-THROUGH (CPT)

13 62 13 CLEANROOM GASKETED T-GRID CEILING SYSTEMS (CRCS)

13 62 33 CLEANROOM FAN FILTER UNITS (FFU)

DIVISION 14 - CONVEYING EQUIPMENT

14 24 00 HOLELESS HYDRAULIC ELEVATORS

DIVISION 21 - FIRE SUPPRESSION

21 13 00.00 40 FIRE-SUPPRESSION SPRINKLER SYSTEMS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 07 19.00 40 PLUMBING PIPING INSULATION

22 14 29.00 40 SUMP PUMPS

22 15 14.00 40 GENERAL SERVICE COMPRESSED-AIR SYSTEMS, LOW PRESSURE

22 63 13 SPECIALTY GAS SYSTEMS

22 63 21 LIQUID NITROGEN PIPING SYSTEM

22 63 80 HIGH PURITY STAINLESS STEEL PIPING SYSTEMS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 COMMON PIPING FOR HVAC

23 05 48 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 08 00 COMMISSIONING OF HVAC SYSTEMS

23 09 23 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC

23 09 53 SPACE TEMPERATURE CONTROL SYSTEMS

23 21 13 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM

PROJECT TABLE OF CONTENTS Page 3

23 22 13 STEAM TRAPS

23 22 23 STEAM CONDENSATE PUMPS

23 22 25 STEAM VALVES

23 22 26 STEAM SYSTEM AND TERMINAL UNITS

23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS

23 64 26 CHILLED WATER PIPING SYSTEMS

23 84 23 CLEAN STEAM GENERATOR

DIVISION 26 - ELECTRICAL

26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 71 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES

26 08 00 APPARATUS INSPECTION AND TESTING

26 09 23.00 40 LIGHTING CONTROL DEVICES

26 11 16 SECONDARY UNIT SUBSTATIONS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 16 PANELBOARDS

26 28 01 COORDINATED POWER SYSTEM PROTECTION

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 33 53.00 20 UNINTERRUPTIBLE POWER SUPPLY (UPS)

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

26 60 13 LOW-VOLTAGE MOTORS

DIVISION 27 - COMMUNICATIONS

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 73 AIR ASPIRATING SMOKE DETECTION SYSTEMS

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

31 11 00 CLEARING AND GRUBBING

31 32 11 SOIL SURFACE EROSION CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 10 00 BITUMINOUS CONCRETE PAVEMENT

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

32 17 23.00 20 PAVEMENT MARKINGS

32 84 24 TEMPORARY IRRIGATION SPRINKLER SYSTEMS

32 92 19 SEEDING

32 93 00 EXTERIOR PLANTS

32 94 00 PLANTING ACCESSORIES

DIVISION 33 - UTILITIES

33 11 00 WATER DISTRIBUTION

33 30 00 SANITARY SEWERS

PROJECT TABLE OF CONTENTS Page 4

33 40 00 STORM DRAINAGE UTILITIES

33 46 16 SUBDRAINAGE SYSTEM

33 60 01 VALVES, PIPING, AND EQUIPMENT IN VALVE MANHOLES

33 61 00 UNDERGROUND CHILLED WATER DISTRIBUTION

33 63 13 UNDERGROUND STEAM DISTRIBUTION SYSTEM

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

SECTION 01 11 00

SUMMARY OF WORK

01/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED (2009) Leadership in Energy and Environmental Design(tm) Green Building Rating System for New Construction

(LEED-NC)

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Division 01 Section 01 33 00 "Submittal Procedures":

SD-01 Preconstruction Submittals

Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance with paragraph entitled, "Government Furnished Property," of this section.

Submit the following items to the Contracting Officer:

Utility Outage Requests; G

Utility Connection Requests; G

Borrow Permits; G

Excavation Permits; G

Hot Work Permits; G

Energy Performance Rating; G

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

The work includes construction of a new 2-story building of approximately 54,000 GSA containing flexible office, office support and laboratories.

The IDF is a steel frame, clear span structure with glass and masonry curtain walls.

SECTION 01 11 00 Page 1

Owner is seeking a LEED Gold designation on the project using the 2009 New ConstructionTM and Major Renovation scoring system.

1.3.2 Location

The work shall be located at the NASA Goddard Space Flight Center, Greenbelt, MD. The exact location will be shown by the Contracting Officer.

1.3.3 Work Hours

Normal duty hours for work shall be from 7:00 a.m. to 3:00 p.m., Monday through Friday. Requests for deviation from normal working hours shall be submitted in writing to the Contracting Officer not less than 3 working days in advance of the proposed work period.

1.4 CONTRACT DRAWINGS

The following drawings accompany this specification and are a part thereof.

Drawing List as per Sheet G001

Sheets 1 through 274

Five sets of full size contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished.

Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.

1.5 PROJECT ENVIRONMENTAL GOALS

Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to product a building that meets the functional program needs and incorporates the principles of sustainability. Specifically:

a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.

b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.

c. Use environmentally preferable products and decrease toxicity level of materials used.

d. Use renewable energy and material resources.

e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended.

Consider the durability, maintainability, and flexibility of building systems.

f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.

SECTION 01 11 00 Page 2

g. Reduce construction waste through reuse, recycling, and supplier take-back.

1.5.1 Independent Verification

1.5.1.1 US Green Building Council (USGBC) - LEED(tm) Rating System

Provide completed project in compliance with USGBC LEED-NC(tm) v3.0 (LEED), level Gold requirements.

1.5.1.2 EPA Energy Performance Rating

Provide work consistent with drawings in order to meet Energy Star in accordance with design.

1.6 OCCUPANCY OF PREMISES

Before work is started, the Contractor shall arrange wit the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.7 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.8 ON-SITE PERMITS

1.8.1 Utility Outage Requests and Utility Connection Requests

Notify the Contracting Officer at least 72 hours prior to starting excavation work. Contractor is responsible for marking and verifying all utilities not marked.

The Contractor shall verify the elevations f existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed. But indicated in locations to be transversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

Work shall be scheduled to hold outages to a minimum.

Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and shall be scheduled outside the regular working hours or on weekends.

Contracting Officer may per utility outages at his discretion.

SECTION 01 11 00 Page 3

Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours.

Requests for utility outages and connections shall be made in writing to the Contracting Officer at least 3 calendar days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.8.2 Borrow Permits, Excavation, Hot Work Permits, and Burning Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Excavation Permits 24 hours prior to work

Hot Water Permits 24 hours prior to work

Permits shall be posted at a conspicuous location in the construction areas.

Burning of trash or rubbish is not permitted.

1.9 LOCATION OF UNDERGROUND FACILITIES

Obtain digging permits prior to start of excavation. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground, where existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.

Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.9.1 Notification Prior to Excavation

Notify the Contracting Officer at least 72 hours prior to starting excavation work.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 CONSTRUCTION AND DEMOLITION (C&D) WASTE PLAN

a. GSFC Executive Order 13693 requires agencies to divert at least 50% of their Construction and Demolition (C&D) waste from landfills to recycling. C&D waste includes products of demolition or removal, excess or unusable construction materials, packaging materials for construction products, and other materials generated during the construction process, but not incorporated into the work.

b. The Contractor shall be required to divert at least 50% (by weight) of the C&D waste from going to a landfill. An exemption for a lower diversion rate shall be allowed if it becomes cost prohibitive to transport the waste a long distance to a recycling center.

Specifically, recycling centers farther than 50 miles from GSFC will

SECTION 01 11 00 Page 4 be considered cost prohibitive.

c. In fulfillment of the requirement, the Contractor shall submit a brief C&D plan. The Plan shall state whether the contractor plans to segregate waste on-site for delivery to recycling centers and landfill, or transport the commingled waste off-site to a segregation facility. The Plan shall name the segregation and recycling facilities. Additionally, the Contractor shall submit a C&D Waste Report annually by November 30. This Report shall give the total tonnage of C&D waste the Contractor generated under this contract. It shall also give the total tonnage sent to a landfill and the total tonnage to various recycling streams (e.g. metal, wood, concrete, asphalt, gypsum, etc). The figures shall be certified (with signature) by the Contractor.

-- End of Section --

SECTION 01 11 00 Page 5

SECTION 01 14 00

WORK RESTRICTIONS

07/07

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Division 01 Section 01 33 00 "Submittal Procedures":

SD-01 Preconstruction Submittals

Contractor regulations; G

Transportation of personnel, materials, and equipment; G

List of Contact Personnel; G

Personnel List; G

Vehicle List; G

Statement of Acknowledgement Form SF 1413; G

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 No Smoking Policy

Smoking is prohibited within and outside of all buildings except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Occupied and Existing Buildings

The Contractor shall be working round existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.

1.2.3 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph "Work Outside Regular Hours."

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire

SECTION 01 14 00 Page 1 alarm, and compressed air shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."

d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 2

SECTION 01 23 00

ALTERNATES

05/16

PART 1 GENERAL

1.1 SUMMARY

Section identifies each Alternate by number and describes basic changes to be incorporated into Work, only when that Alternate is made a part of Work by specific provisions in Construction Contract.

Section includes only nontechnical descriptions of Alternates.

Refer to specific Sections of Specifications and Drawings for technical description of Alternates.

Coordinate related Work, and modify surrounding Work as required to properly integrate Work under each Alternate and to provide complete construction required by Contract Documents.

1.2 DESCRIPTION

1.2.1 Work Includes

a. Indicate Alternate prices on Bid Form.

b. Alternates will be selected after bids are evaluated.

c. Selected Alternates will be made a part of Contract and final Contract Amount will be adjusted accordingly.

1.3 ALTERNATES

Alternate No. 01: Provide "Integrate Low Voltage Distributed Module Lighting Control System" as specified in Section 26 09 23.00 40 and indicated in drawings.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 23 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

02/10

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Division 01 Section 01 33 00 "Submittal Procedures":

SD-01 Preconstruction Submittals

List of contact personnel; G

View location map; G

Statement of Acknowledgement Form SF 1413

1.2 VIEW LOCATION MAP

Submit to the Contracting Officer, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.3 MINIMUM INSURANCE REQUIREMENTS

Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:

a. Comprehensive general liability: $500,000 per occurrence.

b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage.

c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.

d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers.

e. Others as required by Maryland law.

1.4 CONTRACTOR PERSONNEL REQUIREMENTS

1.4.1 Subcontractors and Personnel

Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

SECTION 01 30 00 Page 1

1.4.2 1.4.2 Contractor Personnel Badging

The Contractor shall adhere to the GSFC security requirements specified in

GPR 1600.1A .

Entrance onto the GSFC campus requires a GSFC-issued picture badge, GSFC-issued temporary badge, or accompaniment by a GSFC-issued picture badged escort. The Contractor shall provide an escort to accompany subcontractors working in secure areas. Only contractor personnel in possession of a GSFC-issued picture badge may serve as an escort.

The Contractor shall obtain personnel badges following the requirements listed on the GSFC protective services website located at URL http://protectiveservicesdivision.gsfc.nasa.gov/persec/badging.

1.4.3 Space Temperature Control, HVAC TAB, and Apparatus Inspection

No work required by Section 23 09 53 TESTING, ADJUSTING AND BALANCING FOR HVAC or 26 08 00 APPARATUS INSPECTION AND TESTING shall be accomplished by a second tier subcontractor.

1.4.4 Contractor Personnel Requirements

Failure to obtain entry approval will not affect the contract price or time of completion.

1.4.5 Citizenship Requirements

Comply with citizenship and restridtions for aliens to enter base.

1.4.6 Document Acceptable for Proof of Citizenship

a. Birth registration card

b. Certificate of live birth, birth certificate

c. Certificate of Naturalization

d. Certificate of registration

e. DD-214 (Must Cite Birthplace)

f. DD Form 4 (Contract for Enlistment and Must Cite Birthplace)

g. DD 1966 (Application for Enlistment)

h. Military discharge papers (must cite birthplace)

i. Delayed birth certificate

j. Hawaii certificate of foreign birth

k. Hospital birth certificate

l. Marriage license certificate

m. Merchant marine certificate

n. Military officer ID card

SECTION 01 30 00 Page 2

o. Notification of birth registration

p. State of Hawaii ID card

q. USA passport

r. Verbal inquiry with State of Hawaii Vital Statistics Office

1.4.7 Passes

Submit request for personnel and vehicle passes together. Include the Certificate of Insurance for Contractor and Subcontractor(s) and the Statement of Acknowledgement Form SF 1413 with the submittal. Passes will normally be issued within 21 days.

1.5 SUPERVISION

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.

1.6 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming and prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.

1.7 PARTNERING

LEVEL A PARTNERING: To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership with the Contractor and its subcontractors. Key personnel, including the client who will occupy the facility, the designer-of-record, principal individuals from the activity contracting office, the project sponsor, and representative(s) of the facility owner will be invited to participate in the partnering process. Key members of the prime and subcontractors teams, including senior management, must participate. The partnership will draw on the strength of each organization in an effort to achieve a quality project done right the first time, within budget, on schedule, and without any safety mishaps. The initial session will be one-day minimum and the follow-on sessions, held at a minimum of once every three months or as agreed to by the partners, will be half-day minimum. The initial partnering session should be held away from the project site at a location acceptable to the Contractor and to the Government; the follow-on sessions can be held at locations agreed to by the partners. The contractor shall pay all costs associated with the partnering effort including facilitator, meeting room and other incidental items. Before the partnering session, the contractor shall coordinate with the facilitator requirements for incidental items (audio-visual equipment, two easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards, etc.) and have these items available at the partnering session. The contractor will copy documents for distribution to all attendees. The facilitator must be

SECTION 01 30 00 Page 3 acceptable to both the Contractor and the Government. The participants shall bear their own costs for meals, lodging and transportation associated with partnering.

1.8 AVAILABILITY OF CADD/BIM DRAWING FILES

After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files and BIM model will only be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions.

Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic CADD drawing files are not construction documents.

Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

1.9 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats.

Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.

Multiple email address will not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including

SECTION 01 30 00 Page 4 field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 5

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Division 01 Section 01 33 00 "Submittal Procedures":

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

Baseline Network Analysis Schedule (NAS); G

SD-07 Certificates

Monthly Network Analysis Updates; G

SD-11 Closeout Submittals

As-Built Schedule; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of

SECTION 01 32 01.00 10 Page 1 reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project, including 3 previous schedules of similar size and complexity of this contract. At least one of the three must be in Primavera P6. Submit a resume outlining the qualifications of the Scheduler. Payment will not be processed until an acceptable Scheduler is provided. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

1.4 SCHEDULE ACCEPTANCE PRIOR TO START OF WORK

Participate with the Contracting Officer in a preliminary meeting(s) to discuss the proposed schedule and requirements of this section prior to the Contractor preparing the Project Baseline Schedule. Government review comments on the Contractor's schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents. Only bonds may be paid prior to acceptance of the Baseline Network Analysis Schedule (NAS) The acceptance of a Baseline NAS is a condition precedent to:

a. The Contractor starting work on the demolition or construction stage(s) of the contract.

b. Processing Contractor's invoices(s) for construction activities/items of work.

c. Review of any schedule updates.

Submittal of the Baseline Network Analysis Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

SECTION 01 32 01.00 10 Page 2

A listing of Primavera P6 settings and parameters which must be used in preparing the Schedules are contained later in this specification section. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development.

Subcontractors and suppliers Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

The schedule is a tool to manage the project, both for Contractor and Government activities. It will also be used to report progress and evaluate time extensions. The Project NAS must be cost-loaded and will provide the basis for progress payments. Use the Critical Path Method (CPM) and the Precedence Diagram Method (PDM) to satisfy time and cost applications. For consistency, when scheduling software terminology is used in this specification, the terms in Primavera's scheduling programs are used.

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN, where CLINS are identified, must equal the value of the CLIN.

The value of commissioning, inspection/testing and closeout may not be less than 10 percent of the total costs for Procurement and Construction Activities. Evenly disperse overhead and profit to each activity over the duration of the project.

Each cost loaded activity must have a detailed quantity breakdown and unit of measure. Lump sum costing is not acceptable unless approved by the Contracting Officer.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

SECTION 01 32 01.00 10 Page 3

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

Within the Baseline Schedule no more than 20 percent of the activities shall be critical or near critical. Critical is defined as having zero days of Total Float. "Near Critical" is defined as having Total Float of 1 to 14 days. Contractor activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Design and Permit Activities

Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. Provide at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work.

Also include review and correction periods associated with each item.

3.3.4 Procurement Activities

Examples of procurement activities include, but are not limited to;

Material/equipment submittal preparation, submittal and approval of material/equipment; material/equipment fabrication and delivery, and material/equipment on-site. As a minimum, separate procurement activities will be provided for critical items, long lead items, items requiring Government approval and material/equipment procurement for which payment will be requested in advance of installation. Show each delivery with relationship tie to the Construction Activity specifically for the

SECTION 01 32 01.00 10 Page 4 delivery.

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.5 Quality Management (QM) Activities

The Preparatory Phase and Initial Phase for each Definable Feature of Work identified in the Contractor's Quality Control Plan must be added to each Three-Week Look Ahead Schedule referenced in the paragraph THREE-WEEK LOOK AHEAD SCHEDULE. The Follow-up Phase will be represented by the Construction Activities in the Baseline Schedule and in the schedule updates.

3.3.6 Construction Activities

No on-site construction activity may have a duration in excess of 20 working days. Contractor activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days, unless otherwise defined in this contract.

3.3.7 Turnover and Closeout Activities

Include all testing, specialized inspection activities, Pre-Final Inspection, Punch List Completion, Final Inspection and Acceptance. Add a milestone for the Facility Turnover Planning Meeting at approximately 75 percent construction contract completion or three to six months prior to Contract Completion Date (CCD), whichever is sooner.

3.3.8 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion Submission, review and acceptance of design packages.

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

j. Submission and approval of fire protection specialist.

SECTION 01 32 01.00 10 Page 5

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

w. Project closeout submissions.

x. Modifications: Create multiple sub-sections as the project progresses identified by modifications issued.

3.3.9 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections/tests, utility tie-in, utility outages, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.10 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. All Activity Codes shall be developed and assigned to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .

The SDEF format is as follows:

SECTION 01 32 01.00 10 Page 6

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.10.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day shall be the average number of workers expected each day to perform a task for the duration of that activity.

3.3.10.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.10.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

SECTION 01 32 01.00 10 Page 7

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.10.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.10.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.10.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are design phase, procurement phase, and construction phase. procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.10.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to design, design submittal, design reviews, review conferences, permits, construction submittals, construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities.

Each activity can have no more than one Category of Work Code.

3.3.10.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 20 CONTRACTOR QUALITY CONTROL. An activity can have only one Feature of Work Code.

3.3.11 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

SECTION 01 32 01.00 10 Page 8

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.3.11.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.11.2 Substantial Completion Milestone

Include an unconstrained finish milestone on the schedule titled "Substantial Completion". Substantial Completion is defined as the point in time the Government would consider the project ready for beneficial occupancy wherein by mutual agreement of the Government and Contractor, Government use of the facility is allowed while construction access continues in order to complete remaining items (e.g. punch list and other close out submittals).

3.3.11.3 Projected Completion Milestone

Include an unconstrained finish milestone on the schedule titled "Projected Completion". Projected Completion is defined as the point in time the Government would consider the project complete. This milestone must have the End Project milestone as its only successor.

3.3.11.4 End Project Finish Milestone and Constraint

The last activity in the schedule shall be a finish milestone titled "End Project."

The project schedule must be constrained to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.